14.E.
Chapter 11 Library Facilities and Collections
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report those residents. Because the empirical demand is resident-based, the fee applies to residential development only.
4. Relationship Between the Need for Facilities and the Type of Development The need for expanded library facilities and collections arises directly from new residents generated by residential development. The program maintains the City’s adopted service standards—0.550 SF per resident for buildings and 1.115 units per resident for collections— and applies them to growth to determine the additional capacity required to keep service whole for both new and existing residents. In effect, the required building area equals netnew residents multiplied by 0.550 SF per resident, and the required collections equal netnew residents multiplied by 1.115 units per resident. These needs are attributable solely to residential growth and exclude backlog, maintenance, and like-for-like replacements.
5. Relationship Between the Amount of the Fee and the Cost Attributable to Development The fee amount is derived by converting each housing type’s projected demand—measured through persons-per-household and the City’s adopted service standards for buildings and collections—into a per-dwelling cost, and then expressing that amount per square foot of residential �loor area using the housing type’s average unit size (AB-602). This method ties each category’s charge directly to the incremental building space and collection units needed to serve its new residents. The resulting per-SF schedule is $0.655/SF for Single-Family Residential, $1.285/SF for Multiple-Family Residential, and $0.538/SF for Mobile Home Dwelling Units, ensuring no housing type is charged more than the cost attributable to the demand it creates.
Implementation Notes
Timing of Payment (Residential): Payment timing conforms to Gov. Code §66007. Fees are collected at building permit unless otherwise provided by ordinance or agreement; the City may allow payment at �inal inspection/certi�icate of occupancy or earlier by agreement.
References
City of Hemet. (2025). Statement of Values — Insured Property Schedule (FY 2025–26). Hemet: City of Hemet.
End of Chapter
197
14.E.
Chapter 12
Parkland and Open Space Acquisition
and Facilities Improvements
Purpose and Scope
Purpose: Update the City’s existing Parks development impact fee (DIF) under the Mitigation Fee Act (AB-1600; Gov. Code § 66000 et seq.) so new residential development continues to fund its fair, proportional share of (a) parkland acquisition and (b) capacity-adding park improvements needed to maintain the City’s existing level of service (LOS) as population grows; establish a new Open Space component (land-only acquisitions for access/corridors; any activation improvements are funded under Parks); and continue the Regional Park participation by allocating a �ixed 16.3% share of Parks DIF receipts to the Valley-Wide Recreation & Park District for capacity-enhancing improvements at Diamond Valley Lake Community Park. Consistent with AB-602, residential fees are expressed on a per square foot basis using the City’s adopted demographic and land use inputs. Quimby Act (Gov.
Code § 66477) subdivision dedication and in-lieu requirements—if and where adopted by City ordinance—are recognized and administered separately and credited �irst to avoid double-counting.
The Regional Park facility is tracked in a separate sub-ledger, excluded from the City’s park inventory and LOS, and treated as proportional participation rather than City-owned acreage.
Scope of Improvements:
Parks (Parkland & Park Improvements): Eligible capital uses include parkland acquisition; planning, design, and permitting; site preparation and capacity-adding improvements such as multipurpose turf and hardscape areas, courts and �ields, destination playgrounds, restrooms and support buildings, lighting and fencing, internal paths and trailheads, and on-site accessibility upgrades necessary to place new capacity into service.
Open Space (Acquisition / Protection): Eligible uses include acquisition or protection of recreation-supporting open spaces, such as linear greenways and off-street trail corridors, to maintain the City’s open space standard. Open space sites must be suitable for recreation or park use to qualify under this fee. Improvements that activate or enhance open space areas (e.g., paving, lighting, way�inding) are funded under the Parks component rather than the Open Space fee, consistent with land-only treatment for open space acquisitions.
Regional Park Participation: The Regional Park component continues the City’s participation in the Valley-Wide Recreation & Park District’s Diamond Valley Lake Community Park. A �ixed 16.3% of Parks DIF receipts is allocated annually to the District for capacity-enhancing improvements at this regional facility. The Regional Park Fund is tracked in a separate sub-ledger (Fund 362) under AB1600 reporting, ensuring transparency and preventing commingling with City-owned park revenues.
Quimby (Subdivision) Dedication / Fee: For subdivisions, the City may require land dedication and/or in-lieu fees under the Quimby Act (Gov. Code § 66477). Quimby funds may be used to develop new or rehabilitate existing neighborhood or community park and recreation facilities that serve the 198
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report subdivision. Quimby may also be used to help remedy existing park de�iciencies only where statutory conditions are met—such as indings of de�iciency in the receiving area, a public hearing demonstrating foreseeable use by subdivision residents, and consistency with adopted plans and service radii. Quimby is administered separately from the AB-1600 Parks and Open Space fees, with credit order and eligible-cost rules de�ined later to avoid double-counting.
Scope of Bene�iciaries: This program is resident-based for Parks and applies to residential development citywide. Fees are assessed per square foot of residential �loor area consistent with AB602. For mixed-use projects, assessments are applied by category, and only the residential component is subject to the Parks fee. Residential categories include Single-Family Residential, Multiple-Family Residential, and Mobile Home Dwelling Units. Because Parks facilities function as a citywide system, improvements funded by this program bene�it both new and existing residents, maintaining a consistent level of service across all neighborhoods.
The Open Space component applies to both residential and nonresidential development.
Residential Open Space fees are expressed per square foot using the City’s open space standard and cost factors.
Nonresidential Open Space contributions are expressed per square foot by land use category (and, where appropriate, per Room for Commercial Lodging Rooms) and are administered alongside—but accounted separately from—the Parks fee to prevent double-counting. Open Space improvements provide recreation access, trail linkages, and connectivity serving the community as a whole.
Scope of Nexus:
Parks (Resident-Based): New dwelling units generate net-new residents, and those residents require added park capacity to maintain the City’s existing level of service (LOS). Net-new residents are calculated by multiplying new dwelling units by the applicable persons-per-household (SingleFamily Residential: 3.461; Multiple-Family Residential: 2.728; Mobile Home Dwelling Units: 1.541).
Required park acreage is then determined by applying the adopted acres-per-1,000-residents standard to the net-new residents. That acreage is priced using the City’s unit costs per acre for land and improvements to produce a cost per resident. The result is translated to cost per square foot by dividing by the average dwelling square footage for each housing type, using the dwelling size assumptions established in Chapter 2 and summarized in Use in Calculations. For mixed-use development, the calculation applies only to the residential component.
Open Space (Residential & Nonresidential): Residential Open Space follows the same residentbased method described above, using the City’s open space standard (acres per 1,000 residents) and the open space land-only unit cost per acre to derive cost per resident, cost per unit, and cost per square foot by housing type based on the applicable persons-per-household and average dwelling square footage.
Nonresidential Open Space is expressed as dollars per square foot by dividing the open space cost per developed acre by the average existing square feet per developed acre for each nonresidential land use category, with a per Room expression for Commercial Lodging Rooms where appropriate. In 199
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report all cases, costs allocated to development are proportional to the demand created by that development and are expressed on a per square foot basis where applicable, consistent with AB-602.
Regional Park Participation (Proportional Share): The regional component is not part of the City’s park acreage or LOS. Instead, the City participates through a �ixed 16.3% allocation of Parks DIF receipts for capacity-enhancing improvements at the regional facility operated by the Valley-Wide Recreation & Park District. This is a proportional-participation nexus rather than an acreage-based standard; funds are restricted to capital improvements that expand usable recreation capacity serving City residents.
Existing System
This section establishes the baseline park and open space system used to evaluate the City’s level of service (LOS) and to derive the fee. It documents current inventories, states how LOS is measured, and explains how existing capacity represented by fund balances is treated in the calculations.
Park Inventory: The City’s park system inventory is documented in Table 12-1, which lists each site and shows park type, developed and undeveloped acreage, core amenities, and notes relevant to eligibility and project scoping. This inventory re�lects the City’s current holdings and is used to benchmark the LOS that new development must maintain. The City’s LOS for parks is measured in acres per 1,000 residents, and the inventory in Table 12-1 establishes the baseline for that standard.
Table 12-1
Total Park Inventory
Park Name Acres
Weston Park 4.000
Gibbel Park 11.000
Mary Henley Park 16.000
Spencer Park 0.500
Brubaker Park 60.000
Stoney Mountain Park 7.000
Dave Oltman Park 6.000
Cawston Community Park 0.840
Griffith Way Park 0.210
Welch Memorial Green 0.320
Rodighier Green 0.200
Total 106.07 Acres
Open Space Inventory: Open space resources used for recreation access and connectivity (e.g., greenways and off-street trail corridors) are documented separately. Open space is treated as landonly under this program; activation improvements (paving, trailheads, lighting, way�inding) are funded under the Parks component when they add usable capacity. 200
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Table 12-2
Open Space Inventory
Simpson Park 483.5
Total 483.5 Acres
Treatment of Existing Capacity and Fund Balances:
• City Parks balances: The existing Parks DIF fund balance of $3,310,852 is applied as a direct cost deduction from the gross program cost, reducing the net amount charged to new development. The fund balance acres are excluded from the physical inventory so the level of service standard re�lects only physical parkland. New development is not charged for capacity already funded through prior collections.
• Regional Park participation: The Valley-Wide regional facility (Diamond Valley Lake Community Park) is not included in the City’s park acreage or LOS. The City participates through a �ixed 16.3% share of Parks DIF receipts for capacity-enhancing improvements at that facility; amounts are disclosed for transparency and tracked in a separate accounting line, but they do not offset the City’s LOS calculations.
Current Level of Service: LOS is measured as acres per 1,000 residents. Using the inventories summarized in Table 12-1 (Parks) and Table 12-2 (Open Space), and the current resident population of 89,663, the City’s baseline LOS is established separately for Parks and for Open Space (land-only).
The regional facility (Diamond Valley Lake Community Park) is excluded from the City’s park acreage and LOS because it is operated by the Valley-Wide Recreation & Park District and treated as proportional participation rather than City-owned capacity. The fee program is designed to maintain these existing service levels as growth occurs, consistent with the standards adopted in this chapter; LOS will be recalibrated in future updates when the City adopts new population or inventory data.
For Open Space (land-only), the baseline standard is derived as 483.5 acres of Open Space (Table 12- 2) divided by the current resident population of 89,663, expressed per 1,000 residents: 483.5 ÷ (89,663 ÷ 1,000) = 5.392 acres per 1,000 residents.
Standards & Application:
This chapter uses two complementary tracks for Parks and a uni�ied approach for Open Space. For Parks, the non-subdivision impact fee follows the Mitigation Fee Act and is expressed per square foot under AB-602; for subdivisions, the City administers Quimby dedication or in-lieu fees separately.
Open Space applies to both residential and nonresidential development and is stated as dollars per square foot, with residential rates set by housing type and nonresidential rates set by land use category.
For all resident-based parkland standards in this chapter, including Parks (non-subdivision, AB1600), Parks (subdivision, Quimby), and Residential Open Space, demand is calculated by �irst translating new dwelling units into residents using persons-per-household assumptions. Net-new 201
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report residents are calculated by housing type as the number of new dwelling units multiplied by the applicable persons-per-household (Single-Family Residential: 3.461; Multiple-Family Residential:
2.728; Mobile Home Dwelling Units: 1.541). The applicable service standard, expressed in acres per 1,000 residents, is then applied to the resulting population to determine the amount of parkland required to serve new development. While these resident-based standards share a common approach for calculating service demand, they differ in how the resulting acreage requirement is implemented, as described in the subsections below.
Parks standard — Non-Subdivision (AB-1600): The study uses a service standard of 1.183 acres per 1,000 residents. The standard is applied to net-new residents to determine required acres, which are then costed and translated to cost per resident, cost per unit (using persons-per-household for Single-Family Residential, Multiple-Family Residential, and Mobile Home Dwelling Units), and �inally to cost per square foot using average dwelling square footage, consistent with AB-602. For mixed-use development, the calculation applies only to the residential component.
Parks standard — Subdivision (Quimby Dedication/Fee): For subdivisions, the City may require land dedication and/or in-lieu fees under the Quimby Act using 3.000 acres per 1,000 residents standard. Quimby is administered separately from the non-subdivision impact fee. Dedications and fees are credited in accordance with the credit and sequencing rules in the Fee Derivation section to avoid double-counting. Where statutory conditions are met, Quimby revenue may be used to develop new or rehabilitate existing neighborhood or community park and recreation facilities that will serve the subdivision.
Open Space Standards and Expressions: Residential Open Space follows the same resident-based method used for Parks. The City’s open space standard (5.392 acres per 1,000 residents), derived from the Current Level of Service using Table 12-2, is applied to net-new residents to determine required open space acreage, which is then priced using the land-only unit cost per acre to derive a cost per resident. That cost is translated to a cost per unit by housing type using the applicable persons-per-household and, consistent with AB-602, converted to a cost per square foot by dividing by the average dwelling square footage for each housing type.
For nonresidential development, Open Space impacts are expressed as dollars per square foot by dividing the open space cost per developed acre by the average existing square feet per developed acre for each land use category; where appropriate, Commercial Lodging Rooms may be expressed on a per Room basis. The nonresidential intensity basis uses 0.0815 acres of Open Space per privately held developed acre, calculated as 483.48 acres of Open Space divided by 5,933.68 privately held developed acres, ensuring proportional allocation across nonresidential land uses.
Application Rules: Fees are assessed on a per square foot basis for residential, consistent with AB602, using housing-type-speci�ic persons-per-household and the average dwelling unit sizes stated in the Use in Calculations section. Mixed-use projects are assessed by category; only the residential portion is subject to the Parks residential fee, and Open Space applies to residential and nonresidential components as speci�ied above. Change-of-use and additions are assessed on the net increase in impact. Quimby applies only to subdivisions and is administered separately from the nonsubdivision impact fee, with clearly de�ined crediting to prevent double-counting. 202
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Growth and Demand
This section quanti�ies the additional system capacity required to maintain the City’s adopted levels of service as development occurs. It applies the study standards to net-new demand and identi�ies the resulting capacity for Parks and Open Space. The regional facility (Diamond Valley Lake Community Park) is excluded from LOS and continues to be addressed through the �ixed 16.3% participation framework.
Parks: Applying the adopted service standard of 1.183 acres per 1,000 residents to the net-new residential population of 40,756 yields a gross growth requirement of 48 acres of additional park capacity (calculation: 40,756 × 1.183 ÷ 1,000 = 48.214 → 48, rounded to whole numbers per project conventions). This gross acreage represents the capacity needed to maintain the City’s existing level of service as development occurs. The existing Parks DIF fund balance of $3,310,852 is deducted from the gross program cost in the capital program accounting, yielding a net DIF-eligible cost of $56,957,374 attributable to new development.
Open Space: Residential Open Space needs are derived from the City’s existing Open Space inventory and current resident population (see Current Level of Service and Table 12-2). Applying that standard of 5.392 acres per 1,000 residents to the same net-new residential population of 40,756 produces 220 acres of additional residential open space capacity (calculation: 40,756 × 5.392 ÷ 1,000 = 219.756 → 220, rounded). Nonresidential Open Space impacts are not expressed as acreage; they are derived on an intensity basis as dollars per square foot by dividing the open space cost per developed acre by the average existing square feet per developed acre for each land use category (and, where appropriate, on a per Room basis for Commercial Lodging Rooms). This approach uses the study’s nonresidential intensity factor of 0.0815 acres of Open Space per privately held developed acre and ensures proportional allocation across nonresidential land uses.
Cost Basis
This nexus study adopts planning unit costs and standards anchored to the Valley-Wide Recreation & Park District Master Plan (GreenPlay, LLC & RRC Associates, 2021) and applies them in current studyyear dollars. The cost basis is organized into (1) parkland acquisition (land fair market value (FMV)), (2) park improvements (capacity-adding construction), and (3) Open Space acquisitions (land-only), with regional participation addressed separately. Supporting documentation for the unit-cost benchmarks and planning cost basis used in this chapter is provided in Appendix N (Quality of Life Infrastructure Cost Basis).
Parkland Acquisition (Land Fair Market Value): Parkland land value is established as a planning fair market value (FMV) per acre for fee-simple, park-suitable sites in Hemet. Using the Valley-Wide planning context as the public benchmark and selecting a Hemet-appropriate point within that defensible range, the study sets a planning baseline of $350,000 per acre. This value represents what 203
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report the City would reasonably expect to pay to procure developable park sites (as opposed to encumbered utility strips or easements) and is used solely to price the land component of new park capacity.
Park Improvements (Capacity-Adding Construction): The improvements baseline is derived from the Master Plan’s typical neighborhood/community park program (multi-purpose turf and hardscape areas, courts and �ields, destination playgrounds, restroom/support building, lighting and fencing, internal paths and trailheads, irrigation, and accessibility). Unit costs for these elements are assembled into a prototype build-out and normalized to a per-acre �igure. Excluding operations and maintenance, like-for-like replacement that does not add capacity, programming, and rolling stock, the planning baseline for capacity-adding improvements is $900,000 per acre. This per-acre treatment scales directly with the acreage requirement generated by the level-of-service (LOS) standard.
Open Space (Land-Only) Unit Cost: Open Space is treated as land-only to acquire or protect recreation-supporting corridors (e.g., linear greenways and off-street trail linkages). California planning law generally de�ines “open-space land” as land or water that is essentially unimproved and devoted to open-space use, including natural resources, outdoor recreation, and public health and safety functions. Consistent with that framework, Open Space corridors are often constrained lands (for example, hillside areas, drainage corridors, buffers, or irregular parcels) that support access and resource protection but are not equivalent to park-ready sites intended for active park development.
To re�lect that these parcels typically transact below park-ready sites, the study applies a land valuation factor equal to two-thirds of the parkland land fair market value, resulting in an Open Space unit cost of $233,333 per acre. Any construction needed to activate Open Space corridors (paving, trailheads, lighting, way�inding) is funded under the Parks improvements cost basis when it adds usable capacity.
Use in Calculations: For Parks (non-subdivision, AB-1600), the study applies the adopted LOS of
1.183 acres per 1,000 residents to net-new residents to determine added park acres. Net-new residents are calculated by housing type using persons-per-household (Single-Family Residential:
3.461; Multiple-Family Residential: 2.728; Mobile Home Dwelling Units: 1.541). Required acres are calculated as (net-new residents × 1.183 ÷ 1,000). The study prices parkland at $350,000 (land) + $900,000 (improvements) = $1,250,000 per acre. The AB-1600 cost per 1,000 residents is calculated as ($1,250,000 × 1.183), and the cost per additional resident is that value ÷ 1,000. The cost per additional resident is then multiplied by the applicable persons-per-household to derive cost per unit by housing type. For purposes of converting cost per unit to cost per residential square foot, the study uses average dwelling unit sizes of 2,304 square feet for Single-Family Residential, 926 square feet for Multiple-Family Residential, and 1,250 square feet for Mobile Home Dwelling Units, consistent with the residential assumptions used throughout the report. The resulting costs are expressed on a per-square-foot basis, consistent with AB-602.
For Parks (subdivision, Quimby), the study applies the same resident-based approach to determine parkland demand using the Quimby standard of 3.000 acres per 1,000 residents. Required acres are calculated as (net-new residents × 3.000 ÷ 1,000). The same $1,250,000 per acre cost basis is used to translate the acreage requirement into land dedication and/or in-lieu value; however, Quimby is administered separately and does not translate the requirement into a development impact fee. 204
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report For Open Space – Residential, the study applies the resident-based Open Space standard of 5.392 acres per 1,000 residents to net-new residents, calculates required acres as (net-new residents ×
5.392 ÷ 1,000), prices the resulting acres at $233,333 per acre, and translates to cost per resident, cost per unit by housing type using the applicable persons-per-household, and cost per residential square foot using the same average dwelling unit sizes stated above, consistent with AB-602.
For Open Space – Nonresidential, impacts are expressed as $/SF using an intensity method: the Open Space cost per developed acre is divided by the average existing square feet per developed acre for each nonresidential land use category (and, where appropriate, expressed per Room for Commercial Lodging Rooms). The nonresidential intensity basis uses 0.0815 acres of Open Space per privately held developed acre. Regional park participation is addressed separately via the �ixed 16.3% allocation of Parks DIF receipts for capacity-enhancing improvements at the regional facility; it is excluded from the City’s park acreage and LOS.
Indexing: All unit costs are stated in current study-year dollars. The improvement baseline is indexed annually under the City’s construction cost index. Land fair market value (FMV) baselines (parkland and Open Space) are policy values subject to recalibration in future nexus updates when market evidence or adopted planning benchmarks are revised.
Existing Financial Commitment
This section explains how existing fee revenues and credits are treated so that growth pays only its proportional share. Existing balances that have already been collected for Parks are recognized as capacity that is already in hand, and development-provided land or improvements that meet this chapter’s eligibility may receive credits or reimbursement, as applicable, under clear, auditable rules.
Parks Fund Balance Treatment: Existing Parks impact fee balances are converted to a capacityequivalent dollar amount by multiplying the equivalent acres recognized in the park inventory by the combined park cost per acre established in this study (parkland fair market value (FMV) plus capacity-adding improvements). The current Parks DIF fund balance of $3,310,852. This amount is deducted from the gross growth-related program cost before allocating remaining costs to new development, ensuring that new development is not charged for capacity already funded through prior collections. The gross program cost of $60,268,226 less the $3,310,852 fund balance deduction yields a net DIF-eligible cost of $56,957,374. Balances are maintained in the City’s accounting system with legacy subledgers for audit trail and are disclosed in the annual AB-1600 report and the �iveyear �indings.
Open Space Balance Treatment: No dedicated Open Space balance is reported at this time; therefore, there is no capacity credit to apply. Going forward, Open Space contributions will be tracked within the citywide fund in a distinct accounting line so that residential and nonresidential receipts and uses remain traceable and auditable.
205
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Regional Park Participation Balances: Regional Park participation (the 16.3% allocation to the Valley-Wide facility) is tracked in a separate accounting line and disclosed for transparency. Because the regional facility is not part of the City’s park inventory or level of service (LOS), any regional balance is not converted to City park capacity and does not offset the City’s Parks LOS calculations. It is applied exclusively to eligible capacity-enhancing improvements at the regional facility.
Derivation of Maximum Justi�ied Fees
Fees are derived and expressed in accordance with Assembly Bill 602 (AB-602), so results are stated per square foot. For Parks, the calculation is resident-based and applies to residential development.
For Open Space, the calculation applies to both residential and nonresidential development, with residential expressed per square foot by housing type and nonresidential expressed per square foot by land use category. All steps use the study-year costs in the Cost Basis section and the service standards in Standards and Application.
Residential — Parks (Non-Subdivision): Required park acreage is determined by applying the Parks standard of 1.183 acres per 1,000 residents to net-new residents. The resulting acres are priced using the combined per-acre park cost (land plus improvements) to determine a cost per resident, translated to a cost per unit using persons-per-household for Single-Family Residential, MultipleFamily Residential, and Mobile Home Dwelling Units, and then to a cost per square foot by dividing by the average dwelling square footage for each housing type. For mixed-use development, only the residential component is subject to the Parks fee.
Residential — Open Space: The residential Open Space amount is derived using the Open Space standard of 5.392 acres per 1,000 residents applied to net-new residents. The resulting acres are priced using the Open Space land-only cost per acre to determine a cost per resident, then a cost per unit using persons-per-household by housing type, and �inally a cost per square foot by dividing by the average dwelling square footage for each housing type.
Nonresidential — Open Space: Nonresidential Open Space is expressed as dollars per square foot by land use category. The calculation divides the Open Space land-only cost per developed acre by the average existing square feet per developed acre for each nonresidential category, producing a rate per square foot. For lodging uses where appropriate, the contribution is expressed per lodging unit using the same land-only basis and the applicable intensity assumption.
Subdivision — Parks (Quimby): For subdivisions, the City administers Quimby requirements as parkland dedication, in-lieu fee, or a combination, using a standard of 3.000 acres per 1,000 residents as authorized by Gov. Code § 66477 (Quimby Act). This Quimby standard is distinct from the Mitigation Fee Act framework that governs the non-subdivision Parks impact fee. Dedicated land is valued at the current fair market value (FMV) and must meet this chapter’s eligibility, and in-lieu fees are programmed consistent with statutory geographic and timing requirements. To prevent doublecounting where both mechanisms apply, the City recognizes Quimby contributions �irst for their eligible purpose and then assesses the non-subdivision Parks impact fee only for remaining, nonduplicative, growth-related costs. 206
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Regional Park Participation — Fixed Allocation (Non-Rate Component): The City’s regional park participation continues under the arrangement with the Valley-Wide Recreation & Park District for the Diamond Valley Lake Community Park. This regional facility is not included in the City’s park inventory or level-of-service (LOS) and therefore is not used in the fee derivation. Instead, the City contributes a �ixed 16.3% allocation of Parks DIF receipts, applied after the Parks residential fee is calculated under AB-602. These funds are restricted to capacity-enhancing improvements that expand usable recreation capacity serving City residents. The regional participation is tracked in a separate accounting line (Fund 362) for AB-1600 reporting, ensuring transparency and preventing commingling with City park revenues. This proportional-participation structure satis�ies the nexus requirement without altering the per square foot fee calculation or the City’s LOS basis.
Mixed-Use, Change of Use, and Additions: Mixed-use projects are assessed by category, with only the residential portion subject to the Parks residential fee and both residential and nonresidential components subject to Open Space as applicable. Changes of use and additions are assessed on the net increase in impact relative to the prior legal use.
Rounding and Presentation: Fees are presented per square foot; see Administrative Provisions:
Rounding and Publication for rounding and publication rules.
Capital Program and Eligibility
The capital program identi�ies the growth-eligible projects and de�ines what costs qualify for Parks and for Open Space. Projects are selected to maintain the City’s adopted service standards as development occurs, and each appropriation will be documented elsewhere in this chapter to preserve a clear audit trail under the Mitigation Fee Act.
Eligibility Test — Parks: Parks funds may be used for parkland acquisition and for capital improvements that add usable recreation capacity to the City’s park system. Eligible work includes site acquisition; site preparation and utility extensions; multi-purpose turf and hardscape areas; �ields and courts; destination playgrounds; restrooms and support buildings; lighting and fencing; internal paths and trailheads; irrigation; and accessibility features necessary to place new capacity into service. Planning, environmental review, design, permitting, construction management, and prudent contingencies are eligible when they are capitalized to deliver new capacity. Operations and routine maintenance, programming, rolling stock, and like-for-like replacements that do not add capacity are not eligible.
Eligibility Test — Open Space: Open Space funds are used for the acquisition of land or property interests that support recreation access and connectivity, including linear greenways and off-street trail corridors that are suitable for recreation or park use. The Open Space component is a land-only program, where development of recreation facilities is required to make an acquired corridor usable; those construction costs are treated under the Parks improvements cost basis if they add capacity.
Landscaping or aesthetic work that does not create usable recreation capacity is not eligible. 207
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Quimby Interface — Eligible Uses and Coordination: Quimby requirements may be satis�ied through parkland dedication, in-lieu fees, or a combination. Quimby contributions may be used to acquire or develop neighborhood or community park and recreation facilities that will serve the subdivision, and—where statutory conditions and �indings are met—to rehabilitate existing park facilities. This chapter coordinates Quimby with the non-subdivision Parks impact fee by recognizing Quimby contributions �irst for their eligible purpose and then applying the Parks impact fee only to remaining, non-duplicative, growth-related costs. The City will make any required geographic and service �indings at appropriation to ensure compliance with the Subdivision Map Act.
Project Listing and Tags: The capital program provides a citywide list of growth-eligible projects that implement this chapter. Each listed project is tagged as Citywide or Legacy-eligible for transition purposes. The list may be expanded or re�ined by Council action, provided added projects meet the eligibility tests in this section and are consistent with maintaining the adopted service standards.
Programming and Prioritization: Appropriations are considered only for projects that add usable recreation capacity. Among those eligible projects, priority is given to locations that score highest under the Parks Master Plan’s access and equity framework while maintaining the adopted service standards.
Land Dedication and Site Control: Where a development dedicates parkland that meets the eligibility criteria of this chapter, the land is credited at fair market value and can be incorporated into the capital program. For City acquisitions, fee revenues may be combined with grants or other sources to assemble sites of suf�icient size and con�iguration to function as neighborhood or community parks or as eligible open space corridors.
Soft Costs and Delivery: Capital soft costs that are integral to delivering new capacity are allowable within the Parks improvements cost basis, including planning, environmental clearance, design, permitting, construction management, and prudent contingencies. These costs are tracked by project to support clear crediting and reimbursement.
Replacement and Rehabilitation: Replacement or rehabilitation projects are eligible only when they create additional usable recreation capacity, such as converting underutilized space to multi-use courts or expanding a facility’s functional area. Work that merely restores existing capacity without expansion is not eligible under this fee.
Joint and Partnership Projects: Projects delivered with schools, other public agencies, or nonpro�its are eligible where they add recreation capacity that is available to City residents under enforceable joint-use or access agreements. The fee contribution is limited to the proportional share of capacity made available to the public consistent with this chapter.
Project List: This subsection presents the growth-eligible capital program for Parks and Open Space as program-level, citywide entries. For Parks, the program aggregates all AB-1600 receipts to acquire new parkland and construct capacity-adding park facilities needed to maintain the adopted level of service. For Open Space, the program aggregates receipts to acquire land or property interests that support recreation access and connectivity; if construction is later required to create usable recreation capacity, those improvements are delivered under the Parks component. Each 208
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report entry is formatted using the standard headings used throughout this study, so the scope, size, cost, and timing are clear and auditable.
The project entry that follows establishes the citywide Parks program and prices the growth-related capacity at the study-year unit costs. Subsequent entries can be added in the same format as additional program or site needs are identi�ied.
Parkland and Open Space Acquisition and Facilities Improvements Projects Project ID: PK-001
Project Title: Parkland Acquisition & Capacity-Adding Park Improvements Description: Acquires new parkland and constructs capacity-adding improvements to maintain the adopted level of service as residential development adds population. Eligible scope includes site acquisition; site preparation and utilities; multi-purpose turf and hardscape; courts and �ields; destination playgrounds; restrooms/support buildings; lighting and fencing; internal paths and trailheads; irrigation; and accessibility features.
Size: 48 acres (growth program)
Location: To be determined, City of Hemet (Citywide)
New Development Share: 100% – $56,957,374 (to be funded through Parks Impact Fees; AB-602 per-SF expression; net of $3,310,852 existing fund balance deduction) Existing Community Share: Fund Balance Credit – $3,310,852 (existing Parks DIF balance converted to capacity-equivalent at $1,250,000/acre; deducted from gross cost to avoid double-charging new development)
Total Cost: $60,268,226
Timing: 2026–2036
Project ID: OS-001
Project Title: Open Space Acquisition
Description: Acquires land or property interests for recreation-supporting corridors (linear greenways and off-street trail linkages) to maintain the adopted Open Space standard as development occurs. Open Space is a land-only program; any construction needed to activate a corridor is delivered under Parks when it adds usable capacity.
Size: 220 acres (residential Open Space capacity target). Nonresidential Open Space is expressed as dollars per square foot by land use category and does not carry an acreage target. 209
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Location: Citywide
New Development Share: 100% — $51,342,763 (to be funded through Open Space Impact Fees; residential and nonresidential components)
Existing Community Share: 0% — $0
Total Cost: $51,342,763
Timing: 2026–2036
Credits, Reimbursements, and In-Lieu
This section establishes how development-provided land and improvements are recognized, how reimbursements may be issued when a project delivers more than its fee obligation, and how Quimby subdivision obligations are coordinated so costs are not duplicated. Credits apply only to eligible, capacity-adding parkland or improvements under the Parks component, or to land acquisition (landonly) under the Open Space component, and are calculated using the valuation methods in this chapter. Credits are applied against the corresponding component and are not interchangeable between Parks and Open Space or across nonresidential land use categories for Open Space. Credits do not fund operations, maintenance, or like-for-like replacements that do not increase usable capacity.
Land Dedication Credits: Where a development dedicates parkland that meets this chapter’s eligibility, the City grants a credit valued at the current fair market value (FMV) for park-suitable sites (by appraisal or other City-accepted valuation). Eligibility includes appropriate size, con�iguration, and characteristics to function as neighborhood/community parkland consistent with the level of service. For Open Space, qualifying land or property interests that provide recreation access/connectivity are credited on a land-only basis. Credits may be adjusted for encumbrances, unusable areas, or conditions that limit recreation capacity.
Construction Credits (Parks only): When a development constructs capacity-adding park improvements, the City grants a credit for documented eligible construction cost (approved engineer’s estimate, awarded bid, or veri�ied costs). Improvements must add usable recreation capacity; cosmetic upgrades, routine maintenance, and like-for-like replacement are ineligible.
Construction to activate Open Space corridors is credited under Parks only if it adds capacity; Open Space remains a land-only program.
Application and Limits: Credits are applied to the corresponding component at permit issuance or another City-de�ined milestone and may not exceed the fee otherwise due for that component unless a reimbursement agreement is executed. Credits are recorded to preserve the audit trail required by the Mitigation Fee Act and are applied before calculating any residual fee for the same component and project phase. Credits are not interchangeable between components or (for Open Space) across nonresidential land use categories.
210
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Reimbursements: If a developer delivers growth-eligible facilities exceeding the project’s creditable obligation and the improvement or acquisition appears on, or is added to, this chapter’s capital program, the City may enter into a reimbursement agreement, subject to fund availability, priority, and Council approval. Agreements identify the eligible scope, the documented cost basis, and repayment terms, and must avoid double-counting.
Quimby Coordination (Sequencing and Double-Counting Guardrail): Quimby subdivision obligations under the Subdivision Map Act are administered separately from this impact fee. Where both mechanisms apply to a project, the City recognizes Quimby land dedication or in-lieu �irst for its eligible purpose; the non-subdivision Parks impact fee is then assessed only on any remaining, nonduplicative growth-related costs. This sequencing formalizes the process and prevents overlap between Quimby obligations and the Parks DIF.
Administration of Quimby Act credits (including eligibility and the amount of credit applied to a subdivision’s Quimby obligation) is determined through the City’s subdivision review and implementation procedures. Adoption of the Parks DIF does not modify Quimby requirements or Quimby crediting; for subdivision projects, Quimby obligations and any eligible credits are applied �irst, and the Parks DIF is assessed only to the extent it funds remaining, non-duplicative growthrelated costs.
For example, if a subdivision constructs a private park and the City determines that a portion of that private park quali�ies for Quimby credit under the City’s subdivision procedures (including any administrative limits historically applied to private-park crediting), that eligible credit is applied �irst toward the project’s Quimby obligation. The Parks DIF is then assessed only for any remaining, nonduplicative growth-related cost not satis�ied through Quimby, to prevent double-counting.
Regional Participation (Credits/In-Lieu/Reimbursement Inapplicable): The regional park participation is a �ixed 16.3% allocation of Parks DIF receipts and is not a rate-derived, project-level obligation. Credits, in lieu, or reimbursements do not apply to the regional allocation and may not offset it. Regional funds are accounted for in a separate line and are restricted to capacity-enhancing improvements at the regional facility; they do not enter City LOS math or Quimby calculations.
Documentation: Each credit or reimbursement is memorialized in a written instrument identifying the facility or land, the eligible scope, the valuation method, and the fee component to which the credit applies. Records must demonstrate that credited or reimbursed items add usable recreation capacity, meet this chapter’s eligibility, and align with the adopted level-of-service standards.
Summary of Development Impact Fees
Proposed Parks Fees (AB-1600 — Table 12-3): The table below summarizes the study-year Parks Development Impact Fees expressed per square foot under AB-602, derived from the 1.183 acresper-1,000 residents standard and this chapter’s cost basis. Use Table 12-3 as the of�icial schedule for residential projects outside the subdivision process. The City may adopt any amount at or below the 211
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report maximum justi�ied levels and may implement annual indexing and administrative provisions consistent with the Mitigation Fee Act and AB-602.
Table 12-3
Proposed AB-1600 Park Development Impact Fees
Land Use Impact Fee per SF
Single-Family Residential $2.099/SF
Multiple-Family Residential $4.117/SF
Mobile Home Dwelling Units $1.723/SF
Quimby Park Fees (Subdivision — Table 12-4): The following table summarizes Quimby subdivision obligations, parkland dedication, in-lieu fee, or a combination, based on the City’s adopted standard.
Quimby is administered separately from the AB-1600 fee; contributions in Table 12-4 are recognized �irst to avoid double-counting.
Table 12-4
Proposed Quimby Park Fees
Land Use Impact Fee per SF
Single-Family Residential $5.633/SF
Multiple-Family Residential $11.048/SF
Mobile Home Dwelling Units $4.623/SF
Open Space Impact Fees (Table 12-5): The table below provides a single summary of Open Space fees for residential and nonresidential development, shown per square foot by category for easy reference. Open Space is a land-only component; Table 12-5 re�lects the study-year cost basis and adopted methods.
Table 12-5
Open Space Development Impact Fees
Land Use Impact Fee per SF/Unit
Single-Family Residential $1.890/SF
Multiple-Family Residential $3.706/SF
Mobile Home Dwelling Units $1.551/SF
Commercial Lodging Rooms $41 per Room
Retail, Commercial, & Service Uses $0.002/SF
Industrial Uses $0.001/SF
Institutional Uses $0.030/SF
212
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Regional Park Allocation: A portion of the City’s Parks Development Impact Fee (DIF) is allocated to the Valley-Wide Recreation and Park District for capacity-enhancing regional park improvements.
This allocation equals 16.3% of total Parks DIF receipts and is not an additional fee. For clarity, the
16.3% allocation is an internal allocation of Parks DIF receipts only; it is not combined with Open Space fees and does not apply to the Open Space program. It represents the City’s proportional participation in regional recreation facilities such as Diamond Valley Lake Community Park, which serve City residents. The 16.3% allocation is applied automatically to all Parks DIF collections and tracked in a separate accounting line for regional projects.
Administrative Provisions
Overview: This section sets the rules for how fees are calculated, collected, indexed, documented, and administered so the program remains consistent, auditable, and simple to apply in day-to-day permitting.
Adoption and Effective Date: Fees are established by ordinance and become effective as provided by law. Applications that are vested or deemed complete before the effective date are processed under the prior rules; all others use this chapter. Subdivision park requirements are administered separately under the Subdivision Map Act.
Point of Collection: For development subject to this chapter, fees are calculated using the schedules in effect on the date of permit issuance and are collected at building permit issuance unless City procedures specify an earlier milestone. For phased projects, fees are calculated and collected by phase based on the �loor area or units permitted in each phase. Payment timing conforms to Gov. Code §66007; fees are due at building permit unless otherwise provided by ordinance or agreement, and the City may allow collection at �inal inspection/certi�icate of occupancy or earlier by agreement.
Calculation Inputs: Applicants must provide �loor area by use category and housing type so the City can apply the per square foot schedules under AB-602. See Standards & Application and Use in Calculations for persons-per-household, average dwelling square footage, and the nonresidential Open Space intensity basis (rates expressed as $/SF by land use category, and per Room for lodging where applicable).
Mixed-Use, Change of Use, and Additions: Apply per Standards & Application: Application Rules (category-by-category assessment and net-increase methodology). Only the residential component is subject to the Parks residential fee; Open Space applies to residential and nonresidential components as speci�ied.
Indexing: The City updates fee schedules once each year using its adopted indexing approach. For the Parks program, only the improvements component is indexed annually using the City’s adopted Engineering News-Record (ENR) Construction Cost Index (CCI), or its successor if the City adopts a replacement. Land components—both parkland and Open Space—are not adjusted by ENR; instead, these planning values are revisited and recalibrated during a formal nexus study update to re�lect current market conditions and policy inputs. When a speci�ic credit or reimbursement requires a 213
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report current cost basis, the City may rely on veri�ied evidence such as an appraisal, approved engineer’s estimate, awarded bid, or documented costs for the eligible scope, provided the documentation aligns with this chapter’s eligibility and valuation rules.
Rounding and Publication: All computations use full precision. For publication, per square foot rates are shown to three decimals ($0.001), and project totals are shown to the dollar. Any per-unit amounts shown for reference are rounded to the nearest dollar. The City will publish the schedules and a plain-language guide showing how to read and apply them.
Credit Application Order (Quimby Coordination): Where both Quimby and non-subdivision Parks fees apply, Quimby land dedication or in-lieu is recognized �irst for its eligible purpose; the nonsubdivision Parks fee is then applied only to any remaining, non-duplicative growth-related costs.
Because the Quimby standard (3.000 acres/1,000 residents) exceeds the Parks standard used for the non-subdivision fee, the residual Parks fee after Quimby is typically minimal or zero for residential subdivisions. Credit mechanics, valuation evidence, and any reimbursements are administered under Credits, Reimbursements, and In-Lieu.
Regional Park Allocation (Administration Only): The regional facility is not part of the City’s park inventory or LOS and therefore does not have a separate rate or schedule. Instead, the City allocates
16.3% of total Parks DIF receipts to capacity-enhancing regional improvements. This allocation is applied after the Parks fee is calculated and collected, is not an additional fee, and is tracked in a separate accounting line for AB-1600 reporting. The allocation does not offset City Parks LOS calculations and does not apply to Open Space or Quimby.
Accounting, Reporting, and Five-Year Findings: The City maintains separate accounting lines for Parks, Open Space (residential and nonresidential components traceable), and the regional allocation. Existing balances and their application are disclosed in the AB-1600 Annual Report, and continued retention or use is addressed in the �ive-year �indings. Documentation supporting credits, in-lieu, and reimbursements (agreements, appraisals, engineer’s estimates, cost substantiation) is retained to preserve the audit trail.
Administrative Adjustments and Appeals: If an applicant believes a fee has been misapplied under this chapter (for example, an incorrect land use category or �loor-area measurement), the City may process an administrative adjustment based on substantial evidence submitted by the applicant.
Requests for adjustment must be made before fee payment. Appeals follow the procedures set out in the adopting ordinance and applicable law.
Severability and Interpretation: If any provision of this chapter is held invalid, the remaining provisions remain in effect. Terms are interpreted to further the purpose of maintaining adopted levels of service and funding growth-related capacity consistent with this study.
Five Findings
1. Purpose of the Fee
214
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report The purpose of the fee is to fund the expansion of park capacity and the acquisition of open space necessary to maintain the City’s established service standards as new development occurs. The Parks component maintains the parkland level of service for residential growth; the Open Space component maintains recreation access and connectivity through land acquisition serving residential and nonresidential development as speci�ied in this chapter.
The City also participates in regional recreation through a �ixed 16.3% allocation of Parks DIF receipts; this is an allocation of revenues, not a separate fee.
2. Use of the Fee
Fee revenues will be used to �inance parkland acquisition and capacity-adding park improvements necessary to place new park capacity into service (e.g., multi-purpose turf and hardscape areas, �ields and courts, destination playgrounds, restrooms and support buildings, lighting and fencing, internal paths and trailheads, irrigation, and accessibility features). Fee revenues will also be used to acquire open space land or property interests suitable for recreation access and connectivity (e.g., linear greenways and off-street trail corridors). The Open Space component is land-only; if construction is later required to create usable recreation capacity on an acquired corridor, those improvements are delivered under the Parks component. Operations and maintenance, programming, rolling stock, landscaping, or aesthetic work that does not add capacity, and like-for-like replacements are not funded.
Subdivision park obligations under the Quimby Act are administered separately and credited to avoid double-counting.
3. Relationship Between the Fee’s Use and the Type of Development New residential development increases population and, therefore, demand for parkland and open space. Accordingly, the Parks component applies to residential development (nonsubdivision) and funds capacity that serves those residents. New residential and nonresidential development also increases the need for access/connectivity; accordingly, the Open Space component applies to both residential (resident-based) and nonresidential (intensity-based) development as speci�ied. Fee uses therefore match the types of development that create the need.
4. Relationship Between the Need for Facilities and the Type of Development Using net-new residents of 40,756, applying the Parks standard of 1.183 acres per 1,000 residents yields 48.214 acres of additional park capacity required. The existing Parks DIF fund balance of $3,310,852 is deducted from the gross program cost of $60,268,226, yielding a net DIF-eligible cost of $56,957,374 attributable to new development. For Open Space (Residential), applying the standard of 5.392 acres per 1,000 residents to the same net-new residents yields 219.757 acres of additional acquisition need.
For Open Space (Nonresidential), need is addressed on an intensity basis, with charges expressed as dollars per square foot by land use category (and, where appropriate, dollars per lodging unit) using the average existing square feet per developed acre. Because the Quimby subdivision standard (3.000 acres/1,000 residents) exceeds the Parks fee standard 215
14.E.
Chapter 12 Parkland and Open Space Acquisition and Facilities Improvements City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report (1.183 acres/1,000 residents), Quimby performance for subdivisions will typically satisfy— and may exceed—the park capacity represented in the non-subdivision Parks fee for the same population; the City therefore recognizes Quimby �irst and applies any non-subdivision Parks fee only to remaining, non-duplicative growth-related costs.
5. Relationship Between the Amount of the Fee and the Cost Attributable to Development The amount of each fee is proportional to the cost of the growth-related capacity it buys. For Parks, the analysis first prices the required park acreage using the study-year combined park cost per acre (land plus improvements). That total is allocated per resident, then translated to per unit by housing type using persons-per-household for Single-Family Residential, Multiple-Family Residential, and Mobile Home Dwelling Units, and finally expressed per square foot using average dwelling square footage, consistent with AB-602. For Open Space (Residential), required open space acres are priced at the land-only cost per acre, then allocated to cost per resident, cost per unit by housing type, and ultimately per square foot by housing type using average dwelling square footage.
For Open Space (Nonresidential), the schedule is derived by dividing the land-only cost per acre by the average existing square feet per developed acre for each nonresidential land use category (and, where appropriate, expressed per lodging unit). Credit rules ensure no payer funds the same capacity twice, and change-of-use and additions are assessed only on the net increase in impact. The City’s regional park participation is implemented as a fixed 16.3% allocation of Parks DIF receipts after fee calculation; it does not alter the per square foot rates or the level-of-service derivation.
The fee amounts set forth in this chapter represent the maximum justi�ied fees supported by this nexus analysis. The City Council retains full discretion to adopt fees at any amount at or below these maximums and may phase implementation, apply different rates to fee programs, or defer adoption of any component. Adoption of a fee within the justi�ied range is a policy decision of the City Council and does not require further nexus �indings.
References
GreenPlay, LLC & RRC Associates. (2021). Valley-Wide Recreation & Park District. 2020 Master Plan Update (Revised January 2021). Hemet: City of Hemet.
End of Chapter
216
14.E.
Chapter 13
Jobs/Housing Linkage Fee
Purpose and Scope
Purpose: The Jobs/Housing Linkage Fee ensures that new market-rate residential and nonresidential development in the City of Hemet contributes its fair, proportional share toward the cost of affordable housing for the lower-income worker households that such development generates. New market-rate residential development generates lower-income worker household demand through the consumer spending it introduces into the local economy; new nonresidential development generates that demand through direct on-site employment. In both cases, the workers whose employment is attributable to new development earn wages that qualify them as lowerincome households under current California Department of Housing and Community Development (HCD) income limits, yet cannot afford market-rate housing in Hemet. This chapter establishes the maximum justified fee for each land use category and provides the required nexus findings under the Mitigation Fee Act.
Scope of Improvements: Fee revenues collected under this program will fund the planning, land acquisition, design, permitting, and construction of deed-restricted affordable housing units serving very low-income, low-income, and moderate-income households in the City of Hemet, consistent with income definitions established by the California Department of Housing and Community Development. Eligible uses include direct financial assistance to affordable housing developers, land acquisition for Housing Element sites, gap financing for deed-restricted projects serving households at or below 80 percent of Area Median Income, and program administration.
Scope of Beneficiaries: The direct beneficiaries of this fee program are the lower-income worker households generated by new market-rate development who require affordable housing at rents or prices below what their incomes support at standard affordability ratios. New market-rate residential development generates this demand through the employment it supports in the local service sector; new nonresidential development generates it through direct on-site hiring. Fee revenues are used to fund affordable housing capacity in proportion to the demand each type of development creates.
Scope of Nexus: The nexus for this fee is established through a Direct Employment Linkage methodology that traces a documented, step-by-step causal chain from new market-rate development to lower-income worker household demand for affordable housing. Each step uses publicly available government data and is independently verifiable. For residential development: (1) new market-rate households generate income at documented levels based on prevailing Hemet rents; (2) those households spend a documented share of income in the local economy; (3) that spending supports local service-sector employment at rates derived from Riverside County economic data published by the U.S. Bureau of Economic Analysis; (4) the workers in those occupations earn wages qualifying them as lower-income households under HCD very low income limits for Riverside County; and (5) those households require affordable housing at a documented affordability gap per unit. For nonresidential development: (1) new buildings generate direct on-site employment at densities calibrated to Hemet’s adopted 2025 base-year employment from this study’s Chapter 2 217
14.E.
Chapter 13 Jobs/Housing Linkage Fee
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report demographic framework; (2) a documented share of that employment falls in occupations earning below HCD very low income thresholds; and (3) those worker households require affordable housing proportional to the employment generated. In both chains, the fee is sized to fund only the proportional share of affordable housing demand directly attributable to the development paying the fee.
Statutory and Judicial Authority
Mitigation Fee Act (Government Code §§ 66000–66025). The Mitigation Fee Act establishes the framework under which cities may impose development impact fees on new development. For each fee program, the Act requires the City to make five findings at the time of adoption demonstrating the purpose of the fee, its use, and the reasonable relationship between the fee, the development paying it, and the public facility it funds. Those findings are documented in this chapter. The Act also requires that fee revenues be deposited in a separate fund, that annual reports be published, and that five-year findings be made for any unexpended balance.
Assembly Bill 1505 (2017) — Government Code §§ 65589.5 and 65913.4. Assembly Bill 1505 reaffirmed and clarified the authority of California cities to impose inclusionary housing requirements and jobs/housing linkage fees on both residential and nonresidential development.
Prior to AB 1505, the Court of Appeal’s decision in Palmer/Sixth Street Properties, L.P. v. City of Los Angeles (2009) 175 Cal.App.4th 1396 had created uncertainty regarding whether linkage fee obligations could be applied to market-rate residential rental development. AB 1505 resolved that uncertainty by expressly authorizing local agencies to impose affordable housing fees on residential development, including rental housing, as a condition of project approval. The residential linkage fee established in this chapter is imposed in reliance on that authority.
Assembly Bill 602 (2021) — Government Code § 66016.5. Assembly Bill 602 strengthens the Mitigation Fee Act by requiring standardized nexus methodologies, per-square-foot residential fee expression by structure type, and enhanced Capital Improvement Plan documentation. This chapter satisfies all AB 602 requirements applicable to the City of Hemet: residential fees are expressed on a per-square-foot basis by land use category, all demographic and employment assumptions are explicitly identified and consistently applied, and the nexus between new development and affordable housing demand is documented through independently verifiable data sources.
California Housing Element Law — Government Code § 65580 et seq. The City of Hemet’s HCDcertified 6th-Cycle Housing Element (2021–2029) commits the City to affirmatively further fair housing and, under Program H-2h, to conduct both a residential and a commercial/housing linkage fee nexus study as implementation measures. This chapter implements that commitment. The adoption of this fee program advances the statutory goals of Government Code § 65580, which declares that the availability of housing is of vital statewide importance and that every locality bears responsibility for providing its fair share of the regional housing need across all income levels.
San Remo Hotel v. City and County of San Francisco (2002) 27 Cal.4th 643. The California Supreme Court in San Remo Hotel affirmed the legal validity of jobs/housing linkage fees imposed on nonresidential development under the Mitigation Fee Act. The Court held that San Francisco’s 218
14.E.
Chapter 13 Jobs/Housing Linkage Fee
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report commercial linkage fee satisfied the reasonable relationship requirements of Government Code § 66001 because the nexus study documented a step-by-step causal chain from new nonresidential development through employment generation to worker household demand for affordable housing.
San Remo Hotel is the controlling California authority for the nonresidential linkage fee chain established in this chapter.
Action Apartment Association v. City of Santa Monica (2007) 41 Cal.4th 1232. The California Supreme Court in Action Apartment Association affirmed the broad authority of local governments to impose fees on residential development to fund affordable housing, provided the nexus between the fee and the demand generated by new development is documented. The Court confirmed that the Mitigation Fee Act’s reasonable relationship standard is satisfied when a nexus study demonstrates that new market-rate residential development generates demand for affordable housing through the employment and economic activity it supports. This authority, read together with Assembly Bill 1505, establishes the complete legal foundation for the residential linkage fee chain in this chapter.
Existing Program
The City of Hemet does not currently levy a Jobs/Housing Linkage Fee. This chapter establishes the fee program for the first time, providing the legal and technical foundation required by the Mitigation Fee Act. The analysis identifies the affordable housing demand attributable to new development, quantifies that demand using a Direct Employment Linkage methodology, and derives a fee that ensures new development funds only its proportional share of the resulting affordability gap.
Fund Balance: No fund balance exists for this program. Upon adoption, the City will establish a dedicated Jobs/Housing Linkage Fee fund. All fee revenues and accrued interest will be deposited into this fund and expended only for the eligible purposes identified in this chapter.
Nexus Methodology Overview
This chapter applies a Direct Employment Linkage methodology to establish the nexus between new market-rate development and lower-income worker household demand for affordable housing. The methodology follows two parallel chains depending on development type.
Residential Linkage Chain (Steps 1–5)
• Step 1 — Household Income: Market-rate household income is derived from prevailing Hemet rents using the standard affordability ratio of 30 percent of gross income for rental housing (Health and Safety Code § 50052.5). Representative rents are based on U.S.
Department of Housing and Urban Development (HUD) Fair Market Rents for Riverside County (FY 2025): studio ($1,350/month), one-bedroom ($1,700/month), two-bedroom ($2,100/month), and three-bedroom ($2,650/month).
• Step 2 — Consumer Expenditures: Annual consumer expenditures are derived from gross household income by applying an expenditure ratio of 71 percent for rental households. This ratio is derived from the U.S. Bureau of Labor Statistics Consumer Expenditure Survey, 2023, Table 1101 (Quintiles of income before taxes). Based on that table, actual expenditure-toincome ratios for households in the $84,000–$117,000 income range—the range corresponding to the Hemet residential prototypes—are approximately 75 to 92 percent. The 219
14.E.
Chapter 13 Jobs/Housing Linkage Fee
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report 71 percent ratio applied in this study is therefore a conservative estimate that produces a lower maximum justified fee than the survey data would otherwise support. • Step 3 — Employment Generated: Local employment supported by resident household spending is estimated using an employment coefficient derived from U.S. Bureau of Economic Analysis (BEA) CAINC30 Economic Profile data for Riverside County (2024) and California Employment Development Department (EDD) Current Employment Statistics for the Riverside–San Bernardino–Ontario Metropolitan Statistical Area (MSA) (2024 annual average). Riverside County’s 2024 personal income totaled $142,697,421 thousand for a resident population of 2,529,933, while the MSA supported 1,700,417 total nonfarm jobs. The resulting employment coefficient is 11.92 jobs per $1 million of personal income. • Step 4 — Lower-Income Worker Households: The share of regional employment in occupations earning below the Riverside County one-person very low income threshold ($39,200 per year, equivalent to $18.85 per hour) is derived from U.S. Bureau of Labor Statistics (BLS) Occupational Employment and Wage Statistics (OEWS) for the Riverside–San Bernardino–Ontario MSA (May 2024). Of 1,678,100 workers in the MSA with identifiable wage data, 488,360 have median wages below the very low income threshold, producing a lower-income worker share of 29.1 percent. The one-person very low income limit is the appropriate reference threshold because the nexus chain traces individual workers — not multi-person households — to a wage cutoff, making it both technically precise and the most directly defensible basis under the Mitigation Fee Act’s proportionality requirements. Net jobs are converted to lower-income worker households using a workers-per-workerhousehold ratio of 1.670, derived from ACS Table B08202 for Hemet city (2024 one-year estimates).
• Step 5 — Affordability Gap: The affordability gap is $161,000 per unit, representing the average local subsidy required to produce one deed-restricted affordable unit in Riverside County under current financing conditions. This figure is derived analytically from three published government sources: (a) California Tax Credit Allocation Committee (CTCAC) 2024 Threshold Basis Limits for Riverside County establish a weighted average Total Development Cost (TDC) of $429,767 per unit for new construction garden-style projects; (b) available Low-Income Housing Tax Credit (LIHTC) equity totals approximately $139,244 per unit at standard 4% and supplemental state credit rates; and (c) supportable permanent debt of approximately $129,105 per unit, based on 2025 HCD maximum rents at 60% AMI for Riverside County at a 1.15x debt service coverage ratio. The resulting gap — TDC less equity less permanent debt — is $161,418, rounded to $161,000 for this study.
Nonresidential Linkage Chain (Steps A–C)
• Step A — Employment Density: New nonresidential buildings generate direct on-site employment at densities calibrated to Hemet’s adopted 2025 base-year employment using SCAG regional employment factors applied throughout this Nexus Study (Chapter 2, General Facilities chapter). The adopted densities are: Retail, Commercial & Service Uses, 0.79 workers per KSF; Industrial Uses, 0.75 workers per KSF; and Commercial Lodging, 0.50 workers per room.
220
14.E.
Chapter 13 Jobs/Housing Linkage Fee
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report • Step B — Lower-Income Worker Households: The same lower-income share of 29.1 percent and workers-per-worker-household ratio of 1.670 applied in the residential chain are applied here to convert lower-income workers to lower-income worker households, ensuring consistency across both fee chains.
• Step C — Fee Derivation: The maximum justified fee per square foot is calculated by multiplying lower-income worker households per 1,000 square feet by the $161,000 affordability gap per unit and dividing by 1,000 to convert to a per-square-foot basis.
Key Data Inputs
The following table summarizes the data inputs confirmed for this analysis and their sources.
Key Data Inputs
Input Value Source
Employment coefficient
11.92 jobs per $1
million personal
income
BEA CAINC30 (2024); EDD CES, Riverside–
SB–Ontario MSA (2024)
Workers per workerhousehold 1.670 ACS Table B08202, Hemet city (2024 oneyear estimates) HCD Area Median
Income (4-person) $103,900 HCD 2025 Income Limits, Riverside County Very low income
threshold (1-person)
$39,200/year
($18.85/hour) HCD 2025 Income Limits, Riverside County
BLS OEWS lower-income
worker share 29.1% BLS OEWS, Riverside–San Bernardino–Ontario MSA (May 2024) Affordability gap $161,000 per unit CTCAC 2024 TDC limits, HCD 2025 rent limits, standard LIHTC equity assumptions
Residential Linkage Fee
Development Prototypes
Two residential categories are used for fee calculation, consistent with the land use structure established in Chapter 2 of this study: Single-Family Residential and Multiple-Family Residential.
Single-Family Residential is represented by the three-bedroom unit prototype, reflecting the predominant unit type in Hemet’s single-family pipeline per the City’s 6th-Cycle Housing Element.
Multiple-Family Residential is represented by the two-bedroom prototype, consistent with the dominant unit type in Hemet’s multifamily development pipeline. 221
14.E.
Chapter 13 Jobs/Housing Linkage Fee
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Fee Derivation
The fee for each residential category is derived by: (1) calculating gross household income from the representative market rent using a 30 percent rent-to-income ratio; (2) applying the 71 percent consumer expenditure ratio to yield annual expenditures; (3) multiplying by the employment coefficient to yield gross jobs per unit; (4) multiplying by the 29.1 percent lower-income worker share; (5) dividing by the 1.670 workers-per-worker-household ratio to yield lower-income worker households per unit; (6) multiplying by the $161,000 affordability gap; and (7) dividing by the adopted average unit size (Single-Family Residential 2,304 square feet; Multiple-Family Residential 926 square feet, consistent with Appendix D of this study) to yield the fee per square foot.
Table 13-1
Residential Linkage Fee Derivation
Step Single-Family Residential Multiple-Family Residential Representative rent $2,650/month (3BR) $2,100/month (2BR) Implied household income (rent ÷
30%) $106,000/year $84,000/year
Annual consumer expenditures (×
71%) $75,260 $59,640
Gross jobs generated (÷ $1M ×
11.92) 0.897 0.711
Lower-income jobs (× 29.1%) 0.261 0.207
Lower-income worker-households
(÷ 1.670) 0.156 0.124
Affordability gap cost (× $161,000) $25,169 $19,946
Average unit size 2,304 SF 926 SF
Maximum justified fee per SF $10.92/SF $21.54/SF
Note: The higher per-square-foot fee for Multiple-Family Residential reflects the greater resident density per square foot of floor area in smaller multifamily units, which generates more consumer spending and associated employment demand per square foot of building area. This relationship is consistent with the per-square-foot fee structure required by Assembly Bill 602.
Nonresidential Linkage Fee
Fee Derivation
The fee for each nonresidential land use category is derived by: (1) applying the SCAG-calibrated employment density to yield workers per 1,000 square feet (or per room for lodging); (2) multiplying by the 29.1 percent lower-income worker share; (3) dividing by the 1.670 workers-per-workerhousehold ratio to yield lower-income worker households per 1,000 square feet; (4) multiplying by the $161,000 affordability gap; and (5) dividing by 1,000 to yield the fee per square foot. 222
14.E.
Chapter 13 Jobs/Housing Linkage Fee
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Table 13-2
Nonresidential Linkage Fee Derivation
Step
Retail,
Commercial &
Service
Industrial Institutional Commercial
Lodging
Employment density 0.79/KSF 0.75/KSF 4.00/KSF 0.50/room Lower-income workers
(× 29.1%) 0.230/KSF 0.218/KSF 1.164/KSF 0.146/room
Lower-income workerHH (÷ 1.670) 0.138/KSF 0.138/KSF 0.697/KSF 0.087/room Affordability gap cost
(× $161,000) $22,165/KSF $21,042/KSF $112,226/KSF $14,028/room Maximum justified
fee $22.16/SF $21.04/SF $112.23/SF $14,028/room
Note: Employment densities for Retail, Commercial & Service Uses and Industrial Uses are derived from SCAG regional employment factors calibrated to Hemet’s 2025 base-year total employment, consistent with the methodology applied in Chapter 9 (General Facilities) of this study. The Institutional Uses density of 4.0 workers per 1,000 square feet reflects the private institutional land use category as defined in Chapter 2 — comprising private hospitals, skilled nursing and assisted living facilities, private schools, and private care facilities — and is consistent with ITE employment generation benchmarks and BLS OEWS data for healthcare support occupations in the Riverside–San Bernardino–Ontario MSA.
Commercial Lodging density reflects 0.50 workers per keyed room, consistent with regional nexus study practice and the U.S. Energy Information Administration’s Commercial Buildings Energy Consumption Survey.
Note on the Institutional Uses Maximum Justified Fee
The maximum justified fee for Institutional Uses ($112.23 per square foot) is substantially higher than the fees for Retail, Commercial & Service Uses ($22.16 per square foot) and Industrial Uses ($21.04 per square foot). This result is not an error in the methodology. It reflects two structural characteristics of private institutional development that are independently verifiable from the data sources cited in this chapter.
First, private institutional uses are unusually labor-intensive per square foot. The adopted employment density of 4.0 workers per 1,000 square feet — applicable to private hospitals, skilled nursing facilities, assisted living centers, and private schools — is approximately five times the density of retail and industrial uses in Hemet. BLS Occupational Employment and Wage Statistics for the Riverside–San Bernardino–Ontario MSA confirm that healthcare support occupations account for the largest single concentration of lower-income workers in the regional labor market, with median wages for nursing aides ($18.42 per hour), home health aides ($17.53 per hour), and dietary and food preparation workers ($16.80 per hour) all near the $18.85 per hour very low income threshold for a one-person Riverside County household.
Second, the private institutional workforce is heavily concentrated in direct-care and support occupations. For retail and industrial uses, the 29.1 percent lower-income worker share reflects a 223
14.E.
Chapter 13 Jobs/Housing Linkage Fee
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report mixed workforce that includes both lower-wage frontline workers and higher-wage management and technical staff. Private institutional uses in Hemet — concentrated in the healthcare and elder care sectors given Hemet’s demographics — employ a workforce that is predominantly in direct-care and support roles. The 29.1 percent regional share applied in this study is therefore conservative for institutional uses specifically. A sector-specific derivation confirms this: BLS Occupational Employment and Wage Statistics for the Riverside–San Bernardino–Ontario MSA (May 2024) show that Healthcare Support occupations (SOC major group 31) — the dominant workforce in private hospitals, skilled nursing facilities, and assisted living centers — have a lower-income worker share of 72.6 percent in this labor market, reflecting the concentration of home health aides ($16.00 per hour median), physical therapist aides ($16.62 per hour), and related direct-care positions at or below the $18.85 per hour very low income threshold. Combining Healthcare Practitioners (SOC 29) and Healthcare Support (SOC 31), the blended lower-income share for the institutional workforce is
43.3 percent. Under either measure, the regional 29.1 percent share understates the lower-income concentration in institutional workplaces, meaning the $112.23 per square foot maximum justified fee is itself conservative relative to what a sector-specific analysis would produce.
The high maximum justified fee is a ceiling, not a recommended adopted fee. The City retains full discretion to set the adopted fee at any amount at or below the maximum justified ceiling. In recognition of the community benefit that private hospitals, care facilities, and educational institutions provide to Hemet residents, the Council may determine that a reduced adopted fee is appropriate for this category. An adopted fee in the range of 10 to 20 percent of the maximum justified ceiling, or approximately $11 to $22 per square foot, would be consistent with the policy approach taken by other California cities that have adopted jobs/housing linkage fees for healthcare and institutional uses.
[This space left blank to fit the following table on one page.] 224
14.E.
Chapter 13 Jobs/Housing Linkage Fee
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Fee Schedule and Summary
Table 13-3
Summary of Proposed Jobs/Housing Linkage Fees
Land Use Fee Basis Maximum Justified
Fee
Single-Family Residential Per square foot of
building area $10.92/SF
Multiple-Family Residential Per square foot of
building area $21.54/SF
Mobile Home Dwelling Units Per square foot of
building area $10.64/SF*
Commercial Lodging Rooms Per room $14,028/room
Retail, Commercial & Service Uses Per square foot of
building area $22.16/SF
Industrial Uses Per square foot of
building area $21.04/SF
Institutional Uses Per square foot of
building area $112.23/SF
*Mobile Home Dwelling Units fee derived using representative rent of $1,400/month (HUD FY2025 Riverside County) and adopted Mobile Home unit size of 1,250 square feet (Appendix D). Maximum justified fee = $10.64/SF.
The fees presented in Table 13-3 represent the maximum justified amounts supported by this nexus analysis. The City retains full discretion to adopt fees at or below these levels as a matter of policy.
Inland Empire cities that have adopted jobs/housing linkage fees have typically set adopted fees at 10 to 30 percent of the maximum justified ceiling, reflecting local market conditions and development feasibility considerations.
Existing Community Financial Commitment
There is no prior Jobs/Housing Linkage Fee program in Hemet, and accordingly no fund balance or existing investment to document for comparison purposes under this program. The nexus analysis is self-contained: the fee is sized exclusively to the affordable housing demand attributable to each category of new development, based on the published data sources identified in this chapter.
For context, Hemet’s 2025 HCD income limits establish a four-person Area Median Income of $103,900 — approximately 65 percent of Alameda County’s $159,800 AMI. The structurally lower wage and income levels in the Inland Empire produce a lower employment coefficient, a lower affordability gap, and lower maximum justified fees than comparable studies in Bay Area jurisdictions, consistent with the proportionality requirements of the Mitigation Fee Act. 225
14.E.
Chapter 13 Jobs/Housing Linkage Fee
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report Five Findings
In accordance with Government Code § 66001(a), the following findings support imposition of the Jobs/Housing Linkage Fee for residential and nonresidential development in the City of Hemet.
1. Purpose of the Fee
The purpose of the Jobs/Housing Linkage Fee is to fund the planning, land acquisition, design, permitting, and construction of deed-restricted affordable housing units for lower-income households in the City of Hemet. The fee is imposed because new market-rate residential and nonresidential development generates lower-income worker household demand for affordable housing, as documented by the Direct Employment Linkage methodology in this chapter. Fee revenues are used exclusively to fund affordable housing capacity proportional to the demand attributable to the development paying the fee.
2. Use of the Fee
Fee revenues will be deposited into the City’s Jobs/Housing Linkage Fee fund, maintained as a separate account pursuant to Government Code § 66006. Revenues will be used for eligible affordable housing production activities, including financial assistance to affordable housing developers, land acquisition for sites identified in the City’s 6th-Cycle Housing Element, gap financing for deed-restricted projects serving households at or below 80 percent of Area Median Income, and program administration. Revenues may not be used for market-rate housing, operational costs, or any purpose not directly related to affordable housing production or preservation. The City will publish annual AB 1600 reports and make the required five-year findings for any unexpended balance.
3. Relationship Between the Fee’s Use and the Type of Development Fee revenues will be used to fund affordable housing for the lower-income worker households attributable to new market-rate development. The Direct Employment Linkage methodology documented in this chapter establishes each link in the causal chain: new development generates household spending or on-site employment; that activity supports employment in occupations whose workers qualify as very low-income households under HCD income limits for Riverside County; and fee revenues fund affordable housing for those worker households. The use of the fee corresponds to the category of demand the development creates.
4. Relationship Between the Need for the Facility and the Type of Development New market-rate residential development generates worker household demand for affordable housing through the employment linkage chain documented in this chapter. New nonresidential development generates worker household demand through direct on-site employment. The number of lower-income worker households attributable to each development type is quantified in Tables 13-1 and 13-2. The need for affordable housing at the income levels generated by new development is documented by the HCD 2025 income limits for Riverside County, which establish that workers in the service, retail, and industrial 226
14.E.
Chapter 13 Jobs/Housing Linkage Fee
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report occupations generated by new development earn wages at or below the very low income threshold for a one-person Riverside County household.
5. Relationship Between the Amount of the Fee and the Cost Attributable to Development The amount of the fee is calculated by multiplying the number of lower-income worker households generated per unit of development by the $161,000 affordability gap per unit, and dividing by the applicable unit size (for residential) or development quantum (for nonresidential). The $161,000 affordability gap is derived analytically from CTCAC 2024 Threshold Basis Limits, HCD 2025 rent limits, and standard LIHTC financing assumptions, as documented in this chapter. No development type is charged more than the proportional share of the affordability gap attributable to the lower-income worker households it generates.
Implementation, Compliance, and Notes
Adoption and Program Structure: The City will adopt the Jobs/Housing Linkage Fee by City Council action at a noticed public hearing, consistent with Government Code §§ 66016 and 66018. This chapter establishes the maximum justified fee for each development type; the adopted fee is a policy determination made at the public hearing. The City retains full discretion to adopt fees at or below the maximum justified levels and to phase in changes over time.
Fund Accounting and Reporting: A separate Jobs/Housing Linkage Fee fund will be established. All fee revenues and interest will be deposited into this account and expended only for the eligible purposes identified in this chapter. The City will publish the annual AB 1600 report (Government Code § 66006) and make the five-year findings required by Government Code § 66001(d). If the City cannot make the required five-year findings, any remaining balances must be refunded as provided by law.
Timing of Collection: Pursuant to Government Code § 66007, as amended by Senate Bill 937 (effective January 1, 2025), fees on designated residential development projects may not be collected until the date of final inspection or the date the certificate of occupancy is issued, whichever occurs first. For nonresidential development and residential projects that do not qualify as designated residential development projects, fees are collected at building permit issuance.
Net New Fee Application: Fees are assessed on net new development consistent with the methodology established in Appendix E of this study. When a project demolishes or replaces existing development, the fee is assessed only on the net incremental increase in floor area or units above the prior legal use.
Annual Indexing: The fee schedule will be indexed annually using the Engineering News-Record Construction Cost Index or a comparable index adopted by the City Council, consistent with standard Hemet DIF program practice.
Use of Funds: Expenditures are limited to eligible affordable housing production and preservation activities as defined in this chapter. Routine operations, market-rate housing, and any purpose not directly related to affordable housing production are not eligible. 227
14.E.
Chapter 13 Jobs/Housing Linkage Fee
City of Hemet 2026–27 Development Impact Fee Calculation and Nexus Report References
California Department of Housing and Community Development (HCD). (2025). “2025 State Income Limits.” Sacramento: HCD Division of Housing Policy Development. Effective April 23, 2025.
California Tax Credit Allocation Committee (CTCAC). (2024). “2024 Threshold Basis Limits.” Sacramento: California Tax Credit Allocation Committee.
City of Hemet. (2024). “City of Hemet 6th Cycle Housing Element 2021–2029 (HCD Certified Final Draft).” Hemet: City of Hemet Community Development Department.
U.S. Bureau of Economic Analysis (BEA). (2024). “CAINC30: Economic Profile — Riverside County, California.” Washington, D.C.: BEA Regional Economic Accounts.
U.S. Bureau of Labor Statistics (BLS). (2024). “Occupational Employment and Wage Statistics (OEWS) — Riverside–San Bernardino–Ontario, CA Metropolitan Statistical Area (May 2024).” Washington, D.C.: U.S. Department of Labor.
U.S. Census Bureau. (2024). “ACS 1-Year Estimates Detailed Tables: Table B08202 — Household Size by Number of Workers in Household, Hemet City, California.” Washington, D.C.:
American Community Survey.
U.S. Department of Housing and Urban Development (HUD). (2025). “FY 2025 Fair Market Rents — Riverside County, California.” Washington, D.C.: HUD Office of Policy Development and Research.
California Employment Development Department (EDD). (2024). “Industry Employment and Labor Force — Riverside–San Bernardino–Ontario MSA, March 2024 Benchmark.” Sacramento:
Labor Market Information Division.
End of Chapter
228
14.E.
APPENDIX A
DEVELOPMENT IMPACT FEE MASTER FEE SCHEDULE
229
14.E.
Land Use Cost Basis
Law Enforcement
Facilities
Fire
Facilities
Bridges, Streets,
& Traffic
Flood
Control
Water System
Facilities
Wastewater
System Facilities
Single-Family Residential Per Square Foot $0.312 $1.157 $0.396 $0.886 $0.227 $0.189 Multiple-Family Residential Per Square Foot $0.892 $0.878 $0.394 $2.388 $0.444 $0.370 Mobile Home Dwelling Unit Per Square Foot $0.395 $1.433 $0.322 $1.311 $0.186 $0.155 Commercial Lodging Rooms Per Room $3,453 $4,255 $227 $363 $21 $17 Retail, Commercial, & Service Uses Per Square Foot $1.648 $1.356 $3.284 $0.707 $0.043 $0.036 Industrial Uses Per Square Foot $0.532 $0.039 $1.224 $0.645 $0.020 $0.017 Institutional Uses Per Square Foot $1.383 $0.074 $0.642 $18.339 $0.089 $0.074 Land Use Cost Basis
General
Facilities
Public Meeting
Facilities
Library Facilities
& Collections
Parkland
AB-1600
Valley-Wide
Parks Fee
Open Space
Acquisition
Single-Family Residential Per Square Foot $0.119 $0.375 $0.655 $2.099 $0.342 $1.890 Multiple-Family Residential Per Square Foot $0.280 $0.736 $1.285 $4.117 $0.671 $3.706 Mobile Home Dwelling Unit Per Square Foot $0.146 $0.308 $0.538 $1.723 $0.281 $1.551 Commercial Lodging Rooms Per Room $32 — — — — $41
Retail, Commercial, & Service Uses Per Square Foot $0.066 — — — — $0.002 Industrial Uses Per Square Foot $0.062 — — — — $0.001
Institutional Uses Per Square Foot $1.704 — — — — $0.030 Land Use Cost Basis
Single-Family Residential
Per Square
Foot
Multiple-Family Residential
Per Square
Foot
Mobile Home Dwelling Unit
Per Square
Foot
Commercial Lodging Rooms Per Room
Retail, Commercial, & Service Uses
Per Square
Foot
Industrial Uses
Per Square
Foot
Institutional Uses
Per Square
Foot
Total Infrastructure DIF
Development Impact Fees Per Infrastructure — Part 2 of 2 (General Government, Public Meeting, Library, Parks, Open Space) $16.162
$7.141
City of Hemet — Development Impact Fee Master Fee Schedule — 2026–27 $8.349
Development Impact Fees Per Infrastructure — Part 1 of 2 (Law Enforcement, Fire, Transportation, Flood Control, Water, Sewer) $8,409
Total Development Impact Fee Per Land Use
$2.540
$8.647
$22.334
230
14.E.
Land Use Cost Basis
Single-Family Residential Per Square Foot
Multiple-Family Residential Per Square Foot
Mobile Home Dwelling Unit Per Square Foot
Commercial Lodging Rooms Per Room
Retail, Commercial, & Service Uses Per Square Foot
Industrial Uses Per Square Foot
Institutional Uses Per Square Foot
Land Use Cost Basis
Single-Family Residential Per Square Foot
Multiple-Family Residential Per Square Foot
Mobile Home Dwelling Unit Per Square Foot
Quimby Fee
Subdivision Park Requirement — Quimby Act (For Reference Only; Not a Development Impact Fee) $21.54
For reference only. Applies to residential subdivisions subject to the City's Quimby ordinance. Administered under the Subdivision Map Act (Government Code § 66477); land dedication and/or inlieu fees are credited first to avoid double-counting with the Parkland AB-1600 DIF. Not included in Total DIF. $10.64
$5.633
Maximum Justified Fee
$4.623
Notes
$10.92
Note: The Jobs/Housing Linkage Fee is maintained in a separate fund from the Development Impact Fee program and is supported by an independent employment linkage nexus analysis (Chapter 13) rather than a capital improvement program. The maximum justified fees shown above represent the highest defensible fee levels supported by this study. The City Council retains full discretion to adopt fees at or below these levels as a matter of policy. Adopted rates are set by separate Council resolution.
Jobs/Housing Linkage Fee — Maximum Justified Fee (Chapter 13) $112.23
$11.048
$22.16
$14,028 Council adopts fee at or below maximum
justified ceiling
$21.04
231
14.E.
APPENDIX B
LAND USE CROSSWALK
232
14.E.
Appendix B: Land Use Crosswalk
Purpose: Align the City’s General Plan land use designations and zoning families to the Nexus Study (Chapter 2) fee categories so every parcel/designation translates cleanly into the fee schedule.
Acronym & Abbreviation Key (Nexus Study Categories) Table Acronym Term Description
SFR Single-Family Residential Detached single dwelling
units on individual lots.
MFR Multiple-Family Residential Attached residential units such as apartments, condos,
or townhomes.
MH Mobile Home Mobile/manufactured home
units or spaces in parks.
COM Retail, Commercial, &
Service Uses
Retail centers, restaurants,
and service businesses.
IND Industrial Uses Manufacturing, assembly,
logistics, and business parktype uses.
INST Institutional Uses Government, schools,
medical, or other
civic/public facilities.
LODGE Commercial Lodging Rooms Hotels, motels, and similar lodging accommodations
(fee per room).
233
14.E.
Land Use Crosswalk Table
General Plan
Designation
Zoning
District(s)*
Nexus/DIF
Category
(Chapter 2)
Notes
RR / HR (Rural &
Hillside
Residential)
RR, HR
families
Single-Family
Residential (SFR)
Very-low density detached
products map to SFR.
LDR / LMDR (Low
/ Low-Medium
Density Res.)
R-1 (various
minimum lot
sizes), SLR
SFR Detached neighborhoods. ADUs
don’t change category.
MDR (Medium
Density Res.) R-2 / R-3 MFR if attached; SFR if detached Use product-type rule (Chapter
2).
HDR / VHDR (High
/ Very High Density
Res.)
R-3 / R-4
Multiple-Family
Residential
(MFR)
Apartments/condos.
Mapped Mobile
Home Areas
(parks/overlays)
Per
map/overlay
Mobile Home
Dwelling Units
(MH)
Use MH category from Chapter
2. NC / CC / RC
(Neighborhood /
Community /
Regional
Commercial)
C-1 / C-2 / CM
Retail,
Commercial, &
Service Uses
(COM)
Corridor, neighborhood, and
regional centers.
Hotels/Hospitality
(in
Commercial/MU
zones)
Hotelpermitted
commercial/M
U zones
Commercial
Lodging Rooms
(LODGE)
Fee unit = per room; split mixed
sites by entitlements.
OP (Office
Professional /
Medical)
OP Institutional Uses
(INST)
Business/professional/medical
/education uses.
MU (Mixed Use;
MU-1..MU-5
, MU-D)
MU with
SP/Design
Guidelines
Split: COM for
nonres; SFR/MFR
by product type;
LODGE if hotel
Allocate by approved program
(vertical or horizontal mix).
234
14.E.
General Plan
Designation
Zoning
District(s)*
Nexus/DIF
Category
(Chapter 2)
Notes
ARPT
(Airport/Support)
Airport plan
districts
Industrial Uses
(IND) or COM
Airport operations + associated
industrial/commercial.
BP (Business Park) BP
IND (primary)
with incidental
COM pads
Light industrial, flex office, R&D;
limited support
commercial/hospitality.
I (Industrial) M-1 / M-2 Industrial Uses
(IND)
Manufacturing, logistics,
assembly, etc.
PF / QP / SCH
(Public Facility,
Quasi-Public,
School)
P-1, S-1, QP Institutional Uses
(INST) Civic, schools, cultural, utilities.
P / OS / A (Parks,
Open
Space/Natural
Resource,
Agriculture)
OS-G / OS-R /
A-1 / A-2
Non-fee (track
only)
Not fee-bearing; revenue uses
(if any) map to COM.
Overlays: SP / EM
(Specific Plan /
Environmental
Mgmt.)
SP, EM
Defer to
underlying base
GP designation
Overlay provides guidance;
doesn’t change base use for DIF.
235
14.E.
APPENDIX C
PERSONS-PER-HOUSEHOLD (PPH) METHODOLOGY
236
14.E.
Appendix C — Persons-Per-Household (PPH) Methodology
Purpose
This appendix documents the derivation and application of persons-per-household (PPH) factors used to translate population impacts into dwelling-unit equivalents for fee allocation.
It supplements Chapter 2 with full methods, category definitions, quality assurance (QA), and a worked application pattern. The approach is designed to meet transparency and proportionality standards under the Mitigation Fee Act (Gov. Code §§ 66000 et seq.) and AB602.
Data Sources & “Fixed Household Structure” Approach
Primary data are the U.S. Census Bureau American Community Survey (ACS) 2019–2023 fiveyear estimates for Hemet. Households by structure type come from ACS Table B25032, and population in occupied housing units by structure type comes from ACS Table B25033.
Because ACS B25033 groups '1, detached or attached' together, the population is apportioned between detached and attached in proportion to the household shares in B25032. After alignment, the three adopted categories ('buckets') are: Single-Family Residential (1-unit detached), Multiple-Family Residential (1-unit attached + multi-unit structures), and MobileHome Dwelling Units.
Inputs used for Hemet: ACS five-year B25032 and B25033; owner-occupied + renteroccupied; three-bucket method; Alternative Scaled Method is available when a Housing Element growth target is provided (not applied here).
Category Definitions (“Buckets”)
• Single-Family Residential (SFR): One-unit, detached structures. • Multiple-Family Residential (MFR): One-unit attached + all multi-unit structures (2– 4, 5–9, 10–19, 20–49, 50+).
• Mobile-Home Dwelling Units (MH): Manufactured/mobile homes as defined by ACS.
Calculation Method
For each category (c): PPHc = Populationc (aligned B25033) ÷ Householdsc (B25032).
Population in the combined '1, detached or attached' bucket (B25033) is split between detached and attached using the household shares from B25032 to preserve the ACS total while aligning categories.
Hemet — Step-by-Step (from ACS B25032/B25033)
1. Form household buckets (B25032, owner+renter):
- SFR (detached): 17,487 households
- MFR (attached + 2–4 + 5+): 7,070 households
- MH: 7,385 households
237
14.E.
2. Align population by structure (B25033):
- Allocate '1, detached or attached' persons between detached vs. attached using household shares.
- SFR persons: 60,513.93; MFR persons: 19,287.07; MH persons: 11,377.00.
3. Compute PPH (persons ÷ households):
- SFR: 3.4605
- MFR: 2.7280
- MH: 1.5406
Results — Adopted PPH Factors (ACS 2019–2023, Hemet)
Residential Category Persons per Household (PPH)
Single-Family Residential (SFR, 1-detached) 3.4605
Multiple-Family Residential (MFR, attached + multiunit) 2.7280 Mobile-Home Dwelling Units (MH) 1.5406
Application in the Fee Program
• Establishing the Standard: PPH converts new housing units into the number of new residents added to the city. That projected population growth defines the level of service standard for facilities like public meeting spaces, libraries, and parks and open space.
• Sizing Future Needs: Those additional residents are used to calculate how much new facility space, collection area, or park acreage is needed to maintain the city’s existing quality of life standard as growth occurs.
238
14.E.
Sensitivity, Reasonableness & Quality Assurance (QA)
• Five-year ACS is used for city-level stability and reproducibility. • Apportionment rule (B25033 → detached/attached using B25032 shares) is deterministic and preserves ACS totals.
• DP02 may be used as a citywide reasonableness check, but is not used for bucket calculations.
• Quality Assurance (QA) refers to internal verification steps confirming that:
- Household and population totals reconcile between ACS B25032 and B25033. - PPH factors are computed with consistent decimal precision. - Any subsequent scaling (Alternative Scaled Method) preserves the relative ratios among categories.
• If a Housing Element growth target is adopted, the Alternative Scaled Method can be applied to proportionally scale the three PPH values while preserving ratios, so the blended result matches the target.
239
14.E.
APPENDIX D
AVERAGE RESIDENTIAL UNIT SIZE
240
14.E.
Appendix D — Average Residential Unit Size (AUS)
Purpose
This appendix documents the adopted Average Residential Unit Sizes (AUS) used in the Hemet Development Impact Fee study to convert between dollars per dwelling unit ($/DU) and dollars per square foot ($/SF). These values support transparent, replicable fee calculations under the Mitigation Fee Act (Gov. Code §§ 66000 et seq.) and AB‑602.
Scope
Applies to residential land use categories: Single‑Family Residential, Multiple‑Family Residential, and Mobile Home Dwelling Units. Accessory Dwelling Units (ADUs) are covered in a separate appendix.
Method & Justification
Average unit sizes are derived solely from public Hemet records and adopted planning documents. Each adopted value represents interior living area (square feet per dwelling unit), computed as a unit‑weighted average of observed products. Atypical outliers were excluded. The public sources below provide the basis for each residential category.
Public Data Sources
• Hemet Municipal Code, Chapter 90 — Zoning, Article XX — Mobile Home Parks, Sec. 90‑656(1) “Interior Site Development (Mobile home spaces).” Establishes minimum mobile home space area of 4,400 sq ft, minimum space width of 40 ft along a public/private street, and minimum space dimensions of 55 ft × 80 ft. These standards support the typical double‑wide configuration used as the public basis for the mobile home AUS. • Seasons at McSweeny Farms (SDR 20‑001, City of Hemet, 2020): plan areas for Agate, Lapis, and Tourmaline models. These plan sizes are averaged (arithmetic mean) to derive the single‑family AUS.
• Aster River Oaks (SDR 23‑001; IS‑MND, City of Hemet, 2024): unit areas and counts for 228 apartments (Table 2). A unit‑weighted average of the mix is used to derive the multiple‑family AUS.
• Hemet Housing Element (HCD‑certified draft, 2021–2029): residential definitions and permitted housing types consistent with the study’s land use framework. 241
14.E.
Adopted Average Unit Sizes
Residential Category Adopted AUS (SF/DU) Use in Fee Program Single‑Family Residential
(SFR, 1‑detached)
2,304 Convert $/DU ↔ $/SF;
residential fee calculations
Multiple‑Family Residential
(MFR, attached +
multi‑unit)
926 Convert $/DU ↔ $/SF;
residential fee calculations
Mobile Home Dwelling
Units (MH)
1,250 Convert $/DU ↔ $/SF;
residential fee calculations
Calculation Notes
Each AUS is a unit‑weighted average: AUS = Σ(units × area) ÷ Σ(units). Values are maintained at full precision internally and rounded to whole square feet for publication.
Examples
• A multi‑family fee of $10,000 per dwelling unit equals $10,000 ÷ 926 = $10.80 per square foot.
• A single‑family fee of $14 per square foot equals 2,304 × $14 = $32,256 per dwelling unit. 242
14.E.
APPENDIX E
NET NEW FEE APPLICATION
243
14.E.
Appendix E — Net New Fee Application
Purpose
This appendix documents the City of Hemet’s Net New Development Impact Fee (DIF) calculation method. The calculation ensures that only the net new development impact is subject to DIFs, with credits for existing legal uses and fees applied solely to incremental increases, in accordance with the Mitigation Fee Act (Gov. Code §§ 66000 et seq.) and AB‑602.
Applicability (Programs & Units)
This method applies to the City of Hemet’s adopted Development Impact Fee programs assessed on a per‑square‑foot ($/SF) or per‑room ($/Room) basis. The examples below use the Water Facilities fee rates as a uniform demonstration for all land uses.
Applicable land uses and reference rates:
• Single‑Family Residential – $0.227/SF
• Multiple‑Family Residential – $0.444/SF
• Mobile‑Home Dwelling Units – $0.186/SF
• Commercial Lodging – $21.00/Room
• Retail / Commercial / Service – $0.043/SF
• Industrial – $0.020/SF
• Institutional – $0.089/SF
Calculation Rules (Net New)
1. Establish Existing Legal Use — Determine the fee credit from the existing legal use based on its current floor area or room count and the adopted rate (Appendix A).
2. Establish Proposed Use — Calculate the proposed fee using the current adopted rate and the new floor area or room count (Appendix A).
3. Compute Net New — Net New DIF = Proposed DIF − Existing DIF (minimum zero).
4. Change of Use — Existing credits are based on prior legal uses verified by permits or other records.
5. Mixed‑Use Sites — Apply the method by component (Residential, Retail, Industrial, etc.) and sum totals.
6. Partial Demolition/Additions — Fee credits are proportional to the remaining existing area or rooms.
244
14.E.
Worked Examples (Water Facilities Adopted Rates)
Example A — Commercial Rebuild (Retail → Retail):
Demolish 5,000 SF retail; construct 7,000 SF retail. Retail rate = $0.043/SF.
Existing Credit = 5,000 × $0.043 = $215.00
Proposed Fee = 7,000 × $0.043 = $301.00
Net New DIF = (7,000 − 5,000) × $0.043 = $86.00
Example B — Change of Use (Industrial → Retail):
Convert 10,000 SF industrial to 10,000 SF retail. Industrial rate = $0.020/SF; Retail rate = $0.043/SF.
Existing Credit = 10,000 × $0.020 = $200.00
Proposed Fee = 10,000 × $0.043 = $430.00
Net New DIF = 10,000 × ($0.043 − $0.020) = $230.00
Example C — Residential Addition (SFR → SFR):
Add 700 SF to an existing 1,800 SF single‑family dwelling. SFR rate = $0.227/SF.
Existing Credit = 1,800 × $0.227 = $408.60
Proposed Fee = 2,500 × $0.227 = $567.50
Net New DIF = (2,500 − 1,800) × $0.227 = $158.90
Example D — Mixed‑Use Redevelopment (Retail + MFR):
Demolish 2,000 SF retail and construct 3,000 SF retail plus 5,000 SF multifamily residential.
Retail rate = $0.043/SF; MFR rate = $0.444/SF.
Retail Credit = 2,000 × $0.043 = $86.00
Retail Fee = 3,000 × $0.043 = $129.00
Net Retail = $43.00
MFR Fee = 5,000 × $0.444 = $2,220.00
Total Net New DIF = $2,263.00
Example E — Commercial Lodging (Rooms):
245
14.E.
Expand a hotel from 20 to 25 rooms. Lodging rate = $21.00/Room.
Existing Credit = 20 × $21.00 = $420.00
Proposed Fee = 25 × $21.00 = $525.00
Net New DIF = (25 − 20) × $21.00 = $105.00
Submittal Requirements
• Site plan and floor area summary (existing and proposed). • Documentation of prior legal use (permits, assessor data, utility records, certificates of occupancy).
• Room counts for lodging, where applicable.
• Completed calculation worksheet demonstrating the net new fee computation.
Administrative Notes
• Negative results (Proposed − Existing < 0) yield a $0 fee. • Totals are rounded to the nearest dollar; intermediate calculations maintain precision.
• Updated rates apply if the Master Impact Fee Schedule (Appendix A) changes before permit issuance.
• Separate utility or district connection fees follow their own schedules but use the same net new principle.
246
14.E.
APPENDIX F
ACCESSORY DWELLING UNIT (ADU) IMPACT FEE
APPLICATION
247
14.E.
Appendix F — Accessory Dwelling Unit (ADU) Impact Fee Application Purpose & Legal Framework
This appendix sets out how the City of Hemet applies development impact fees (DIFs) to Accessory Dwelling Units (ADUs) consistent with California Government Code and the City’s adopted per‑square‑foot methodology. Under Government Code § 65852.2(f)(3)(A), a local agency may not impose any impact fee on an ADU less than 750 square feet; for ADUs of 750 square feet or more, any impact fees must be charged proportionately in relation to the size of the primary dwelling. DIFs must also comply with the Mitigation Fee Act (Gov. Code §§ 66000 et seq., as amended by AB‑602), which requires a reasonable relationship (nexus) and proportionality between the fee and the development’s impacts.
Methodology & Calculation Rules
• Threshold: ADUs under 750 square feet are exempt from DIFs (§ 65852.2(f)(3)(A)).
ADUs that are 750 square feet or larger may be assessed. • Composite per‑SF basis: Hemet assesses residential DIFs per square foot across programs. For ADUs ≥ 750 square feet, apply the adopted Single‑Family Residential (SFR) $/SF rate by program; the example below uses the Water Facilities rate as a uniform demonstration.
• Formula (per‑SF method): ADU Fee = SFR Rate ($/SF) × ADU Area (SF). • Proportionality (primary comparison): Because SFR is charged per SF, ADU Fee = (ADU SF ÷ Primary SF) × Primary Fee = SFR Rate × ADU SF. The per‑SF method satisfies § 65852.2’s proportionality requirement.
• Net‑new/credit: If the ADU replaces prior fee‑paid floor area and City policy provides a credit, apply Hemet’s net‑new rule (Proposed − Existing), floored at $0. • Rounding: Compute to the cent; round totals to the nearest dollar in the final fee.
At‑a‑Glance
If an ADU is under 750 square feet, no development impact fees may be charged. If an ADU is 750 square feet or larger, development impact fees may be charged, but must be proportional to size. State law also imposes size allowances/caps that affect how large an ADU may be:
detached ADUs must be allowed up to 1,200 square feet (unless a local ordinance allows more); attached ADUs may be limited to 50% of the primary dwelling’s floor area, but 248
14.E.
jurisdictions must allow at least 850 square feet for a studio/one‑bedroom ADU or at least 1,000 square feet for a two‑bedroom ADU or larger, even if percentage limits would otherwise be smaller.
Unit Size (from Appendix D): 2,304 square feet.
Example 1 — ADU 700 SF (Exempt):
Result: No DIF may be charged (ADU < 750 SF).
Example 2 — ADU 850 SF (Chargeable & Proportional):
Example 3 — ADU 1,100 SF (Within state allowances):
Note: Detached ADUs up to 1,200 SF must be allowed under state law; attached ADUs are subject to the 50% primary limit but not below 850/1,000 SF minimums.
Sources
• Gov. Code § 65852.2(f)(3)(A): ADUs < 750 SF exempt; ADUs ≥ 750 SF proportionate to the primary unit.
• Mitigation Fee Act (Gov. Code §§ 66000 et seq., as amended by AB‑602). • City of Hemet Nexus Chapters (Water Facilities rate used here as the demonstration SFR $/SF).
• Appendix D — Average Residential Unit Size (Hemet): 2,304 SF SFR average.
Inputs & Examples (Hemet - Water Facilities Adopted Rate) Reference SFR Rate (Water Facilities, adopted): $0.227 per square foot. Hemet Average SFR Primary (reference): 2,304 SF × $0.227/SF = $523.01
ADU fee (per·SF): 850 SF × $0.227/SF = $192.95 · $193 (rounded) Proportional check: (850 ÷ 2,304) × $523.01 = $192.95 · $193 (rounded) ADU fee (per·SF): 1,100 SF × $0.227/SF = $249.70 · $250 (rounded) 249
14.E.
APPENDIX G
FIRE STATION COST BASIS
250
14.E.
Appendix G
Fire Station Cost Basis
Purpose
This appendix documents the planning-level cost basis for fire station projects in the City of Hemet Development Impact Fee Nexus Study. It presents the per-square-foot construction cost estimate provided by the Hemet Fire Department, the application of that estimate to each station project, the Station 3 growth-delta calculation, and a benchmark comparison to a contemporaneous California public safety construction project to confirm reasonableness. This appendix supersedes the earlier Public Safety Building Model (Kern County FIRE prototype) previously used as the basis for station planning estimates.
Fire Department Cost Estimate
The Hemet Fire Department provided a planning-level construction cost estimate of $1,600 per square foot (all-in) for standard fire station facilities in Hemet. This figure was developed by Fire Department staff based on current market conditions and is the authoritative basis for all station project costs in Chapter 4.
What the Rate Covers: The $1,600/SF rate is all-in and inclusive of: structure and framing; interior build-out; mechanical, electrical, and plumbing (MEP) systems; life-safety and fire suppression systems; site work and site improvements; soft costs (design, engineering, permitting, construction management, testing, and inspection); and standard contingencies appropriate to this level of planning. Because all of these elements are embedded in the per-square-foot figure, no separate line items are added for individual cost components.
Application: The rate is applied directly to the station's building square footage: Total Station Cost (no land) = Building SF × $1,600/SF. A planning-level land line is added separately where applicable, based on an estimated site area and prevailing land value. Estimates are stated in study-year (2025) dollars consistent with the Fire Department's estimate.
Station 7 Note: Station 7 (West) is a three-bay facility programmed at 9,757 square feet, matching the footprint of existing Station 4. All other new stations are two-bay facilities at 7,367 square feet. 251
14.E.
Table G-1: Station Project Cost Summary
Project Station SF Bldg. Cost
(@$1,600/SF) Land
Full
Replacement
Total Cost
DIF-Eligible Cost
and Notes
FD-001
Station 3
(Relocation &
Expansion)
7,367 $11,787,200 $27,069 $11,814,269
Growth delta
only: 2,093 SF ×
$1,600 + land =
$3,375,869
FD-002 Station 6
(Southeast) 7,367 $11,787,200 $27,069 $11,814,269 100% new development FD-004 Station 7 (West) 9,757 $15,611,200 $35,850 $15,647,050 3-bay facility;
100% new
development
FD-008 Station 8
(Southwest) 7,367 $11,787,200 $27,069 $11,814,269 100% new development Note: The DIF-eligible cost for FD-001 (Station 3) reflects only the growth-attributable increment; see Table G-2 below for the delta calculation. For all other stations (FD-002, FD-004, FD-008), the full replacement cost equals the DIF-eligible cost because these are entirely new facilities. Land values are planning-level estimates and will be refined at time of project delivery.
Station 3 Growth-Delta Methodology (FD-001)
Station 3 is being relocated and expanded from 5,274 SF to 7,367 SF. Under the Mitigation Fee Act, only the capacity-increasing share attributable to growth is eligible for fee funding. The DIF-eligible cost is therefore based on the incremental square footage (the growth delta), not the full replacement cost. The growth-delta approach applies the same $1,600/SF all-in rate to the delta square footage and adds the land cost separately, producing the DIF-eligible cost for FD-001.
Table G-2: Station 3 Delta Calculation
Item Value Basis
Replacement station SF 7,367 SF Fire Department program Existing Station 3 SF 5,274 SF City records
Growth-eligible delta SF 2,093 SF 7,367 − 5,274
Per-SF cost (all-in) $1,600/SF Fire Department estimate Building cost (delta SF) $3,348,800 2,093 SF × $1,600
Land (planning-level) $27,069 0.54 acres × est. land value (prorated) DIF-eligible cost (FD001) $3,375,869 Delta SF × $1,600 + land 252
14.E.
Reasonableness Benchmark: Higgins Corner Fire Station
As a benchmark for reasonableness, the City reviewed a contemporaneous CAL FIRE station replacement project in California. The Higgins Corner Fire Station (Colusa County) was the subject of a Capital Outlay Budget Change Proposal submitted to the California Department of Finance in January 2025, based on July 2024 engineer estimates (FY 2025–26 Capital Outlay BCP; available at bcp.dof.ca.gov).
The Higgins Corner project is a multi-building CAL FIRE facility including a main station, dormitory, apparatus bays, administrative space, and support structures — a more complex program than Hemet’s standard two-bay municipal station. Colusa County also has lower prevailing construction labor costs than Southern California. Accordingly, the Higgins Corner benchmark provides a conservative reference point: a Hemet station of similar or greater complexity in the same cost environment would be expected to cost more, not less.
Table G-3: Higgins Corner Benchmark Comparison
Item Amount Notes
CAL FIRE Higgins Corner FS
project cost $12,029,000 Total BCP estimate incl. land ($900K) Less: land acquisition ($900,000) Excluded for construction-cost comparison All-in construction cost (no
land) $11,129,000 Multi-building CAL FIRE facility, Colusa County Hemet 2-bay station cost (no
land) $11,787,200 7,367 SF × $1,600/SF; simpler single-building municipal station Reasonableness
conclusion —
Hemet's $1,600/SF is conservative relative to
the Higgins Corner benchmark, given Southern
California's higher labor costs
The Higgins Corner benchmark confirms that $1,600 per square foot is a conservative and wellsupported planning-level estimate for a standard fire station facility in the City of Hemet.
Source and Attribution
The $1,600/SF planning-level estimate was provided by the Hemet Fire Department. The Higgins Corner benchmark is drawn from publicly available California Department of Finance budget documents (bcp.dof.ca.gov). No proprietary cost model or third-party estimating database is used as the primary cost basis for this program; the Fire Department’s estimate is the authoritative source. 253
14.E.
APPENDIX H
TRIP GENERATION & TRIP-MILES METHODOLOGY
254
14.E.
Appendix H — Trip Generation & Trip-Miles Methodology
This appendix documents the methodology used to measure new development’s demand on the City of Hemet’s transportation network for purposes of the Bridges, Streets & Traffic (BST) Development Impact Fee.
What Is Being Measured
The BST fee is based on trip-miles — the number of daily vehicle trips generated by a development multiplied by the average length of those trips. Trip-miles capture both how often vehicles enter the street system and how far they travel, providing a proportional measure of each development type’s demand on the road network.
Trip-miles are calculated for each land-use category and used to allocate the BST program cost in proportion to each category’s share of total projected demand.
Data Sources
Two published sources provide the inputs for every land-use category:
Source What It Provides
ITE Trip Generation
Manual (11th Edition,
2021)
Daily vehicle trip-end rates by land-use type — the number of trips entering or leaving a site per dwelling unit, per 1,000 square feet, or per room. Compiled from counts at thousands of real buildings nationwide.
SANDAG Regional Travel
Behavior Data (Appendix
T9)
Average one-way trip lengths (miles) and trip-type shares — the fractions of trips that are primary (new to the network), diverted (partial detour), or pass-by (already on the road) — for each land-use family. Based on Southern California travel surveys.
Neither source alone is sufficient: ITE counts how many trips a building generates; SANDAG identifies how many of those trips are genuinely new to the network and how far they travel.
The methodology combines them to calculate net new trip-miles.
How Trip-Miles Are Calculated
The calculation follows three steps for each land-use category:
Step 1
Count trip-ends
Multiply the development quantity (dwelling units, square feet, or rooms) by the ITE daily trip-end rate for that land use. This gives the total vehicle trips generated per day.
↓
Step 2
Adjust for trip type
Not all generated trips are new to the road network. Primary trips are fully counted. Diverted trips — vehicles making a detour on their way somewhere else — are partially counted. Pass-by trips — vehicles already on the road that pull in — receive the lowest weighting. These adjustments, based on SANDAG T9 data, prevent over-attributing demand to land uses that attract passing traffic. ↓
255
14.E.
Step 3
Multiply by trip length
Multiply the adjusted trip-ends by the average one-way trip length (miles) from SANDAG T9. The result is the daily trip-miles attributable to that land-use category.
Steps 1–3 are summarized in a single multiplier — the Trip-End and Length Factor — shown in the Chapter 5 fee schedule tables. The practical calculation is: Development Quantity × Trip-End and Length Factor = Trip-Miles.
From Trip-Miles to Fees
Once trip-miles are calculated for all land-use categories, each category’s share of total projected trip-miles determines its proportionate share of the BST program cost. That cost share is divided by the projected development quantity to produce the per-square-foot (or per-room) fee, consistent with AB-602.
Sources & Audit Trail
The Trip-End and Length Factor for each land-use category, and the resulting fee amounts, are reported in the Chapter 5 fee schedule tables. The underlying inputs can be independently verified using:
• ITE Trip Generation Manual, 11th Edition (2021) — source of all daily trip-end rates • SANDAG Regional Travel Behavior Data, Appendix T9 (April 2002) — source of trip lengths and primary/diverted/pass-by shares for Southern California land uses • Chapter 5 — Bridges, Streets & Traffic — reports the adopted Trip-End and Length Factors and the resulting per-square-foot fees
No intermediate rounding is applied; all values are carried at full precision through the fee calculation.
256
14.E.
APPENDIX I
BRIDGES, STREETS, & TRAFFIC CAPITAL PROJECT
SUMMARY
257
14.E.
Appendix I: Bridges, Streets, & Traffic Capital Project Summary Allocation of Costs Between Existing and New Development | Program Period: 2026–2036 Existing Development New Development
Project
ID Project Title Total Cost Allocation % Allocated Cost Allocation % Allocated Cost Project Timing ST-001 Acacia Ave, Florida Ave To Kirby St — Full-Width Widening $2,143,500 20% $428,700 80% $1,714,800 2026–2036 ST-002 Berkeley Ave, Hemet St To Lake St — Sidewalks
& Streetlights $189,940 75% $142,455 25% $47,485 2026–2036 ST-003 Buena Vista, North City Boundary To Oakland —
Sidewalks & Streetlights $1,286,300 20% $257,260 80% $1,029,040 2026–2036 ST-004 California Ave, Florida Ave To Devonshire Ave —
Sidewalks & Streetlights $27,540 60% $16,524 40% $11,016 2026–2036 ST-005 California Ave, Devonshire Ave To Menlo Ave —
Half-St Widening $441,145 35% $154,401 65% $286,744 2026–2036 ST-006 Cawston Ave, Esplanade To Florida Ave —
Sidewalks & Streetlights $544,180 75% $408,135 25% $136,045 2026–2036 ST-007 Chambers St, Lyon Ave To State St — Sidewalks
& Streetlights $273,809 75% $205,357 25% $68,452 2026–2036 ST-008 Charlton Ave, Park Ave To Ramona Expressway
— Sidewalks & Streetlights $513,272 75% $384,954 25% $128,318 2026–2036 ST-009 Columbia St, Park Ave To Florida Ave — Half-St
Widening $395,300 35% $138,355 65% $256,945 2026–2036
ST-010 Devonshire Ave, State St To Cornell — Half-St
Widening $503,908 35% $176,368 65% $327,540 2026–2036
ST-011 Eaton Ave, Cawston Ave To Palm Ave —
Sidewalks & Streetlights $1,053,034 75% $789,776 25% $263,258 2026–2036 ST-012 Fisher Ave, Poplar To Simpson — Full
Improvement $795,040 20% $159,008 80% $636,032 2026–2036 ST-013 Fruitvale Ave, Cawston Ave To State St —
Sidewalks & Streetlights $654,006 75% $490,505 25% $163,501 2026–2036 ST-014 Girard St, Park Ave To Devonshire Ave —
Sidewalks & Streetlights $348,864 75% $261,648 25% $87,216 2026–2036 ST-015 Girard St, Florida Ave To Devonshire Ave —
Sidewalks & Streetlights $106,284 75% $79,713 25% $26,571 2026–2036 ST-016 Hemet St, Ramona Expressway To Florida Ave
— Sidewalks & Streetlights $1,417,061 65% $921,090 35% $495,971 2026–2036 ST-017 Kirby St, Esplanade To Florida Ave — Half-St
Widening $503,505 35% $176,227 65% $327,278 2026–2036
258
14.E.
Existing Development New Development
Project
ID Project Title Total Cost Allocation % Allocated Cost Allocation % Allocated Cost Project Timing ST-018 Lake St, Ramona Expressway To Florida Ave —
Half-St Widening $207,030 35% $72,460 65% $134,570 2026–2036 ST-019 Lincoln Ave, Park Ave To City Limits —
Sidewalks & Streetlights $823,384 75% $617,538 25% $205,846 2026–2036 ST-020 Lyon Ave, Esplanade To Florida Ave — Half-St
Widening $1,542,510 35% $539,878 65% $1,002,632 2026–2036 ST-021 Menlo Ave, Rose Ave To Cawston Ave — Full
Improvement $1,166,020 20% $233,204 80% $932,816 2026–2036 ST-022 Menlo Ave, Cawston Ave To State St —
Sidewalks & Streetlights $1,260,702 75% $945,526 25% $315,176 2026–2036 ST-023 Meridian St, Washington To Park Ave —
Sidewalks & Streetlights $478,625 75% $358,969 25% $119,656 2026–2036 ST-024 Mountain Ave (Ramona Expressway) — Hemet
St To City Limits $711,567 75% $533,675 25% $177,892 2026–2036 ST-025 Meyers, Florida Ave To Devonshire Ave — HalfSt Widening $685,410 35% $239,894 65% $445,516 2026–2036 ST-026 Walden Weaver, Stetson Ave To Devonshire Ave
— Half-St Widening $5,095,975 35% $1,783,591 65% $3,312,384 2026–2036 ST-027 Newport Rd, State St To East City Limits —
Sidewalks & Streetlights $176,800 75% $132,600 25% $44,200 2026–2036 ST-028 Stetson Ave, California Ave To Walden Weaver
— Full-Width Widening $3,178,750 20% $635,750 80% $2,543,000 2026–2036 ST-029 Palm Ave, Esplanade To Florida Ave —
Sidewalks & Streetlights $1,666,810 75% $1,250,108 25% $416,702 2026–2036 ST-030 Park Ave, Hewitt To Black Walnut — Sidewalks &
Streetlights $3,189,790 75% $2,392,342 25% $797,448 2026–2036 ST-031 Celeste, Old Warren To Meyers (Old Rose Ave)
— Full Improvement $1,833,800 20% $366,760 80% $1,467,040 2026–2036 ST-032 San Jacinto St To South City Limits — Half-St
Widening $989,925 35% $346,474 65% $643,451 2026–2036
ST-033 Santa Fe St, North City Limits To Date St —
Sidewalks & Streetlights $687,728 75% $515,796 25% $171,932 2026–2036 ST-034 Soboba St, North City Limits To Florida Ave —
Half-St Widening $966,475 35% $338,266 65% $628,209 2026–2036 ST-035 State St, Domenigoni To Newport Rd — Half-St
Widening $1,574,500 35% $551,075 65% $1,023,425 2026–2036 ST-036 Stetson Ave, Walden Weaver To Cawston Ave —
Full-Width Widening $428,800 20% $85,760 80% $343,040 2026–2036 259
14.E.
Existing Development New Development
Project
ID Project Title Total Cost Allocation % Allocated Cost Allocation % Allocated Cost Project Timing ST-037 Thorton, Fischer To Sanderson Ave — Half-St
Widening $433,825 35% $151,839 65% $281,986 2026–2036
ST-038 Whittier Ave, Cawston Ave To Sanderson Ave —
Full Improvement $1,799,200 20% $359,840 80% $1,439,360 2026–2036 ST-039 Yale St, Park Ave To Florida Ave — Sidewalks &
Streetlights $458,960 75% $344,220 25% $114,740 2026–2036 ST-040 Right-of-Way Acquisition — Full Improvement $6,907,509 20% $1,381,502 80% $5,526,007 2026–2036 ST-041 Traffic Signal Update $1,000,000 60% $600,000 40% $400,000 2026–2036 ST-042 Traffic Signal, State St At Devonshire Ave $400,000 60% $240,000 40% $160,000 2026–2036 ST-043 Traffic Signal, State St At Whittier Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-044 Traffic Signal, Lyon Ave At Devonshire Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-045 Traffic Signal, Lyon Ave At Menlo Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-046 Traffic Signal, Acacia Ave At Palm Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-047 Traffic Signal, Kirby St At Menlo Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-048 Traffic Signal, State St At Johnston $800,000 60% $480,000 40% $320,000 2026–2036 ST-049 Traffic Signal, Sanderson Ave At Johnston $400,000 60% $240,000 40% $160,000 2026–2036 ST-050 Traffic Signal, Kirby St At Johnston $800,000 20% $160,000 80% $640,000 2026–2036 ST-051 Traffic Signal, California Ave At Florida Ave $400,000 60% $240,000 40% $160,000 2026–2036 ST-052 Traffic Signal, Palm Ave At Menlo Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-053 Traffic Signal, Santa Fe St At Stetson Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-054 Traffic Signal, Warren At Devonshire Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-055 Traffic Signal, Warren At Stetson Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-056 Traffic Signal, Fisher Ave At Stetson Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-057 Traffic Signal, Fisher Ave At Harrison Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-058 Traffic Signal, Dartmouth At Florida Ave $400,000 60% $240,000 40% $160,000 2026–2036 ST-059 Traffic Signal, Hemet St At Florida Ave $400,000 60% $240,000 40% $160,000 2026–2036 ST-060 Traffic Signal, Devonshire Ave At Myers Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-061 Traffic Signal, Cawston Ave At Florida Ave $400,000 60% $240,000 40% $160,000 2026–2036 ST-062 Traffic Signal, Cawston Ave At Devonshire Ave $400,000 60% $240,000 40% $160,000 2026–2036 ST-063 Traffic Signal, Sanderson Ave At Fruitvale Ave $400,000 60% $240,000 40% $160,000 2026–2036 ST-064 Traffic Signal, State St At Fruitvale Ave $400,000 60% $240,000 40% $160,000 2026–2036 ST-065 Traffic Signal, State St At Mayberry $800,000 20% $160,000 80% $640,000 2026–2036 260
14.E.
Existing Development New Development
Project
ID Project Title Total Cost Allocation % Allocated Cost Allocation % Allocated Cost Project Timing ST-066 Traffic Signal, Santa Fe St At Acacia Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-067 Traffic Signal, Santa Fe St At Devonshire Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-068 Traffic Signal, San Jacinto St At Acacia Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-069 Traffic Signal, Soboba St At Mountain Ave $400,000 60% $240,000 40% $160,000 2026–2036 ST-070 Traffic Signal, Florida Ave At Lake St $800,000 20% $160,000 80% $640,000 2026–2036 ST-071 Traffic Signal, Sanderson Ave At Wentworth $400,000 60% $240,000 40% $160,000 2026–2036 ST-072 Traffic Signal, Palm Ave At Devonshire Ave $800,000 20% $160,000 80% $640,000 2026–2036 ST-073 Traffic Signal, State St At Thornton Ave $400,000 60% $240,000 40% $160,000 2026–2036 ST-074 Future Traffic Signalization $1,000,000 20% $200,000 80% $800,000 2026–2036 ST-075 Hemet St Bridge Over Charlton Ave — Full
Improvement $5,000,000 40% $2,000,000 60% $3,000,000 2026–2036 ST-076 Highway 79 Bridge Over Devonshire Ave — Full
Improvement $5,000,000 0% $0 100% $5,000,000 2026–2036
ST-077 Highway 79 Bridge Over Stetson Ave — Full
Improvement $5,000,000 0% $0 100% $5,000,000 2026–2036
ST-078 Buena Vista St, Johnston Ave To Chambers St –
Sidewalks & Streetlights $309,775 75% $232,331 25% $77,444 2026–2036 ST-079 Cawston Ave, Florida Ave To Cloudywing Road –
Corridor Widening $2,257,936 50% $1,128,968 50% $1,128,968 2026–2036 ST-080 Devonshire Ave, California Ave To Sanderson
Ave – Half-St Widening $3,077,348 35% $1,077,072 65% $2,000,276 2026–2036 ST-081 Lyon Ave, Florida Ave To Stetson Ave – Half-St
Widening $1,532,960 35% $536,536 65% $996,424 2026–2036 ST-082 Lyon Ave, Stetson Ave To Salt Creek – FullWidth Widening $2,719,560 20% $543,912 80% $2,175,648 2026–2036 ST-083 Menlo Ave, State St To Park Ave – Sidewalks &
Streetlights $1,010,742 75% $758,056 25% $252,686 2026–2036 ST-084 Meridian St, Park Ave To Florida Ave – Half-St
Widening $192,890 35% $67,512 65% $125,378 2026–2036
ST-085 Palm Ave, Florida Ave To South of Chambers St
– Corridor Widening $3,512,850 20% $702,570 80% $2,810,280 2026–2036 ST-086 Santa Fe St, Devonshire Ave To Florida Ave –
Half-St Widening $2,760,400 35% $966,140 65% $1,794,260 2026–2036 ST-087 Thornton Ave, Lyon Ave To Santa Fe St –
Sidewalks & Streetlights $885,015 75% $663,761 25% $221,254 2026–2036 261
14.E.
Existing Development New Development
Project
ID Project Title Total Cost Allocation % Allocated Cost Allocation % Allocated Cost Project Timing ST-088 Warren Road – Half-Street Widening, Local
Share (Non-TUMF Scope) $2,499,600 35% $874,860 65% $1,624,740 2026–2036 ST-089 Warren Road Bridge Widening – Bridge/Structure
(Local DIF Share) $5,000,000 40% $2,000,000 60% $3,000,000 2026–2036 Subtotal of Project Costs $111,019,859 $38,119,260 $72,900,599 2026–2036 Less: Fund Balance (8,620,952) (8,620,952)
Net DIF-Eligible Program Cost $64,279,647
Notes: All costs are in 2025 dollars. Allocation percentages reflect project-specific trip generation and benefit analysis per the Circulation Impact Fee Nexus Study. Fund balance as of June 30, 2024 per City of Hemet FY 2023–24 AB-1600 Annual Report.
262
14.E.
APPENDIX J
FLOOD CONTROL COST BASIS AND PROJECT DETAIL
263
14.E.
APPENDIX J – FLOOD CONTROL COST BASIS AND PROJECT DETAIL Purpose
The purpose of this appendix is to document the cost basis, escalation methodology, and project components supporting the Flood Control (FC) regional drainage improvements included in the City’s Flood Control Development Impact Fee. This appendix provides the complete supporting detail for all five drainage basins—Little Lake Basin (FC-001), Southwest Hemet Basin (FC-002), San Jacinto Basin (Hemet Segments) (FC-003), West Hemet Basin (FC-004), and Hemet Main Basin (FC-005)—including the original Master Drainage Plan (MDP) cost years, ENR Construction Cost Index (CCI) escalation factors, and the fully escalated 2025-dollar project costs. The appendix also identifies each basin’s master-planned storm drain facilities and demonstrates how the project-level costs reconcile to the basin-level totals used in the fee calculation.
Methodology
The Flood Control cost basis is derived from the original facility costs reported in the applicable Master Drainage Plans for each basin and escalated to 2025 dollars using the Engineering News-Record (ENR) Construction Cost Index (CCI). Each MDP outlines the master-planned trunk lines, laterals, channels, and detention facilities required to provide regional storm drainage service. Because these plans were prepared over several decades, each basin has a distinct MDP cost year. The adopted approach applies ENR-CCI escalation from each MDP’s original cost year to January 2025 (or August 2025 for the San Jacinto Basin) to produce consistent 2025-dollar project costs. For documentation, escalation factors are presented to three decimal places, while the escalated project costs are reported at the whole-dollar values previously computed. Where basin totals are allocated 50 percent to existing development and 50 percent to new development, the resulting allocation amounts are shown at full precision and may include cents to preserve exact proportionality.
The City’s adopted methodology aggregates individual master-planned line segments into five basin-level capital projects corresponding to the hydrologic basins serving the City’s urban area. All escalated project components within each basin are summed to establish the basin-level cost used in the Flood Control Development Impact Fee. This appendix documents each basin’s components, their escalation to 2025 dollars, and the reconciliation between project-level detail and basin-level totals. The 50/50 allocation reflects the dual-benefit nature of regional storm drainage improvements, which both remedy long-standing conveyance deficiencies affecting existing neighborhoods and provide the additional trunk capacity required to serve future development. This allocation approach is consistent with accepted practice under the Mitigation Fee Act in cases where precise proportional data is unavailable.
GIS Review and Fee-Eligible Cost Adjustments: Following Public Works direction, a GIS-based review of each master-planned facility alignment using the Riverside County Flood Control (RCFC) Master Drainage Plan / Area Drainage Plan GIS to identify two categories of adjustments: (1) facilities whose alignments extend outside the City limits, requiring jurisdictional boundary proration, and (2) facilities that have been partially or fully constructed, requiring exclusion of the constructed portion from the fee-eligible program.
For jurisdictional boundary proration, the City-eligible length of each affected alignment was divided by its total alignment length to derive a City-eligible percentage, which was then applied to the facility’s allocated cost. For partial construction exclusions, the unconstructed percentage of each affected facility was applied to its allocated cost. All GIS measurements and construction verifications were performed using RCFC 264
14.E.
MDP/ADP GIS data. The resulting fee-eligible costs are documented in each basin section below and are reflected in the GIS Adjustment column of each Component Cost Detail table and the Revised Fee-Eligible Basin Cost row of each Escalation Summary table.
Data Sources
The following documents provide the source information for the cost basis, facility components, and escalation calculations used in this appendix:
• Little Lake Master Drainage Plan (Report, Plates, and Map) • Southwest Hemet Master Drainage Plan (Report, Plates, and Map) • San Jacinto Valley Master Drainage Plan (Report and Maps) • West Hemet Master Drainage Plan (Report, Plates, and Map) • Hemet Area Master Drainage Plan (Report, Plates, and Map) • ENR Construction Cost Index (CCI), historical and January/August 2025 values • City of Hemet Development Impact Fee Nexus Study (this report), used for consistency with adopted land use categories and fee program structure
Basin Detail
FC-001 — Little Lake Basin Regional Drainage Improvements Purpose: This section documents the cost basis and component facilities for the Little Lake Basin (FC-001) regional storm drainage improvements. The purpose of this section is to summarize the master-planned storm drain systems included in the Little Lake Basin, identify the original Master Drainage Plan (MDP) cost year, document the ENR Construction Cost Index (CCI) escalation to 2025 dollars, and present the fully reconciled basin-level project cost that supports the Flood Control Development Impact Fee.
Scope: The Little Lake Basin includes the northern drainage area of the City served by the trunk and lateral storm drain facilities identified in the Little Lake Master Drainage Plan. The basin improvements include the Line A Storm Drain System (including Lines A-2 and A-4), the Line B Storm Drain System (including Line B4), the Line C Storm Drain System (including Line C-1), the Line D Storm Drain System (including Line D-1), and the Line E trunk improvement. These facilities together form the regional conveyance network for the Little Lake Basin and are required to collect runoff from existing and future development and convey flows toward the Little Lake outfall.
Method & Justification: The Little Lake Basin cost basis is derived from the original facility costs reported in the Little Lake Master Drainage Plan, which was prepared using 1978 dollars. These costs were escalated to 2025 dollars using the ENR Construction Cost Index (CCI) methodology described in Section I.2. The 1978 base-year CCI is 2,776, and the January 2025 CCI is 13,731.6, yielding an escalation factor of 4.947 when rounded to three decimals for documentation. All escalated project costs shown in this section reflect the previously computed whole-dollar values prepared by Revenue & Cost Specialists (RCS) for this study using the exact escalation factor.
265
14.E.
Following Public Works direction, four adjustments were applied to this basin. Line A-4 was identified as crossing the City boundary at Charlton Avenue (the portion north of Charlton is in the County of Riverside) and was confirmed partially constructed on and north of Lincoln Avenue via RCFC GIS. The combined Cityjurisdictional and unconstructed eligible portion (56.58% of alignment length) is included in the fee program, resulting in a reduction of −$1,356,323. Line B-4 was confirmed partially constructed via RCFC GIS (11.14% complete); the constructed portion is excluded from the fee-eligible program, resulting in a reduction of −$173,317. Line E was confirmed to extend partially outside the City limits; the City-eligible portion (70.23% of alignment length, measured via RCFC GIS) is included, resulting in a reduction of −$546,975. Line B (trunk) was confirmed partially constructed via RCFC GIS; Stage 1 (4,906 LF accepted) has been constructed against a total planned alignment of 10,411 LF, leaving 4,470 LF (42.93%) unbuilt. The unbuilt portion is eligible for inclusion in the fee program; the constructed portion is excluded, resulting in a reduction of −$7,012,415. Lines A, A-2, C, C-1, D, and D-1 are fully eligible with no further adjustments. The revised fee-eligible basin cost is $18,030,385.
The basin improvements include multiple MDP line segments that function collectively as a single regional drainage project. The escalated costs for each line segment are summed to produce the basin-level cost used in the fee calculation. Consistent with the methodology in Section I.2, the total basin cost is allocated 50 percent to existing development and 50 percent to new development to reflect the shared benefit of these regional drainage improvements and the absence of updated hydrologic modeling that would support a more granular allocation.
Escalation Summary
Item Value
MDP Base Year 1978
Base-Year CCI 2,776
Target CCI (Jan 2025) 13,731.6
Escalation Factor (3 decimals) 4.947
Total Escalated Basin Cost (2025$) $27,119,415
Less: Line A-4 combined boundary proration and
construction exclusion (56.58% eligible)
−$1,356,323
Less: Line B-4 partial construction exclusion (88.86%
unconstructed)
−$173,317
Less: Line E county boundary proration (70.23% in City) −$546,975 Less: Line B trunk partial construction exclusion
(42.93% eligible; 4,470 LF unbuilt of 10,411 LF total)
−$7,012,415
Revised Fee-Eligible Basin Cost (2025$) $18,030,385
Existing Community Share (50%) $9,015,192.50
New Development Share (50%) $9,015,192.50
266
14.E.
Component Cost Detail
Component Original
MDP Cost
Escalation
Factor
2025
Escalated
Cost
Source GIS
Adjustment
Fee-Eligible
Cost
Line A (incl. A-2,
A-4)
$1,173,500 4.947 $5,804,767 Little Lake
MDP / RCS
Escalation
A-4:
−$1,356,323
(56.58%
eligible —
boundary &
construction)
$4,448,444
Line B (incl. B-4) $2,798,500 4.947 $13,842,897 Little Lake
MDP / RCS
Escalation
B-4:
−$173,317
(88.86%
unconstructed)
$6,657,165
Line C (incl. C-1) $550,500 4.947 $2,723,071 Little Lake
MDP / RCS
Escalation
— $2,723,071
Line D (incl. D-1) $588,500 4.947 $2,911,040 Little Lake
MDP / RCS
Escalation
— $2,911,040
Line E $371,500 4.947 $1,837,640 Little Lake
MDP / RCS
Escalation
−$546,975
(70.23% in
City)
$1,290,665
Total Basin Cost — — $27,119,415 — −$2,076,615 $18,030,385 Basin Summary: The Little Lake Basin improvements complete the regional storm drainage network serving the northern portion of the City. The master-planned Line A, Line B, Line C, Line D, and Line E systems address conveyance gaps, inadequate capacity in key trunk segments, and long-standing flooding concerns along several roadway corridors. The improvements also provide the additional regional capacity required to serve long-term development in the basin. The cost basis shown in this section reflects the full MDP improvement need for the Little Lake Basin and forms the basis for FC-001 in the Flood Control Development Impact Fee.
267
14.E.
FC-002 — Southwest Hemet Basin Regional Drainage Improvements Purpose: This section documents the cost basis and component facilities for the Southwest Hemet Basin (FC002) regional storm drainage improvements. The purpose of this section is to summarize the master-planned storm drain systems included in the Southwest Hemet Basin, identify the original Master Drainage Plan (MDP) cost year, document the ENR Construction Cost Index (CCI) escalation to 2025 dollars, and present the fully reconciled basin-level project cost that supports the Flood Control Development Impact Fee.
Scope: The Southwest Hemet Basin includes the southwestern drainage area of the City and encompasses the trunk and lateral storm drain facilities identified in the Southwest Hemet Master Drainage Plan. The basin improvements include Line A and its laterals (A-1 through A-4), Line B and its laterals (B-1 through B-6), and additional regional lines including Line C, Line D, Line F, Line H, Line I, Line J, Line K, Line L, Line M, Line N, Line O, and Line P. Together, these improvements establish the regional conveyance system serving both existing neighborhoods and anticipated development areas within the southwest basin.
Method & Justification: The Southwest Hemet Basin cost basis is derived from the original facility costs reported in the Southwest Hemet Master Drainage Plan, which was prepared using 1981 dollars. These costs were escalated to 2025 dollars using the ENR Construction Cost Index (CCI) methodology described in Section I.2. The 1981 base-year CCI is 3,535, and the January 2025 CCI is 13,731.6, yielding an escalation factor of 3.884 when rounded to three decimals for documentation. All escalated project costs shown in this section reflect the previously computed whole-dollar values prepared by Revenue & Cost Specialists (RCS) for this study using the exact escalation factor.
Following Public Works direction, one adjustment was applied to this basin. Line B was confirmed partially constructed via RCFC GIS (23.87% complete), with the constructed portion located approximately between Simpson Road and Olive Avenue; the constructed portion is excluded from the fee-eligible program, resulting in a reduction of −$1,220,225. All other facilities are fully eligible with no further adjustments. The revised fee-eligible basin cost is $28,468,776.
The Southwest Hemet Basin contains numerous master-planned line segments that collectively function as the regional storm drainage system for the basin. The escalated costs for each line segment are summed to determine the basin-level cost used in the fee calculation. Consistent with the methodology in Section I.2, the total basin cost is allocated 50 percent to existing development and 50 percent to new development to reflect the shared benefit of these improvements and the absence of updated hydrologic modeling that would enable a more refined proportional allocation.
Escalation Summary
Item Value
MDP Base Year 1981
Base-Year CCI 3,535
Target CCI (Jan 2025) 13,731.6
Escalation Factor (3 decimals) 3.884
Total Escalated Basin Cost (2025$) $29,689,001
268
14.E.
Less: Line B partial construction exclusion (76.13%
unconstructed, approx. Simpson Rd to Olive Ave)
−$1,220,225
Revised Fee-Eligible Basin Cost (2025$) $28,468,776
Existing Community Share (50%) $14,234,388.00
New Development Share (50%) $14,234,388.00
Component Cost Detail
Component Original
MDP Cost
Escalation
Factor
2025
Escalated
Cost
Source GIS
Adjustment
Fee-Eligible
Cost
Line A $1,135,000 3.884 $4,408,873 Southwest
Hemet MDP /
RCS
Escalation
— $4,408,873
Lateral A-1 $466,000 3.884 $1,810,163 Southwest
Hemet MDP /
RCS
Escalation
— $1,810,163
Lateral A-2 $42,000 3.884 $163,148 Southwest
Hemet MDP /
RCS
Escalation
— $163,148
Lateral A-3 $64,000 3.884 $248,606 Southwest
Hemet MDP /
RCS
Escalation
— $248,606
Lateral A-4 $63,000 3.884 $244,722 Southwest
Hemet MDP /
RCS
Escalation
— $244,722
Line B $1,316,000 3.884 $5,111,962 Southwest
Hemet MDP /
RCS
Escalation
−$1,220,225
(76.13%
unconstructed)
$3,891,737
Lateral B-1 $239,000 3.884 $928,388 Southwest
Hemet MDP /
RCS
Escalation
— $928,388
Lateral B-2 $288,000 3.884 $1,118,727 Southwest
Hemet MDP /
RCS
Escalation
— $1,118,727
Lateral B-3 $67,000 3.884 $260,259 Southwest
Hemet MDP /
RCS
Escalation
— $260,259
Lateral B-4 $67,000 3.884 $260,259 Southwest
Hemet MDP /
RCS
Escalation
— $260,259
269
14.E.
Lateral B-5 $96,000 3.884 $372,909 Southwest
Hemet MDP /
RCS
Escalation
— $372,909
Lateral B-6 $83,000 3.884 $322,411 Southwest
Hemet MDP /
RCS
Escalation
— $322,411
Line C $606,000 3.884 $2,353,989 Southwest
Hemet MDP /
RCS
Escalation
— $2,353,989
Line D $401,000 3.884 $1,557,672 Southwest
Hemet MDP /
RCS
Escalation
— $1,557,672
Line F $42,000 3.884 $163,148 Southwest
Hemet MDP /
RCS
Escalation
— $163,148
Line H $64,000 3.884 $248,606 Southwest
Hemet MDP /
RCS
Escalation
— $248,606
Line I $216,000 3.884 $839,045 Southwest
Hemet MDP /
RCS
Escalation
— $839,045
Line J $80,000 3.884 $310,758 Southwest
Hemet MDP /
RCS
Escalation
— $310,758
Line K $395,000 3.884 $1,534,365 Southwest
Hemet MDP /
RCS
Escalation
— $1,534,365
Line L $564,000 3.884 $2,190,841 Southwest
Hemet MDP /
RCS
Escalation
— $2,190,841
Line M $500,000 3.884 $1,942,235 Southwest
Hemet MDP /
RCS
Escalation
— $1,942,235
Line N $241,000 3.884 $936,157 Southwest
Hemet MDP /
RCS
Escalation
— $936,157
Line O $117,000 3.884 $454,483 Southwest
Hemet MDP /
RCS
Escalation
— $454,483
270
14.E.
Line P $491,000 3.884 $1,907,275 Southwest
Hemet MDP /
RCS
Escalation
— $1,907,275
Total Basin Cost — — $29,689,001 — −$1,220,225 $28,468,776 Basin Summary: The Southwest Hemet Basin improvements provide the regional storm drainage backbone for the southwestern area of the City. The master-planned Line A and Line B systems and their associated laterals address capacity deficiencies and conveyance needs throughout the basin, while the additional regional lines (C through P) expand the network to support full buildout. These improvements accommodate both existing drainage demands and the additional runoff associated with future development. The cost basis shown in this section reflects the complete MDP improvement needs for the Southwest Hemet Basin and forms the basis for FC-002 in the Flood Control Development Impact Fee. 271
14.E.
FC-003 — San Jacinto Basin (Hemet Segments) Regional Drainage Improvements Purpose: This section documents the cost basis and component facilities for the San Jacinto Basin (Hemet Segments) (FC-003) regional storm drainage improvements. The purpose of this section is to summarize the master-planned storm drain systems serving the City’s portion of the San Jacinto Basin, identify the original Master Drainage Plan (MDP) cost year, document the ENR Construction Cost Index (CCI) escalation to 2025 dollars, and present the fully reconciled basin-level project cost that supports the Flood Control Development Impact Fee.
Scope: The San Jacinto Basin (Hemet Segments) includes storm drain improvements located within the City of Hemet that tie into the San Jacinto Valley regional drainage system. As identified in the San Jacinto Valley Master Drainage Plan, the Hemet improvements include the Line A Florida Avenue Storm Drain, Line B-1 Menlo Avenue Storm Drain, Line C-4 Santa Fe Street Storm Drain, Line E-2 State Street Regional Trunk, and Line X W. Esplanade Avenue Regional Trunk. These trunk facilities convey flows originating within Hemet toward the larger San Jacinto regional outfall system.
Method & Justification: The San Jacinto Basin cost basis is derived from the original facility costs reported in the San Jacinto Valley Master Drainage Plan, which was prepared using 2015 dollars. These costs were escalated to 2025 dollars using the ENR Construction Cost Index (CCI) methodology described in Section I.2.
The October 2015 base-year CCI is 10,128, and the August 2025 CCI is 13,913.52, yielding an escalation factor of 1.374 when rounded to three decimals for documentation. All escalated project costs shown in this section reflect the previously computed whole-dollar values prepared by Revenue & Cost Specialists (RCS) for this study using the exact escalation factor.
Following Public Works direction, facility labels were verified against the San Jacinto Valley Master Drainage Plan and RCFC GIS. Line C-4 is located along Santa Fe Street and is identified accordingly as the Santa Fe Street Storm Drain. Line E-2 is located along State Street and is identified accordingly as the State Street Regional Trunk. One cost adjustment was also applied: Line X (W. Esplanade Avenue Regional Trunk) was confirmed via RCFC GIS to extend outside the City limits; the City-eligible portion (38.21% of alignment length) is included in the fee program, resulting in a reduction of −$7,557,320. All other facilities are fully eligible with no further adjustments. The revised fee-eligible basin cost is $22,804,321.
The Hemet improvements within the San Jacinto Basin comprise several major trunk facilities that function together as a single regional drainage project within the basin. The escalated costs for each line segment are summed to produce the basin-level cost used in the fee calculation. Consistent with the methodology in Section I.2, the total basin cost is allocated 50 percent to existing development and 50 percent to new development to reflect the shared benefit of these regional facilities and the absence of updated hydrologic modeling that would allow for more detailed proportional allocation. 272
14.E.
Escalation Summary
Item Value
MDP Base Year 2015
Base-Year CCI 10,128
Target CCI (Aug 2025) 13,913.52
Escalation Factor (3 decimals) 1.374
Total Escalated Basin Cost (2025$) $30,361,641
Less: Line X county boundary proration (38.21% in City; W. Esplanade Ave confirmed via RCFC GIS)
−$7,557,320
Revised Fee-Eligible Basin Cost (2025$) $22,804,321
Existing Community Share (50%) $11,402,160.50
New Development Share (50%) $11,402,160.50
Component Cost Detail
Component Original
MDP Cost
Escalation
Factor
2025
Escalated
Cost
Source GIS
Adjustment
Fee-Eligible Cost
Line A — Florida
Avenue Storm
Drain
$5,300,000 1.374 $7,280,969 San Jacinto
MDP / RCS
Escalation
— $7,280,969
Line B-1 — Menlo
Avenue Storm
Drain
$927,000 1.374 $1,273,483 San Jacinto
MDP / RCS
Escalation
— $1,273,483
Line C-4 — Santa
Fe Street Storm
Drain
$2,631,000 1.374 $3,614,383 San Jacinto
MDP / RCS
Escalation
— $3,614,383
Line E-2 — State
Street Regional
Trunk
$4,340,000 1.374 $5,962,152 San Jacinto
MDP / RCS
Escalation
— $5,962,152
Line X — W.
Esplanade Avenue
Regional Trunk
$8,903,000 1.374 $12,230,654 San Jacinto
MDP / RCS
Escalation
−$7,557,320
(38.21% in
City)
$4,673,334
Total Basin Cost — — $30,361,641 — −$7,557,320 $22,804,321 Basin Summary: The San Jacinto Basin (Hemet Segments) improvements represent Hemet’s portion of the regional storm drainage system serving the larger San Jacinto Valley. The master-planned trunk segments along Florida Avenue, Menlo Avenue, State Street, Santa Fe Street, and Esplanade Avenue provide the primary conveyance routes needed to manage runoff originating within Hemet and to route flows toward the regional outfall system. These facilities support both existing drainage needs and the additional flows anticipated with long-term development. The cost basis shown in this section reflects the full MDP improvement need for the Hemet segments of the San Jacinto Basin and forms the basis for FC-003 in the Flood Control Development Impact Fee.
273
14.E.
FC-004 — West Hemet Basin Regional Drainage Improvements Purpose: This section documents the cost basis and component facilities for the West Hemet Basin (FC-004) regional storm drainage improvements. The purpose of this section is to summarize the master-planned storm drain systems included in the West Hemet Basin, identify the original Master Drainage Plan (MDP) cost year, document the ENR Construction Cost Index (CCI) escalation to 2025 dollars, and present the fully reconciled basin-level project cost that supports the Flood Control Development Impact Fee.
Scope: The West Hemet Basin encompasses the western drainage area of the City and includes the masterplanned storm drain facilities identified in the West Hemet Master Drainage Plan. The basin improvements include the Line A Storm Drain System, the A-1 lateral, Line E and E-1, the Line C system (including C-1 through C-4, C-7, and C-8), Line D, and the Devonshire Retention Basin. Together, these improvements form the backbone regional drainage system required to safely convey stormwater generated within the West Hemet Basin.
Method & Justification: The West Hemet Basin cost basis is derived from the original facility costs reported in the West Hemet Master Drainage Plan, which was prepared in 1982. These costs were escalated to 2025 dollars using the ENR Construction Cost Index (CCI) methodology described in Section I.2. The 1982 baseyear CCI is 3,825, and the January 2025 CCI is 13,731.6, resulting in an escalation factor of 3.590 when rounded to three decimals for documentation. All escalated project costs shown in this section reflect the previously computed whole-dollar values prepared by Revenue & Cost Specialists (RCS) for this study using the exact escalation factor.
Following Public Works review, no adjustments were identified for the West Hemet Basin. All masterplanned facilities included in FC-004 are located within the City limits. The fee-eligible basin cost is $41,161,577.
The West Hemet Basin contains multiple interconnected master-planned facilities that operate collectively as a regional drainage system. The escalated costs of these facilities are summed to determine the basin-level cost used in the fee calculation. Consistent with the methodology in Section I.2, the total basin cost is allocated 50 percent to existing development and 50 percent to new development to account for the dual-benefit nature of the improvements and the absence of updated hydrologic modeling that could support a more refined allocation.
Escalation Summary
Item Value
MDP Base Year 1982
Base-Year CCI 3,825
Target CCI (Jan 2025) 13,731.6
Escalation Factor (3 decimals) 3.590
Total Escalated Basin Cost (2025$) $41,161,577
Existing Community Share (50%) $20,580,788.50
New Development Share (50%) $20,580,788.50
274
14.E.
Component Cost Detail
Component Original
MDP Cost
Escalation
Factor
2025
Escalated
Cost
Source GIS
Adjustment
Fee-Eligible Cost
Line A $1,406,000 3.590 $5,047,485 West Hemet
MDP / RCS
Escalation
— $5,047,485
Lateral A-1 $260,000 3.590 $933,390 West Hemet
MDP / RCS
Escalation
— $933,390
Line E $2,053,000 3.590 $7,370,189 West Hemet
MDP / RCS
Escalation
— $7,370,189
Lateral E-1 $464,000 3.590 $1,665,742 West Hemet
MDP / RCS
Escalation
— $1,665,742
Line C $1,319,000 3.590 $4,735,389 West Hemet
MDP / RCS
Escalation
— $4,735,389
Lateral C-1 $1,074,000 3.590 $3,857,742 West Hemet
MDP / RCS
Escalation
— $3,857,742
Lateral C-2 $496,000 3.590 $1,779,520 West Hemet
MDP / RCS
Escalation
— $1,779,520
Lateral C-3 $1,156,000 3.590 $4,151,417 West Hemet
MDP / RCS
Escalation
— $4,151,417
Lateral C-4 $113,000 3.590 $405,666 West Hemet
MDP / RCS
Escalation
— $405,666
Lateral C-7 $120,000 3.590 $430,795 West Hemet
MDP / RCS
Escalation
— $430,795
Lateral C-8 $96,000 3.590 $344,636 West Hemet
MDP / RCS
Escalation
— $344,636
Line D $508,000 3.590 $1,823,700 West Hemet
MDP / RCS
Escalation
— $1,823,700
Devonshire
Retention Basin
$2,400,000 3.590 $8,615,906 West Hemet
MDP / RCS
Escalation
— $8,615,906
Total Basin Cost — — $41,161,577 — — $41,161,577
Basin Summary: The West Hemet Basin improvements constitute the core regional storm drainage system serving the western portion of the City. The Line A and Line E systems address major conveyance needs along key corridors, while the Line C and Line D systems provide additional trunk capacity to move flows through the basin. The Devonshire Retention Basin further supports regional attenuation needs. Together, these improvements provide essential drainage capacity for both existing neighborhoods and future development 275
14.E.
areas. The cost basis shown in this section represents the complete MDP improvement need for the West Hemet Basin and forms the basis for FC-004 in the Flood Control Development Impact Fee. 276
14.E.
FC-005 — Hemet Main Basin Regional Drainage Improvements Purpose: This section documents the cost basis and component facilities for the Hemet Main Basin (FC-005) regional storm drainage improvements. The purpose of this section is to summarize the master-planned storm drain systems included in the Hemet Main Basin, identify the original Master Drainage Plan (MDP) cost year, document the ENR Construction Cost Index (CCI) escalation to 2025 dollars, and present the fully reconciled basin-level project cost that supports the Flood Control Development Impact Fee.
Scope: The Hemet Main Basin includes the central drainage area of the City and consists of the trunk channels, pipelines, and system laterals identified in the Hemet Area Master Drainage Plan. The basin improvements include the Line A system (including Lines A-2, A-3, A-6, and A-7), the Line B system (including B-1 and B-2), the Line C-1 trunk, and the Line D system (including D-1 and D-6). These elements together form the primary regional conveyance system serving the City’s historic urban core and surrounding development areas.
Method & Justification: The Hemet Main Basin cost basis is derived from the original facility costs reported in the Hemet Area Master Drainage Plan, which was prepared using 1977 dollars. These costs were escalated to 2025 dollars using the ENR Construction Cost Index (CCI) methodology described in Section I.2. The 1977 base-year CCI is 2,576, and the January 2025 CCI is 13,731.6, resulting in an escalation factor of 5.331 when rounded to three decimals for documentation. All escalated project costs shown in this section reflect the previously computed whole-dollar values prepared by Revenue & Cost Specialists (RCS) for this study using the exact escalation factor.
Following Public Works direction, three adjustments were applied to this basin. First, the Hemet Storm Channel mainline (Line A Reaches 1–3) was confirmed fully constructed via RCFC GIS. The mainline cost ($3,609,000 in 1977 dollars, escalated to $19,238,099) is excluded in full from the fee-eligible program, as a constructed facility does not represent an unmet capital need attributable to new development. Second, Line A-3 was confirmed substantially constructed via RCFC GIS (60.85% complete); the unconstructed portion (39.15%) is eligible for inclusion in the fee program. The eligible cost is calculated directly against Line A-3’s own escalated cost ($6,897,784 × 39.15% = $2,700,481), resulting in a reduction of −$4,197,303. Third, the Acacia Avenue Storm Drain mainline (Line B Reaches 1–5) was confirmed substantially constructed via RCFC GIS (80.15% complete); the unconstructed portion (19.85%, representing 2,975 LF of 14,984 LF total) is eligible for inclusion. Line B laterals (B-1 and B-2) are fully unbuilt and remain fully eligible. The constructed mainline portion is excluded, resulting in a reduction of −$6,770,406. Lines A-2, A-6, A-7, C-1, D-1, D-6, and Line D are fully eligible with no further adjustments. The Line D mainline (Stetson Avenue Channel) was reviewed and confirmed to be excluded from the fee program entirely; only Lines D-1 and D-6 are included, consistent with the cost basis in this section. The revised fee-eligible basin cost is $15,458,161.
The Hemet Main Basin contains multiple interconnected master-planned facilities that together provide the regional drainage capacity for the basin. The escalated costs of these facilities are summed to determine the basin-level cost used in the fee calculation. Consistent with the methodology in Section I.2, the total basin cost is allocated 50 percent to existing development and 50 percent to new development to reflect the dual benefit of these regional improvements and the absence of updated hydrologic modeling that could support a more refined proportional allocation.
277
14.E.
Escalation Summary
Item Value
MDP Base Year 1977
Base-Year CCI 2,576
Target CCI (Jan 2025) 13,731.6
Escalation Factor (3 decimals) 5.331
Total Escalated Basin Cost (2025$) $45,663,968
Less: Line A mainline (Reaches 1–3) full construction
exclusion (Hemet Storm Channel, fully constructed)
−$19,238,099
Less: Line A-3 partial construction exclusion (39.15%
unconstructed; applied directly to A-3 escalated cost)
−$4,197,303
Less: Line B mainline partial construction exclusion
(19.85% eligible; 2,975 LF unbuilt of 14,984 LF total;
Acacia Avenue Storm Drain)
−$6,770,406
Revised Fee-Eligible Basin Cost (2025$) $15,458,161
Existing Community Share (50%) $7,729,080.50
New Development Share (50%) $7,729,080.50
Component Cost Detail
Component Original
MDP Cost
Escalation
Factor
2025
Escalated
Cost
Source GIS
Adjustment
Fee-Eligible
Cost
Line A (incl. A-2,
A-3, A-6, A-7)
$5,716,000 5.331 $30,469,653 Hemet Area
MDP / RCS
Escalation
Mainline
(Reaches 1–
3):
−$19,238,099
(fully
constructed);
A-3:
−$4,197,303
(39.15%
unconstructed)
$7,034,252
Line B (incl. B-1,
B-2)
$1,890,700 5.331 $10,078,547 Hemet Area
MDP / RCS
Escalation
Mainline
(Reaches 1–
5):
−$6,770,406
(19.85%
eligible; 2,975
LF unbuilt of
14,984 LF)
$3,308,141
Line C-1 $230,000 5.331 $1,226,036 Hemet Area
MDP / RCS
Escalation
— $1,226,036
Line D (incl. D-1,
D-6)
$729,700 5.331 $3,889,732 Hemet Area
MDP / RCS
Escalation
— $3,889,732
Total Basin Cost — — $45,663,968 — −$30,205,807 $15,458,161 278
14.E.
Basin Summary: The Hemet Main Basin improvements represent the regional storm drainage system serving the City’s central urban area. The Line A, Line B, Line C-1, and Line D systems collectively provide the trunk capacity required to manage both existing stormwater flows and the additional runoff expected with future development. These facilities address long-standing conveyance constraints and create the backbone infrastructure needed to support buildout within the basin. The cost basis shown in this section reflects the complete MDP improvement need for the Hemet Main Basin and forms the basis for FC-005 in the Flood Control Development Impact Fee.
Basin Total Allocation Summary
This section summarizes the basin-level fee-eligible project costs for the five Flood Control (FC) regional drainage basins, incorporating all GIS-based adjustments, and applies the uniform 50 percent allocation to existing development and 50 percent to new development, consistent with the methodology described above. The purpose of this summary is to provide a consolidated reference table showing the fee-eligible basin costs and proportional allocations used in the Flood Control Development Impact Fee.
Basin ID Basin Name Total
Escalated
Cost (2025$)
Existing
Development
Share (50%)
New Development
Share (50%)
FC-001 Little Lake Basin $18,030,385 $9,015,192.50 $9,015,192.50 FC-002 Southwest Hemet Basin $28,468,776 $14,234,388.00 $14,234,388.00 FC-003 San Jacinto Basin
(Hemet Segments)
$22,804,321 $11,402,160.50 $11,402,160.50
FC-004 West Hemet Basin $41,161,577 $20,580,788.50 $20,580,788.50 FC-005 Hemet Main Basin $15,458,161 $7,729,080.50 $7,729,080.50 Total $125,923,220 $62,961,610.00 $62,961,610.00
Category Amount
Total Fee-Eligible Cost Across All Basins $125,923,220
Existing Development Share (50%) $62,961,610.00
New Development Share (50%) $62,961,610.00
Notes on Defensibility and Application
The Flood Control cost basis and allocation methodology presented in this appendix are designed to comply with the requirements of the Mitigation Fee Act and Assembly Bill 602 (AB-602), which together require a reasonable relationship between the cost of public facilities and the development that will benefit from or require those facilities. The use of ENR Construction Cost Index (CCI) escalation provides a consistent, industry-recognized method of converting historical Master Drainage Plan (MDP) cost estimates into 2025 dollars. Because the MDPs serving the City’s drainage basins were prepared across several decades, each with different cost years, the ENR-based escalation method allows heterogeneous cost inputs to be expressed on a comparable basis and provides a transparent, replicable escalation process suitable for audit and longterm documentation. 279
14.E.
Aggregating the individual MDP-identified line segments into five basin-level capital projects aligns with the hydrologic boundaries that govern regional storm drainage function and the manner in which the infrastructure is planned and operated. This approach consolidates numerous interconnected improvements into basin-scale projects that reflect how stormwater is conveyed, managed, and discharged within the City.
The basin-level cost summaries presented in this appendix reconcile exactly to the component-level escalated costs, ensuring that the Flood Control Development Impact Fee is grounded in identifiable, documented facility needs.
In the absence of updated hydrologic modeling or flow-based demand analysis, the City applies a 50 percent allocation to existing development and 50 percent to new development for all basin-level projects. This allocation reflects the dual-benefit nature of regional drainage facilities, which both address existing conveyance constraints affecting established neighborhoods and provide the additional trunk and backbone capacity necessary to accommodate future development. This proportional allocation is consistent with accepted practice under the Mitigation Fee Act when precise engineering or operational data needed for more granular apportionment is not available.
Together, the escalation documentation, GIS-based fee-eligible cost adjustments, basin-level reconciliation, and proportional allocation methodology described in this appendix provide the defensibility required to demonstrate the nexus between development activity and the need for regional flood control facilities. This appendix establishes a transparent audit trail that supports the Flood Control Development Impact Fee calculation and provides the foundational cost documentation necessary for ongoing reporting and future updates.
280
14.E.
APPENDIX K
FLOOD CONTROL CAPITAL PROJECT SUMMARY
281
14.E.
Appendix K: Flood Control Capital Project Summary
Allocation of Costs Between Existing and New Development | Program Period: 2026–2036 Existing Development New Development
Project
ID Project Title Total Cost Allocation % Allocated Cost Allocation % Allocated Cost Project Timing FC-001: Little Lake Master Drainage Plan
FC-001 FC-001 — Line A (incl. A-2, A-4) $4,448,444 50% $2,224,222 50% $2,224,222 2026–2036 FC-001 FC-001 — Line B (incl. B-4) $6,657,165 50% $3,328,583 50% $3,328,583 2026–2036 FC-001 FC-001 — Line C (incl. C-1) $2,723,071 50% $1,361,536 50% $1,361,536 2026–2036 FC-001 FC-001 — Line D (incl. D-1) $2,911,040 50% $1,455,520 50% $1,455,520 2026–2036 FC-001 FC-001 — Line E $1,290,665 50% $645,333 50% $645,333 2026–2036 FC-001 Subtotal $18,030,385 50% $9,015,193 50% $9,015,193 FC-002: Southwest Hemet Master Drainage Plan
FC-002 FC-002 — Line A $4,408,873 50% $2,204,437 50% $2,204,437 2026–2036 FC-002 FC-002 — Lateral A-1 $1,810,163 50% $905,082 50% $905,082 2026–2036 FC-002 FC-002 — Lateral A-2 $163,148 50% $81,574 50% $81,574 2026–2036 FC-002 FC-002 — Lateral A-3 $248,606 50% $124,303 50% $124,303 2026–2036 FC-002 FC-002 — Lateral A-4 $244,722 50% $122,361 50% $122,361 2026–2036 FC-002 FC-002 — Line B $3,891,737 50% $1,945,869 50% $1,945,869 2026–2036 FC-002 FC-002 — Lateral B-1 $928,388 50% $464,194 50% $464,194 2026–2036 FC-002 FC-002 — Lateral B-2 $1,118,727 50% $559,364 50% $559,364 2026–2036 FC-002 FC-002 — Lateral B-3 $260,259 50% $130,130 50% $130,130 2026–2036 FC-002 FC-002 — Lateral B-4 $260,259 50% $130,130 50% $130,130 2026–2036 FC-002 FC-002 — Lateral B-5 $372,909 50% $186,455 50% $186,455 2026–2036 FC-002 FC-002 — Lateral B-6 $322,411 50% $161,206 50% $161,206 2026–2036 FC-002 FC-002 — Line C $2,353,989 50% $1,176,995 50% $1,176,995 2026–2036 FC-002 FC-002 — Line D $1,557,672 50% $778,836 50% $778,836 2026–2036 FC-002 FC-002 — Line F $163,148 50% $81,574 50% $81,574 2026–2036 FC-002 FC-002 — Line H $248,606 50% $124,303 50% $124,303 2026–2036 FC-002 FC-002 — Line I $839,045 50% $419,523 50% $419,523 2026–2036 FC-002 FC-002 — Line J $310,758 50% $155,379 50% $155,379 2026–2036 FC-002 FC-002 — Line K $1,534,365 50% $767,183 50% $767,183 2026–2036 282
14.E.
Existing Development New Development
Project
ID Project Title Total Cost Allocation % Allocated Cost Allocation % Allocated Cost Project Timing FC-002 FC-002 — Line L $2,190,841 50% $1,095,421 50% $1,095,421 2026–2036 FC-002 FC-002 — Line M $1,942,235 50% $971,118 50% $971,118 2026–2036 FC-002 FC-002 — Line N $936,157 50% $468,079 50% $468,079 2026–2036 FC-002 FC-002 — Line O $454,483 50% $227,242 50% $227,242 2026–2036 FC-002 FC-002 — Line P $1,907,275 50% $953,638 50% $953,638 2026–2036 FC-002 Subtotal $28,468,776 50% $14,234,388 50% $14,234,388 FC-003: Hemet Area Master Drainage Plan
FC-003 FC-003 — Line A — Florida Avenue
Storm Drain $7,280,969 50% $3,640,485 50% $3,640,485 2026–2036 FC-003 FC-003 — Line B-1 — Menlo
Avenue Storm Drain $1,273,483 50% $636,742 50% $636,742 2026–2036 FC-003 FC-003 — Line C-4 — Santa Fe
Street Storm Drain $3,614,383 50% $1,807,192 50% $1,807,192 2026–2036 FC-003 FC-003 — Line E-2 — State Street
Regional Trunk $5,962,152 50% $2,981,076 50% $2,981,076 2026–2036 FC-003 FC-003 — Line X — Esplanade
Avenue Regional Trunk $4,673,334 50% $2,336,667 50% $2,336,667 2026–2036 FC-003 Subtotal $22,804,321 50% $11,402,161 50% $11,402,161 FC-004: San Jacinto Master Drainage Plan
FC-004 FC-004 — Line A $5,047,485 50% $2,523,743 50% $2,523,743 2026–2036 FC-004 FC-004 — Lateral A-1 $933,390 50% $466,695 50% $466,695 2026–2036 FC-004 FC-004 — Line E $7,370,189 50% $3,685,095 50% $3,685,095 2026–2036 FC-004 FC-004 — Lateral E-1 $1,665,742 50% $832,871 50% $832,871 2026–2036 FC-004 FC-004 — Line C $4,735,389 50% $2,367,695 50% $2,367,695 2026–2036 FC-004 FC-004 — Lateral C-1 $3,857,742 50% $1,928,871 50% $1,928,871 2026–2036 FC-004 FC-004 — Lateral C-2 $1,779,520 50% $889,760 50% $889,760 2026–2036 FC-004 FC-004 — Lateral C-3 $4,151,417 50% $2,075,709 50% $2,075,709 2026–2036 FC-004 FC-004 — Lateral C-4 $405,666 50% $202,833 50% $202,833 2026–2036 FC-004 FC-004 — Lateral C-7 $430,795 50% $215,398 50% $215,398 2026–2036 FC-004 FC-004 — Lateral C-8 $344,636 50% $172,318 50% $172,318 2026–2036 FC-004 FC-004 — Line D $1,823,700 50% $911,850 50% $911,850 2026–2036 FC-004 FC-004 — Devonshire Retention
Basin $8,615,906 50% $4,307,953 50% $4,307,953 2026–2036 283
14.E.
Existing Development New Development
Project
ID Project Title Total Cost Allocation % Allocated Cost Allocation % Allocated Cost Project Timing FC-004 Subtotal $41,161,577 50% $20,580,788 50% $20,580,788 FC-005: West Hemet Master Drainage Plan
FC-005 FC-005 — Line A (incl. A-2, A-3, A6, A-7) $7,034,252 50% $3,517,126 50% $3,517,126 2026–2036 FC-005 FC-005 — Line B (incl. B-1, B-2) $3,308,141 50% $1,654,071 50% $1,654,071 2026–2036 FC-005 FC-005 — Line C-1 $1,226,036 50% $613,018 50% $613,018 2026–2036 FC-005 FC-005 — Line D (incl. D-1, D-6) $3,889,732 50% $1,944,866 50% $1,944,866 2026–2036 FC-005 Subtotal $15,458,161 50% $7,729,081 50% $7,729,081 Subtotal of Project Costs $125,923,220 50% $62,961,610 50% $62,961,610 2026–2036 Less: Fund Balance (Fund 326) (6,864,347) (6,864,347)
Net DIF-Eligible Program Cost $56,097,263
Notes: All costs are in 2025 dollars, escalated from master drainage plan unit costs using ENGR-ENR Construction Cost Index. The 50% growth allocation reflects the dual-benefit nature of regional trunk infrastructure designed to accommodate ultimate buildout conditions. Fund balance as of June 30, 2024 per City of Hemet FY 2023–24 AB-1600 Annual Report (Fund 326). 284
14.E.
APPENDIX L
WATER SYSTEM FACILITIES CAPITAL PROJECT
SUMMARY
285
14.E.
Appendix L: Water System Facilities Capital Project Summary Allocation of Costs Between Existing and New Development | Program Period: 2026–2036 Existing Development New Development
Project ID Project Title Total Cost Allocation % Allocated Cost Allocation % Allocated Cost Project Timing WT-001 Park Hill to Florida Water Main
Upsizing Project $1,865,500 70% $1,313,312 30% $552,188 2026–2036 WT-002 Stetson Avenue Distribution Main $1,072,500 0% $0 100% $1,072,500 2026–2036 WT-003 Distribution Systems Upgrades $786,500 16% $126,784 84% $659,716 2026–2036 WT-004 Echo Hills 2.0 MG Storage Tanks $4,550,000 95% $4,322,500 5% $227,500 2026–2036 WT-005 Echo Hills Distribution Main Upsizing $1,225,185 34.5% $422,689 65.5% $802,496 2026–2036 WT-006 Ground Water Recharge Pipeline $1,513,550 0% $0 100% $1,513,550 2026–2036 Subtotal of Project Costs $11,013,235 $6,185,285 $4,827,950 2026–2036 Less: Fund Balance — —
Net DIF-Eligible Program Cost $4,827,950
Notes: All costs are in 2025 dollars. Allocation percentages reflect project-specific demand analysis. Fund balance as of June 30, 2024 per City of Hemet FY 2023–24 AB-1600 Annual Report. 286
14.E.
APPENDIX M
WASTEWATER SYSTEM FACILITIES CAPITAL PROJECT
SUMMARY
287
14.E.
Appendix M: Wastewater System Facilities Capital Project Summary Allocation of Costs Between Existing and New Development | Program Period: 2026–2036 Existing Development New Development
Project
ID Project Title Total Cost Allocation % Allocated Cost Allocation % Allocated Cost Project Timing SW001 Southeast Lift Station and Force Main $2,867,150 0% $0 100% $2,867,150 2026–2036 SW002Southwest Service Area – New Trunk Sewer
Extension $1,909,050 0% $0 100% $1,909,050 2026–2036
SW003 Mid-City Collector Upsize $422,500 21% $88,725 79% $333,775 2026–2036 SW004 South Hemet Collector Upsize $422,450 21% $88,715 79% $333,735 2026–2036 Subtotal of Project Costs $5,621,150 $177,439 $5,443,711 2026–2036 Less: Fund Balance — —
Net DIF-Eligible Program Cost $5,443,711
Notes: All costs are in 2025 dollars. Allocation percentages reflect project-specific capacity analysis. No fund balance is available for credit against the fee-eligible program cost. 288
14.E.
APPENDIX N
QUALITY OF LIFE COST BASIS
289
14.E.
Appendix N — Quality of Life Infrastructure Cost Basis (Land Acquisition and Construction Costs)
Purpose
This appendix documents the public cost benchmarks used to establish the City of Hemet’s development impact fee cost bases for land acquisition and for park and community-center construction. These values support the City’s Quality of Life Infrastructure programs— covering parks, community centers, libraries, and public meeting facilities. All figures are drawn from adopted local and regional plans and public market data, in compliance with the Mitigation Fee Act (Gov. Code § 66000 et seq.) and Assembly Bill (AB) 602.
1. Land Acquisition Cost Basis
Legal Framework: The Quimby Act (Gov. Code § 66477) requires that in-lieu park fees reflect the fair-market value (FMV) of land otherwise required for dedication. Using current local comparables ensures that the value represents true market conditions in Hemet.
Public Market Evidence (2024–2025):
Type Example Sites
(Verified Public
Listings)
Indicated $/Acre
Range
Source
Community-center /
civic sites
W Stetson Ave (1.1
ac @$865k); SWC
Sanderson &
Wentworth (1.62 ac
@$2.15M); NW of
Sanderson & Tanya
(0.75 ac @$375k)
≈ $330k – $1.33M
per ac
LoopNet / Moody’s
/ Showcase
Neighborhood park
sites
541 S San Jacinto St
(1.32 ac @$155k);
40105 E Johnston
Ave (0.32 ac
@$139k); Quail Rd
(1.00 ac @$109k)
≈ $110k – $435k per
ac
LandSearch
Recommended Planning Values (for nexus purposes):
• Community Center Site (Commercial / BP corridors): $800,000 per acre 290
14.E.
• Neighborhood or Community Park Site (Residential areas): $350,000 per acre These mid-market values reflect Hemet-specific comparables and are consistent with Quimby-Act methodology. Each figure represents FMV only; due diligence and closing costs (≈ 5–8%) are addressed separately as soft-cost adders.
2. Construction Cost Basis
Public Planning Source: The Valley-Wide Recreation and Park District (VWRPD) Master Plan Update (2021, amended 2025) provides detailed local cost estimates for recreation and park facilities.
Published Baseline Unit Costs (from VWRPD Action Plan):
Facility Type Unit Cost (2020 $) Typical Size /
Context
Source
Community /
Recreation Center
(Fieldhouse)
$380 / SF 75,000 – 100,000 SF VWRPD Master Plan
(2021)
New Parks (fully
improved acre) $900,000 / acre Neighborhood / Community parks VWRPD Master Plan
(2021)
Athletic Fields $5 / SF Sports field
surfacing
VWRPD Master Plan
(2021)
Courts $10 / SF Basketball/Tennis VWRPD Master Plan
(2021)
Dog Parks $3 / SF Fenced areas VWRPD Master Plan
(2021)
Splash Pads $400 / SF Interactive water
features
VWRPD Master Plan
(2021)
Playgrounds $150 / SF Composite play
structures
VWRPD Master Plan
(2021)
Application to the Nexus Study:
• Community Centers: Baseline $380/SF escalated to current year via ENR Construction Cost Index.
• Parks: Baseline $900k/acre similarly escalated.
• Amenities: Supplemental unit rates used for component-level cost support. 291
14.E.
Defensibility: These adopted, public-plan-based values are local, verifiable, and consistent with regional construction norms for Southern California.
3. Summary of Planning Values (2025 Baseline)
Category Unit Baseline Value Source
Community Center
Land $/ac $800,000 LoopNet / Showcase / Moody’s
Park Land $/ac $350,000 LandSearch
Community Center
Construction $/SF $380
VWRPD Master Plan
(2021 + 2025
Amend.)
Park Construction $/ac $900,000
VWRPD Master Plan
(2021 + 2025
Amend.)
Conclusion
By basing both land and construction costs on publicly accessible data—verified market listings and adopted master-plan cost tables—the City of Hemet’s Quality of Life Infrastructure cost bases satisfy AB-602’s transparency requirements and the Mitigation Fee Act’s reasonable relationship test.
292
14.E.
APPENDIX 0
CAPITAL IMPROVEMENT PLAN
293
14.E.
Prepared by Revenue & Cost Specialists, LLC
This Capital Improvement Plan (CIP) documents the growth-related capital projects supporting the City of Hemet’s Development Impact Fee program for the period 2026–2036. Each project is assigned to the infrastructure program it serves, with costs allocated between existing development and new development consistent with the Mitigation Fee Act (Gov. Code §§ 66000 et seq.) and Assembly Bill 602.
Program Cost Summary
Program Gross Cost Fund Balance Net DIF Cost
Law Enforcement Facilities $39,922,967 (864,916) $39,058,051 Fire Facilities $46,642,311 (3,743,576) $42,898,735
Bridges, Streets, & Traffic $111,019,859 (8,620,952) $64,279,647 Flood Control $125,923,220 (6,864,347) $56,097,263
Water System Facilities $11,013,235 — $4,827,950
Wastewater System Facilities $5,621,150 — $5,443,711
General Facilities $11,500,372 (1,761,429) $6,166,927
Public Meeting Facilities $10,410,940 (232,104) $10,178,836 Library Facilities and Collections $17,779,255 (1,345,952) $17,779,255 Parkland and Open Space $60,268,226 (3,310,852) $56,957,374 Open Space Acquisition $51,342,763 — $51,342,763
294
14.E.
Prepared by Revenue & Cost Specialists, LLC
Law Enforcement Facilities
Law Enforcement projects provide the facilities, vehicles, and equipment needed to maintain the adopted level of police service as Hemet grows.
Program Cost Allocation
Gross DIF-Eligible Program Cost $39,922,967
Less: Fund Balance Credit (864,916)
Net DIF-Eligible Program Cost $39,058,051
LE-001 Police Station Space Expansion
Department Hemet Police Department
Category Law Enforcement Facilities
Location To be determined, City of
Hemet
Size/Scope 48,721 square feet (growthrelated building expansion) Total Cost $25,822,130
New Dev. % 100%
Availability 2026–2036
Brief Description
This project expands police building space to accommodate the additional 83 sworn officers and supporting staff required to serve growth-related calls-for-service. The scope includes planning, design, permitting, and construction of additional law enforcement space within the City. This expansion could take several forms, including a remodel of existing facilities to create more efficient officer space, construction of a substation, or expansion of the existing Police Department headquarters. The project is necessary to provide the 48,721 square feet of new police building capacity identified in the growth analysis, ensuring that the City’s established level of service is maintained as development occurs.
LE-002 Police Response and Staff
Vehicles
Department Hemet Police Department
Category Law Enforcement Facilities
Location Citywide
Size/Scope 84 vehicles (growth-related
fleet expansion)
Total Cost $8,653,072
New Dev. % 100%
Availability 2026–2036
Brief Description
This project provides additional patrol and staff vehicles required to maintain deployment ratios for the 83 new sworn officers added to serve growth-related calls-for-service. Vehicles are necessary to ensure timely emergency response and effective coverage of the City as it grows. The scope includes acquisition, outfitting, and deployment of marked patrol units, unmarked support vehicles, and specialized units in proportion to the existing fleet.
LE-003 Sworn Officer Assigned
Equipment
Department Hemet Police Department
Category Law Enforcement Facilities
Location Citywide
Size/Scope 83 equipment kits (growthrelated officer assignments) Total Cost $815,521
New Dev. % 100%
Availability 2026–2036
Brief Description
This project provides assigned equipment kits for each of the 83 new sworn officers required to serve growth-related calls-forservice. Equipment includes protective gear, body-worn cameras, communication devices, firearms, and other standard-issue items necessary to ensure readiness and safety.
295
14.E.
Prepared by Revenue & Cost Specialists, LLC
LE-004 Specialty Equipment and
Technology
Department Hemet Police Department
Category Law Enforcement Facilities
Location Citywide
Size/Scope Various specialized systems and
equipment
Total Cost $4,632,244
New Dev. % 100%
Availability 2026–2036
Brief Description
This project provides specialized law enforcement equipment and technology needed to support the expansion of the City’s police system as growth occurs. Items may include
communications systems, surveillance technology, tactical equipment, and other specialty assets necessary to maintain the established level of service.
296
14.E.
Prepared by Revenue & Cost Specialists, LLC
Fire Facilities
Fire Facilities projects construct new stations and provide apparatus and equipment to maintain fire protection and emergency medical service levels as development increases calls-for-service.
Program Cost Allocation
Gross DIF-Eligible Program Cost $46,642,311
Less: Fund Balance Credit (3,743,576)
Net DIF-Eligible Program Cost $42,898,735
FD-001 New Fire Station No. 3
Department Hemet Fire Department
Category Fire Facilities
Location To be determined
Size/Scope 7,367 SF Station (2 bays)
Total Cost $3,375,869
New Dev. % 100%
Availability 2026–2036
Brief Description
This project relocates and replaces Station 3 with a modern twobay facility to maintain the established level of service as new development increases calls-for-service. The existing 5,274 SF station will be replaced with a 7,367 SF station located to the north and east to align coverage with growth areas. The development-related cost is based on the delta between the replacement facility and the existing station, reflecting only the capacity-increasing share attributable to growth. The scope includes planning, environmental review, site acquisition (if needed), design, permitting, and construction of a fully functional station with required site and building improvements.
FD-002 New Fire Station No. 6 (Southeast)
Department Hemet Fire Department
Category Fire Facilities
Location Approximately State St. &
Dominigoni Pkwy.
Size/Scope 7,367 SF Station (2 bays)
Total Cost $11,814,269
New Dev. % 100%
Availability 2026–2036
Brief Description
This project provides a City-owned fire station to add capacity necessary to maintain the established level of service as new development increases calls-for-service. The scope includes planning, environmental review, site acquisition (if needed), design, permitting, and construction of a fully functional station with required site and building improvements.
FD-003 Type I Fire Engine for Station No.
6 Department Hemet Fire Department
Category Fire Facilities
Location Station 6 service area
Size/Scope One Type I engine (frontline)
Total Cost $950,000
New Dev. % 100%
Availability 2026–2036
Brief Description
This project acquires a frontline Type I engine to equip the new Station 6, ensuring the station can be placed into service as development proceeds.
297
14.E.
Prepared by Revenue & Cost Specialists, LLC
FD-004 New Fire Station No. 7 (West)
Department Hemet Fire Department
Category Fire Facilities
Location Approximately Devonshire Ave.
& Warren Rd.
Size/Scope 9,757 SF Station (3 bays)
Total Cost $15,647,050
New Dev. % 100%
Availability 2026–2036
Brief Description
This project provides a City-owned �ire station to add capacity necessary to maintain the established level of service as new development increases calls-for-service. The scope includes planning, environmental review, site acquisition (if needed), design, permitting, and construction of a fully functional station with required site and building improvements.
FD-005 Type I Fire Engine for Station No.
7 Department Hemet Fire Department
Category Fire Facilities
Location Station 7 service area
Size/Scope One Type I engine (frontline)
Total Cost $950,000
New Dev. % 100%
Availability 2026–2036
Brief Description
This project acquires a frontline Type I engine to equip the new Station 7.
FD-006 Water Tender for Station No. 7
Department Hemet Fire Department
Category Fire Facilities
Location Station 7 service area, City of
Hemet
Size/Scope One water tender
Total Cost $500,000
New Dev. % 100%
Availability 2026–2036
Brief Description
This project acquires a water tender to support operations in areas with longer hydrant spacing and to augment �ire �low for multi-company incidents.
FD-007 Squad Vehicle for Station No. 7
Department Hemet Fire Department
Category Fire Facilities
Location Station 7 service area
Size/Scope One squad vehicle
Total Cost $270,000
New Dev. % 100%
Availability 2026–2036
Brief Description
This project acquires a squad to provide flexible response capability for EMS and support calls, paired with Station 7 staffing.
298
14.E.
Prepared by Revenue & Cost Specialists, LLC
FD-008 New Fire Station No. 8
(Southwest)
Department Hemet Fire Department
Category Fire Facilities
Location Approximately Simpson Rd. &
Warren Rd.
Size/Scope 7,367 SF Station (2 bays)
Total Cost $11,814,269
New Dev. % 100%
Availability 2026–2036
Brief Description
This project provides a City-owned �ire station to add capacity necessary to maintain the established level of service as new development increases calls-for-service. The scope includes planning, environmental review, site acquisition (if needed), design, permitting, and construction of a fully functional station with required site and building improvements.
FD-009 Type I Fire Engine for Station No.
8 Department Hemet Fire Department
Category Fire Facilities
Location Station 8 service area
Size/Scope One Type I engine (frontline)
Total Cost $950,000
New Dev. % 100%
Availability 2026–2036
Brief Description
This project acquires a frontline Type I engine to equip the new Station 8.
FD-011 Uniform PPE for Added Personnel
Department Hemet Fire Department
Category Fire Facilities
Location City of Hemet
Size/Scope Initial issue sets for added
positions
Total Cost $265,848
New Dev. % 100%
Availability 2026–2036
Brief Description
This project provides initial issue PPE and required uniforms for personnel added to new stations and companies.
FD-012 Specialty Equipment for Added
Personnel
Department Hemet Fire Department
Category Fire Facilities
Location City of Hemet
Size/Scope Equipment cache for added
positions
Total Cost $105,006
New Dev. % 100%
Availability 2026-2036
Brief Description
This project provides the specialized incident, training, and support equipment needed to place new companies into service (e.g., extrication, ventilation, HazMat support, rehab, and related inventory).
299
14.E.
Prepared by Revenue & Cost Specialists, LLC
Bridges, Streets, & Traffic
Bridges, Streets, & Traffic projects widen roadways to ultimate cross-sections, construct bridges and structures, install traffic signals, and acquire right-of-way to maintain the adopted level of service as development increases vehicle trips and demand on the circulation system.
Program Cost Allocation
Gross DIF-Eligible Program Cost $111,019,859
Less: Existing Community Share (38,119,260)
Growth-Eligible Subtotal $72,900,599
Less: Fund Balance Credit (8,620,952)
Net DIF-Eligible Program Cost $64,279,647
ST-001 Acacia Ave, Florida Ave To Kirby
St - Full-Width Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Acacia Avenue between
Florida Avenue and Kirby Street
Size/Scope 6,100 LF of full-width, 10 ADA
curb ramps; standard in-ROW
improvements.
Total Cost $2,143,500
New Dev. % 80%
Availability 2036
Brief Description
Widen Acacia Avenue from Florida Avenue to Kirby Street to provide the adopted ultimate cross-section, including
approximately 6,100 linear feet of full-width widening and installation of approximately 10 ADA-compliant curb ramps.
ST-002 Berkeley Avenue, Hemet Street to
Lake Street – Sidewalks & Streetlights
Department Public Works
Category Bridges, Streets, & Traffic
Location On Berkeley Avenue between
Hemet Street and Lake Street
Size/Scope 2,205 LF of sidewalk, streetlight
frontage, 4 ADA curb ramps;
standard in-ROW
improvements.
Total Cost $189,940
New Dev. % 25%
Availability 2036
Brief Description
Construct and upgrade sidewalks and street lighting along Berkeley Avenue from Hemet Street to Lake Street, including approximately 2,205 linear feet of frontage improvements and installation of approximately 4 ADA-compliant curb ramps. 300
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-003 Buena Vista Street, North City
Boundary to Oakland Avenue– Corridor
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Buena Vista Street between
North City Boundary and
Oakland Avenue
Size/Scope 1,000 LF full-width, 560 LF
half-street, 1,785 LF sidewalk &
streetlight frontage; 13 ADA
curb ramps; standard in-ROW
improvements.
Total Cost $1,286,300
New Dev. % 80%
Availability 2036
Brief Description
Widen Buena Vista Street from North City Boundary to Oakland Avenue toward the adopted ultimate cross-section, including approximately 1,000 linear feet of full-width improvements and approximately 560 linear feet of half-street widening, plus approximately 1,785 linear feet of sidewalk and streetlight frontage improvements and installation of approximately 13 ADA-compliant curb ramps.
ST-004 California Avenue, Florida Avenue
to Devonshire Avenue – Sidewalks &
Streetlights
Department Public Works
Category Bridges, Streets, & Traffic
Location On California Avenue between
Florida Avenue and Devonshire
Avenue
Size/Scope 405 LF sidewalk & streetlight
frontage; standard in-ROW
improvements.
Total Cost $27,540
New Dev. % 40%
Availability 2036
Brief Description
Construct and upgrade sidewalks and street lighting along California Avenue from Florida Avenue to Devonshire Avenue, including approximately 405 linear feet of frontage
improvements.
ST-005 California Avenue, Devonshire
Avenue to Menlo Avenue – Half Street
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On California Avenue between
Devonshire Avenue and Menlo
Avenue
Size/Scope 2,574 LF half-widening, 1 ADA
curb ramp; standard in-ROW
improvements.
Total Cost $441,145
New Dev. % 65%
Availability 2036
Brief Description
Widen one side of California Avenue from Devonshire Avenue to Menlo Avenue, including approximately 2,574 linear feet of halfstreet widening and installation of approximately 1 ADAcompliant curb ramp. 301
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-006 Cawston Avenue, Esplanade
Avenue to Florida Avenue – Half Street
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Cawston Avenue between
Esplanade Avenue and Florida
Avenue
Size/Scope 2,009 LF half-widening, 3,054
LF sidewalk & streetlight
frontage; standard in-ROW
improvements.
Total Cost $544,180
New Dev. % 25%
Availability 2036
Brief Description
Widen one side of Cawston Avenue from Esplanade Avenue to Florida Avenue, including approximately 2,009 linear feet of halfstreet widening and approximately 3,054 linear feet of sidewalk and streetlight frontage improvements.
ST-007 Chambers Street, Lyon Avenue to
State Street – Half Street Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Chambers Street between
Lyon Avenue and State Street
Size/Scope 1,454 LF of half-widening, 298
LF sidewalk & streetlight
frontage, 1 ADA curb ramp;
standard in-ROW.
Total Cost $273,809
New Dev. % 25%
Availability 2036
Brief Description
Widen one side of Chambers Street from Lyon Avenue to State Street, including approximately 1,454 linear feet of half-street widening and approximately 298 linear feet of sidewalk and streetlight frontage improvements, with installation of approximately 1 ADA-compliant curb ramp.
ST-008 Charlton Avenue, Park Avenue to
Ramona Expressway – Half Street
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Charlton Avenue between
Park Avenue and Ramona
Expressway
Size/Scope half-street widening; sidewalk
& streetlight infill; drainage as
needed.
Total Cost $513,272
New Dev. % 25%
Availability 2036
Brief Description
Widen one side of Charlton Avenue from Park Avenue to Ramona Expressway, including approximately 1,281 linear feet of halfstreet widening and approximately 2,628 linear feet of sidewalk and streetlight frontage improvements, with installation of approximately 12 ADA-compliant curb ramps.
302
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-009 Columbia Street, Park Avenue to
Florida Avenue – Corridor Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Columbia Street between
Park Avenue and Florida
Avenue
Size/Scope 610 LF full-width & 1,140 LF of
half-widening; standard inROW
Total Cost $395,300
New Dev. % 65%
Availability 2036
Brief Description
Widen Columbia Street from Park Avenue to Florida Avenue toward the adopted ultimate cross-section, including
approximately 610 linear feet of full-width improvements and approximately 1,140 linear feet of half-street widening.
ST-010 Devonshire Ave, State St to
Cornell St – Half Street Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Devonshire Avenue between
State Street and Cornell Street
Size/Scope 2,889 LF half-widening & 2
ADA curb ramps; standard inROW
Total Cost $503,908
New Dev. % 65%
Availability 2036
Brief Description
Widen one side of Devonshire Avenue from State Street to Cornell Street, including approximately 2,889 linear feet of halfstreet widening and installation of approximately 2 ADAcompliant curb ramps.
ST-011 Eaton Avenue, Cawston Avenue to
Palm Avenue – Half Street Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Eaton Avenue between
Cawston Avenue and Palm
Avenue
Size/Scope 4,539 LF half-widening; 3,864
LF sidewalk & streetlight
frontage; 3 ADA curb ramps;
standard in-ROW
Total Cost $1,053,034
New Dev. % 25%
Availability 2036
Brief Description
Widen one side of Eaton Avenue from Cawston Avenue to Palm Avenue, including approximately 4,539 linear feet of half-street widening and approximately 3,864 linear feet of sidewalk and streetlight frontage improvements, with installation of approximately 3 ADA-compliant curb ramps.
303
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-012 Fisher Street, Poplar Street to
Simpson Road – Full Street Improvements
Department Public Works
Category Bridges, Streets, & Traffic
Location On Fisher Street between
Poplar Street and Simpson Road
Size/Scope 1,120 LF full-width; 2 ADA curb
ramps; standard in-ROW
Total Cost $795,040
New Dev. % 80%
Availability 2036
Brief Description
Widen Fisher Street from Poplar Street to Simpson Road to the adopted ultimate cross-section, including approximately 1,120 linear feet of full-width improvements and installation of approximately 2 ADA-compliant curb ramps
ST-013 Fruitvale Avenue, Cawston
Avenue to State Street – Half Street
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Fruitvale Avenue between
Cawston Avenue and State
Street
Size/Scope 3,164 LF half-widening; 1,677
LF sidewalk & streetlight
frontage; 1 ADA curb ramp;
standard in-ROW
Total Cost $654,006
New Dev. % 25%
Availability 2036
Brief Description
Construct and upgrade sidewalks and street lighting along Girard Street from Park Avenue to Devonshire Avenue, including approximately 4,248 linear feet of frontage improvements and installation of approximately 6 ADA-compliant curb ramps.
ST-014 Girard Street, Park Avenue to
Devonshire Avenue – Sidewalks &
Streetlights
Department Public Works
Category Bridges, Streets, & Traffic
Location On Girard Street between Park
Avenue and Devonshire Avenue
Size/Scope 4,248 LF sidewalk & streetlight
frontage; 6 ADA curb ramps;
standard in-ROW
Total Cost $348,864
New Dev. % 25%
Availability 2036
Brief Description
Construct and upgrade sidewalks and street lighting along Girard Street from Park Avenue to Devonshire Avenue, including approximately 4,248 linear feet of frontage improvements and installation of approximately 6 ADA-compliant curb ramps. 304
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-015 Girard Street, Florida Avenue to
Devonshire Avenue – Sidewalks &
Streetlights
Department Public Works
Category Bridges, Streets, & Traffic
Location On Girard Street between
Florida Avenue and Devonshire
Avenue
Size/Scope 1,563 LF sidewalk & streetlight
frontage; standard in-ROW
Total Cost $106,284
New Dev. % 25%
Availability 2036
Brief Description
Construct and upgrade sidewalks and street lighting along Girard Street from Florida Avenue to Devonshire Avenue, including approximately 1,563 linear feet of frontage improvements ST-016 Hemet Street, Ramona
Expressway to Florida Avenue – Corridor
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Hemet Street between
Ramona Expressway and
Florida Avenue
Size/Scope 1,271 LF full-width; 2,510 LF
half-widening; 1,428 LF
sidewalk & streetlight frontage;
2 ADA curb ramps; standard inROW
Total Cost $1,417,061
New Dev. % 35%
Availability 2036
Brief Description
Widen Hemet Street from Ramona Expressway to Florida Avenue toward the adopted ultimate cross-section, including
approximately 1,271 linear feet of full-width improvements and approximately 2,510 linear feet of half-street widening, plus approximately 1,428 linear feet of sidewalk and streetlight frontage improvements and installation of approximately 2 ADAcompliant curb ramps ST-017 Kirby Street, Esplanade Avenue to
Florida Avenue – Corridor Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Kirby Street between
Esplanade Avenue and Florida
Avenu
Size/Scope 510 LF full-widening & 1,986 LF
half-widening; standard inROW
Total Cost $503,505
New Dev. % 65%
Availability 2036
Brief Description
Widen Kirby Street from Esplanade Avenue to Florida Avenue toward the adopted ultimate cross-section, including
approximately 510 LF full widening and 1,986 LF half-widening 305
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-018 Lake Street, Ramona Expressway
to Florida Avenue – Half Street Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Lake Street between
Ramona Expressway and
Florida Avenue
Size/Scope 1,236 LF half-widening;
standard in-ROW
Total Cost $207,030
New Dev. % 65%
Availability 2036
Brief Description
Widen one side of Lake Street from Ramona Expressway to Florida Avenue, including approximately 1,236 linear feet of halfstreet widening.
ST-019 Lincoln Avenue, Park Avenue to
City Limits – Corridor Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Lincoln Avenue between
Park Avenue and the City Limits
Size/Scope 1,037 LF full-widening; 1,125
LF half-widening; 2,464 LF
sidewalk & streetlight frontage;
12 ADA curb ramps; standard
in-ROW
Total Cost $823,384
New Dev. % 25%
Availability 2036
Brief Description
Widen Lincoln Avenue from Park Avenue to the City Limits toward the adopted ultimate cross-section, including
approximately 1,037 linear feet of full-width widening and approximately 1,125 linear feet of half-street widening, plus approximately 2,464 linear feet of sidewalk and streetlight frontage improvements and installation of approximately 12 ADA-compliant curb ramps.
ST-020 Lyon Avenue, Esplanade Avenue
to Florida Avenue – Corridor Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Lyon Avenue between
Esplanade and Florida Avenue
Size/Scope 3,180 LF full-widening; 2,252
LF half-widening; 10 ADA curb
ramps; standard in-ROW
Total Cost $1,542,510
New Dev. % 65%
Availability 2036
Brief Description
Widen Lyon Avenue from Esplanade Avenue to Florida Avenue toward the adopted ultimate cross-section, including
approximately 3,180 linear feet of full-width widening and approximately 2,252 linear feet of half-street widening, and installation of approximately 10 ADA-compliant curb ramps. 306
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-021 Menlo Avenue, Rose Avenue to
Cawston Avenue – Full Street
Improvements
Department Public Works
Category Bridges, Streets, & Traffic
Location On Menlo Avenue between Rose
Avenue and Cawston Avenue
Size/Scope 1,685 LF full-width; standard
in-ROW
Total Cost $1,166,020
New Dev. % 80%
Availability 2036
Brief Description
Widen Menlo Avenue from Rose Avenue to Cawston Avenue to the adopted ultimate cross-section, including approximately 1,685 linear feet of full-width improvements.
ST-022 Menlo Avenue, Cawston Avenue
to State Street – Corridor Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Menlo Avenue between
Cawston Avenue and State
Street
Size/Scope 1,133 LF sidewalk & streetlight
frontage & 8 ADA curb ramps;
standard in-ROW
Total Cost $1,260,702
New Dev. % 25%
Availability 2036
Brief Description
Widen Menlo Avenue from Cawston Avenue to State Street
toward the adopted ultimate cross-section, including
approximately 1,815 linear feet of full-width widening and approximately 2,959 linear feet of half-street widening, plus approximately 1,133 linear feet of sidewalk and streetlight frontage improvements and installation of approximately 8 ADAcompliant curb ramps.
ST-023 Meridian Street, Washington
Avenue to Park Avenue – Half Street
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Meridian Street between
Washington Avenue and Park
Avenue
Size/Scope 1,870 LF half-widening; 1,550
LF sidewalk & streetlight
frontage; 6 ADA curb ramps;
standard in-ROW
Total Cost $478,625
New Dev. % 25%
Availability 2036
Brief Description
Widen one side of Meridian Street from Washington Avenue to Park Avenue, including approximately 1,870 linear feet of halfstreet widening and approximately 1,550 linear feet of sidewalk and streetlight frontage improvements, with installation of approximately 6 ADA-compliant curb ramps.
307
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-024 Mountain Avenue, Hemet Street to
City Limits – Half Street Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Mountain Avenue between
Hemet Street and the City
Limits
Size/Scope 4,210 LF half-widening; 94 LF
sidewalk & streetlight frontage;
standard in-ROW
Total Cost $711,567
New Dev. % 25%
Availability 2036
Brief Description
Widen one side of Mountain Avenue from Hemet Street to the City Limits, including approximately 4,210 linear feet of halfstreet widening and approximately 94 linear feet of sidewalk and streetlight frontage improvements.
ST-025 Myers Street, Florida Avenue to
Devonshire Avenue – Corridor Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Myers Street between
Florida Avenue and Devonshire
Avenue
Size/Scope 1,790 LF full-widening & 512 LF
half-widening; standard inROW
Total Cost $685,410
New Dev. % 65%
Availability 2036
Brief Description
Widen Myers Street from Florida Avenue to Devonshire Avenue toward the adopted ultimate cross-section, including
approximately 1,790 linear feet of full-width widening and approximately 512 linear feet of half-street widening.
ST-026 Walden Weaver Road, Stetson
Avenue to Devonshire Avenue – Corridor
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Walden Weaver Road
between Stetson Avenue and
Devonshire Avenue
Size/Scope 6,500 LF full-width & 3,570 LF
half-widening; standard inROW
Total Cost $5,095,975
New Dev. % 65%
Availability 2036
Brief Description
Widen Walden Weaver Road from Stetson Avenue to Devonshire Avenue toward the adopted ultimate cross-section, including approximately 6,500 linear feet of full-width improvements and approximately 3,570 linear feet of half-street widening. 308
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-027 Newport Road, State Street to East
City Limits – Sidewalks & Streetlights
Department Public Works
Category Bridges, Streets, & Traffic
Location On Newport Road between
State Street and the East City
Limits
Size/Scope 2,600 LF sidewalk & streetlight
frontage; standard in-ROW
Total Cost $176,800
New Dev. % 25%
Availability 2036
Brief Description
Construct and upgrade sidewalks and street lighting along Newport Road from State Street to the East City Limits, including approximately 2,600 linear feet of frontage improvements.
ST-028 Stetson Avenue, California
Avenue to Walden Weaver Road – Full
Width Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Stetson Avenue between
California Avenue and Walden
Weaver Road
Size/Scope 9,250 LF full-widening; 8 ADA
curb ramps; standard in-ROW
Total Cost $3,178,750
New Dev. % 80%
Availability 2036
Brief Description
Widen Stetson Avenue from California Avenue to Walden Weaver Road to provide the adopted ultimate cross-section, including approximately 9,250 linear feet of full-width widening and installation of approximately 8 ADA-compliant curb ramps.
ST-029 Palm Avenue, Esplanade Avenue
to Florida Avenue – Corridor Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Palm Avenue between
Esplanade Avenue and Florida
Avenue
Size/Scope 2,630 LF of full-widening; 4,480
LF of half-widening; 520 LF
sidewalk & streetlight frontage;
standard in-ROW
Total Cost $1,666,810
New Dev. % 25%
Availability 2036
Brief Description
Widen Palm Avenue from Esplanade Avenue to Florida Avenue toward the adopted ultimate cross-section, including
approximately 2,630 linear feet of full-width widening and approximately 4,480 linear feet of half-street widening, plus approximately 520 linear feet of sidewalk and streetlight frontage improvements.
309
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-030 Park Avenue, Hewitt Street to
Black Walnut Drive – Corridor Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Park Avenue between
Hewitt Street and Black Walnut
Drive
Size/Scope 5,482 LF full-widening; 5,703
LF half-widening; 1,001 LF
sidewalk & streetlight frontage;
33 ADA curb ramps; standard
in-ROW
Total Cost $3,189,790
New Dev. % 25%
Availability 2036
Brief Description
Widen Park Avenue from Hewitt Street to Black Walnut Drive toward the adopted ultimate cross-section, including
approximately 5,482 linear feet of full-width widening and approximately 5,703 linear feet of half-street widening, plus approximately 1,001 linear feet of sidewalk and streetlight frontage improvements and installation of approximately 33 ADA-compliant curb ramps.
ST-031 Celeste Road, Old Warren Road to
Myers Street – Full Street Improvements
Department Public Works
Category Bridges, Streets, & Traffic
Location On Celeste Road between Old
Warren Road and Myers Street
Size/Scope 2,650 LF of full-width; standard
in-ROW
Total Cost $1,833,800
New Dev. % 80%
Availability 2036
Brief Description
Widen Celeste Road from Old Warren Road to Myers Street to the adopted ultimate cross-section, including approximately 2,650 linear feet of full-width improvements.
ST-032 San Jacinto Street, South City
Limits – Half Street Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On San Jacinto Street, South City
Limits
Size/Scope 5,910 LF half-widening;
standard in-ROW
Total Cost $989,925
New Dev. % 65%
Availability 2036
Brief Description
Widen one side of San Jacinto Street toward the South City Limits, including approximately 5,910 linear feet of half-street widening.
310
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-033 Santa Fe Street, North City Limits
to Date Street – Half Street Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Santa Fe Street between the
North City Limits and Date
Street
Size/Scope 3,600 LF of half-widening;
1,246 LF sidewalk & streetlight
frontage; standard in-ROW
Total Cost $687,728
New Dev. % 25%
Availability 2036
Brief Description
Widen one side of Santa Fe Street from the North City Limits to Date Street, including approximately 3,600 linear feet of halfstreet widening and approximately 1,246 linear feet of sidewalk and streetlight frontage improvements.
ST-034 Soboba Street, North City Limits
to Florida Avenue – Half Street Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Soboba Street between the
North City Limits and Florida
Avenue
Size/Scope 5,770 LF half-widening;
standard in-ROW
Total Cost $966,475
New Dev. % 65%
Availability 2036
Brief Description
Widen one side of Soboba Street from the North City Limits to Florida Avenue, including approximately 5,770 linear feet of halfstreet widening.
ST-035 State Street, Domenigoni Parkway
to Newport Road – Corridor Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On State Street between
Domenigoni Parkway and
Newport Road.
Size/Scope 3,165 LF full-widening & 3,070
LF half-widening; standard inROW
Total Cost $1,574,500
New Dev. % 65%
Availability 2036
Brief Description
Widen State Street from Domenigoni Parkway to Newport Road toward the adopted ultimate cross-section, including
approximately 3,165 linear feet of full-width widening and approximately 3,070 linear feet of half-street widening. 311
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-036 Stetson Avenue, Walden Weaver
Road to Cawston Avenue – Full Width
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Stetson Avenue between
Walden Weaver Road and
Cawston Avenue
Size/Scope 1,280 LF full-widening;
standard in-ROW
Total Cost $428,800
New Dev. % 80%
Availability 2036
Brief Description
Widen Stetson Avenue from Walden Weaver Road to Cawston Avenue to provide the adopted ultimate cross-section, including approximately 1,280 linear feet of full-width widening.
ST-037 Thornton Avenue, Fisher Street to
Sanderson Avenue – Half Street Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Thornton Avenue between
Fisher Street and Sanderson
Avenue
Size/Scope 2,590 LF half-widening;
standard in-ROW
Total Cost $433,825
New Dev. % 65%
Availability 2036
Brief Description
Widen one side of Thornton Avenue from Fisher Street to Sanderson Avenue, including approximately 2,590 linear feet of half-street widening.
ST-038 Whittier Avenue, Cawston Avenue
to Sanderson Avenue – Full Street
Improvements
Department Public Works
Category Bridges, Streets, & Traffic
Location On Whittier Avenue between
Cawston Avenue and Sanderson
Avenue
Size/Scope 2,600 LF full-width; standard
in-ROW
Total Cost $1,799,200
New Dev. % 80%
Availability 2036
Brief Description
Widen Whittier Avenue from Cawston Avenue to Sanderson
Avenue to the adopted ultimate cross-section, including approximately 2,600 linear feet of full-width improvements. 312
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-039 Yale Street, Park Avenue to
Florida Avenue – Sidewalks & Streetlights
Department Public Works
Category Bridges, Streets, & Traffic
Location On Yale Street between Park
Avenue and Florida Avenue
Size/Scope 5,720 LF sidewalk & streetlight
frontage; 7 ADA curb ramps;
standard in-ROW
Total Cost $458,960
New Dev. % 25%
Availability 2036
Brief Description
Construct and upgrade sidewalks and street lighting along Yale Street from Park Avenue to Florida Avenue, including
approximately 5,720 linear feet of frontage improvements and installation of approximately 7 ADA-compliant curb ramps.
ST-040 Citywide – Right-of-Way
Acquisition
Department Public Works
Category Bridges, Streets, & Traffic
Location Citywide along designated
corridors
Size/Scope Citywide—right-of-way
acquisition for designated
roadway segments per the
adopted circulation network.
Total Cost $6,907,509
New Dev. % 80%
Availability 2036
Brief Description
Acquire right-of-way along designated corridors to deliver the adopted ultimate cross-sections and approach transitions.
ST-041 Citywide – Traffic Signal
Upgrade/Coordination
Department Public Works
Category Bridges, Streets, & Traffic
Location Citywide at selected signalized
intersections
Size/Scope Citywide—signal hardware,
detection, communications, &
timing upgrades at selected
intersections
Total Cost $1,000,000
New Dev. % 40%
Availability 2036
Brief Description
Upgrade and coordinate existing traffic signals at priority intersections to meet current standards and improve operations, including new signal.
313
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-042 State Street at Devonshire Avenue
– Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location State Street at Devonshire
Avenue
Size/Scope New traffic signal & associated
intersection improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at State Street and Devonshire Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-043 State Street at Whittier Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location State Street at Whittier Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at State Street and Whittier Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-044 Lyon Avenue at Devonshire
Avenue – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Lyon Avenue at Devonshire
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Lyon Avenue and Devonshire Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required. 314
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-045 Lyon Avenue at Menlo Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Lyon Avenue at Menlo Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Lyon Avenue and Menlo Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-046 Acacia Avenue at Palm Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Acacia Avenue at Palm Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Acacia Avenue and Palm Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-047 Kirby Street at Menlo Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Kirby Street at Menlo Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Kirby Street and Menlo Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required. 315
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-048 State Street at Johnston Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location State Street at Johnston Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at State Street and Johnston Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-049 Sanderson Avenue at Johnston
Avenue – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Sanderson Avenue at Johnston
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Sanderson Avenue and Johnston Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-050 Kirby Street at Johnston Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Kirby Street at Johnston Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Kirby Street and Johnston Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required. 316
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-051 California Avenue at Florida
Avenue – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location California Avenue at Florida
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at California Avenue and Florida Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-052 Palm Avenue at Menlo Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Palm Avenue at Menlo Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Palm Avenue and Menlo Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-053 Santa Fe Street at Stetson Avenue
– Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Santa Fe Street at Stetson
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Santa Fe Street and Stetson Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required. 317
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-054 Warren Road at Devonshire
Avenue – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Warren Road at Devonshire
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Warren Road and Devonshire Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-055 Warren Road at Stetson Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Warren Road at Stetson Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Warren Road and Stetson Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-056 Fisher Street at Stetson Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Fisher Street at Stetson Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Fisher Street and Stetson Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required. 318
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-057 Fisher Street at Harrison Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Fisher Street at Harrison
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Fisher Street and Harrison Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-058 Dartmouth Street at Florida
Avenue – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Dartmouth Street at Florida
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Dartmouth Street and Florida Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-059 Hemet Street at Florida Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Hemet Street at Florida Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Hemet Street and Florida Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required. 319
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-060 Devonshire Avenue at Myers
Street – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Devonshire Avenue at Myers
Street
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Devonshire Avenue and Myers Street to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-061 Cawston Avenue at Florida
Avenue – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Cawston Avenue at Florida
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Cawston Avenue and Florida Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-062 Cawston Avenue at Devonshire
Avenue – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Cawston Avenue at Devonshire
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Cawston Avenue and Devonshire Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required. 320
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-063 Sanderson Avenue at Fruitvale
Avenue – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Sanderson Avenue at Fruitvale
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Sanderson Avenue and Fruitvale Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-064 State Street at Fruitvale Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location State Street at Fruitvale Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at State Street and Fruitvale Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-065 State Street at Mayberry Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location State Street at Mayberry
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at State Street and Mayberry Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required. 321
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-066 Santa Fe Street at Acacia Avenue
– Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Santa Fe Street at Acacia
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Santa Fe Street and Acacia Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-067 Santa Fe Street at Devonshire
Avenue – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Santa Fe Street at Devonshire
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Santa Fe Street and Devonshire Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-068 San Jacinto Street at Acacia
Avenue – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location San Jacinto Street at Acacia
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at San Jacinto Street and Acacia Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required. 322
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-069 Soboba Street at Mountain Avenue
– Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Soboba Street at Mountain
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Soboba Street and Mountain Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-070 Florida Avenue at Lake Street –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Florida Avenue at Lake Street
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Florida Avenue and Lake Street to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-071 Sanderson Avenue at Wentworth
Drive – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Sanderson Avenue at
Wentworth Drive
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Sanderson Avenue and Wentworth Drive to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required. 323
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-072 Palm Avenue at Devonshire
Avenue – Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location Palm Avenue at Devonshire
Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $800,000
New Dev. % 80%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at Palm Avenue and Devonshire Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-073 State Street at Thornton Avenue –
Traffic Signal
Department Public Works
Category Bridges, Streets, & Traffic
Location State Street at Thornton Avenue
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $400,000
New Dev. % 40%
Availability 2036
Brief Description
Install a new traffic signal and intersection improvements at State Street and Thornton Avenue to achieve the ultimate lane layout, including poles/mast arms, signal heads,
controller/cabinet, vehicle detection, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
ST-074 Citywide – Future Traffic
Signalization
Department Public Works
Category Bridges, Streets, & Traffic
Location Citywide at selected
intersections
Size/Scope New traffic signal and
associated intersection
improvements
Total Cost $1,000,000
New Dev. % 80%
Availability 2036
Brief Description
Plan, design, and implement future traffic signals at priority intersections citywide to meet the adopted ultimate lane layouts and current standards, including controllers/cabinets, detection, communications, ADA pedestrian push buttons, signing/striping, and lighting adjustments as required.
324
14.E.
Prepared by Revenue & Cost Specialists, LLC
ST-075 Hemet Street Bridge over Charlton
Avenue – Bridge / Structure
Department Public Works
Category Bridges, Streets, & Traffic
Location Hemet Street over Charlton
Avenue
Size/Scope Bridge/structure and approach
improvements.
Total Cost $5,000,000
New Dev. % 60%
Availability 2036
Brief Description
Construct a bridge at Hemet Street over Charlton Avenue to deliver the adopted cross-section through the structure and approaches, including structure, approach roadway, drainage, signing/striping, and safety features.
ST-076 Highway 79 Bridge over
Devonshire Avenue – Bridge / Structure
Department Public Works
Category Bridges, Streets, & Traffic
Location Highway 79 over Devonshire
Avenue
Size/Scope New bridge/structure and
approach improvements.
Total Cost $5,000,000
New Dev. % 100%
Availability 2036
Brief Description
Construct a new bridge on Highway 79 over Devonshire Avenue to deliver the adopted cross-section through the structure and approaches, including structure, approach roadway, drainage, signing/striping, and safety features.
ST-077 Highway 79 Bridge over Stetson
Avenue – Bridge / Structure
Department Public Works
Category Bridges, Streets, & Traffic
Location Highway 79 over Stetson
Avenue
Size/Scope New bridge/structure and
approach improvements.
Total Cost $5,000,000
New Dev. % 100%
Availability 2036
Brief Description
Construct a new bridge on Highway 79 over Stetson Avenue to deliver the adopted cross-section through the structure and approaches, including the bridge structure, approach roadway, drainage, signing and striping, safety features, lighting adjustments, and utility coordination.
ST-078 Buena Vista Street, Johnston
Avenue to Chambers Street – Sidewalks &
Streetlights
Department Public Works
Category Bridges, Streets, & Traffic
Location On Buena Vista Street between
Johnston Avenue and Chambers
Street
Brief Description
Construct and upgrade sidewalks and street lighting along Buena Vista Street from Johnston Avenue to Chambers Street, including approximately 1,730 linear feet of frontage improvements and installation of approximately 2 ADA-compliant curb ramps. Work includes pavement improvements where required, new curb and gutter, drainage improvements, signing and striping, driveway and access tie-ins, temporary traffic control, and restoration within the project limits.
325
14.E.
Prepared by Revenue & Cost Specialists, LLC
Size/Scope 1,730 LF sidewalk & streetlight
frontage; 2 ADA curb ramps;
standard in-ROW
improvements.
Total Cost $309,775
New Dev. % 25%
Availability 2036
ST-079 Cawston Avenue, Florida Avenue
to Cloudywing Road – Corridor Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Cawston Avenue between
Florida Avenue and Cloudywing
Road
Size/Scope 2,173 LF full-width; 1,190 LF
half-widening; 1,884 LF
sidewalk & streetlight frontage;
4 ADA curb ramps; standard inROW improvements.
Total Cost $2,257,936
New Dev. % 50%
Availability 2036
Brief Description
Widen Cawston Avenue from Florida Avenue to Cloudywing
Road toward the adopted ultimate cross-section, including approximately 2,173 linear feet of full-width improvements, approximately 1,190 linear feet of half-street widening, approximately 1,884 linear feet of sidewalk and streetlight frontage improvements, and installation of approximately 4 ADAcompliant curb ramps. Work includes pavement improvements where required, new curb and gutter, drainage improvements, signing and striping, driveway and access tie-ins, temporary traffic control, and restoration within the project limits.
ST-080 Devonshire Avenue, California
Avenue to Sanderson Avenue – Half Street
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Devonshire Avenue between
California Avenue and
Sanderson Avenue
Size/Scope 7,037 LF half-widening; 3,343
LF sidewalk & streetlight
frontage; 16 ADA curb ramps;
standard in-ROW
improvements.
Total Cost $3,077,348
New Dev. % 65%
Availability 2036
Brief Description
Widen one side of Devonshire Avenue from California Avenue to Sanderson Avenue, including approximately 7,037 linear feet of half-street widening, approximately 3,343 linear feet of sidewalk and streetlight frontage improvements, and installation of approximately 16 ADA-compliant curb ramps. Work includes pavement improvements where required, new curb and gutter, drainage improvements, signing and striping, driveway and access tie-ins, temporary traffic control, and restoration within the project limits.
ST-081 Lyon Avenue, Florida Avenue to
Stetson Avenue – Half Street Widening
Department Public Works
Category Bridges, Streets, & Traffic
Brief Description
Widen one side of Lyon Avenue from Florida Avenue to Stetson Avenue, including approximately 4,410 linear feet of half-street widening and approximately 332 linear feet of sidewalk and streetlight frontage improvements. Work includes pavement improvements where required, new curb and gutter, drainage improvements, signing and striping, driveway and access tie-ins, 326
14.E.
Prepared by Revenue & Cost Specialists, LLC
Location On Lyon Avenue between
Florida Avenue and Stetson
Avenue
Size/Scope 4,410 LF half-widening; 332 LF
sidewalk & streetlight frontage;
standard in-ROW
improvements.
Total Cost $1,532,960
New Dev. % 65%
Availability 2036
temporary traffic control, and restoration within the project limits.
ST-082 Lyon Avenue, Stetson Avenue to
Salt Creek – Full Width Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Lyon Avenue between
Stetson Avenue and Salt Creek
Size/Scope 3,930 LF full-width widening;
standard in-ROW
improvements.
Total Cost $2,719,560
New Dev. % 80%
Availability 2036
Brief Description
Widen Lyon Avenue from Stetson Avenue to Salt Creek to
provide the adopted ultimate cross-section, including
approximately 3,930 linear feet of full-width widening. Work includes pavement improvements where required, new curb and gutter, drainage improvements, signing and striping, driveway and access tie-ins, temporary traffic control, and restoration within the project limits.
ST-083 Menlo Avenue, State Street to Park
Avenue – Sidewalks & Streetlights
Department Public Works
Category Bridges, Streets, & Traffic
Location On Menlo Avenue between
State Street and Park Avenue
Size/Scope 270 LF half-widening; 4,344 LF
sidewalk & streetlight frontage;
7 ADA curb ramps; standard inROW improvements.
Total Cost $1,010,742
New Dev. % 25%
Availability 2036
Brief Description
Construct and upgrade sidewalks and street lighting along Menlo Avenue from State Street to Park Avenue, including
approximately 270 linear feet of half-street widening,
approximately 4,344 linear feet of sidewalk and streetlight frontage improvements, approximately 1,804 linear feet of additional frontage improvements, and installation of
approximately 7 ADA-compliant curb ramps. Work includes pavement improvements where required, new curb and gutter, drainage improvements, signing and striping, driveway and access tie-ins, temporary traffic control, and restoration within the project limits.
ST-084 Meridian Street, Park Avenue to
Florida Avenue – Half Street Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Meridian Street between
Park Avenue and Florida
Avenue
Size/Scope 269 LF half-widening; 242 LF
sidewalk & streetlight frontage;
Brief Description
Widen one side of Meridian Street from Park Avenue to Florida Avenue, including approximately 269 linear feet of half-street widening, approximately 242 linear feet of sidewalk and streetlight frontage improvements, and installation of
approximately 5 ADA-compliant curb ramps. Work includes pavement improvements where required, new curb and gutter, drainage improvements, signing and striping, driveway and access tie-ins, temporary traffic control, and restoration within the project limits.
327
14.E.
Prepared by Revenue & Cost Specialists, LLC
5 ADA curb ramps; standard inROW improvements.
Total Cost $192,890
New Dev. % 65%
Availability 2036
ST-085 Palm Avenue, Florida Avenue to
South of Chambers Street – Corridor
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Palm Avenue between
Florida Avenue and south of
Chambers Street
Size/Scope 2,560 LF full-width; 5,198 LF
half-widening; standard inROW improvements.
Total Cost $3,512,850
New Dev. % 80%
Availability 2036
Brief Description
Widen Palm Avenue from Florida Avenue to south of Chambers Street toward the adopted ultimate cross-section, including approximately 2,560 linear feet of full-width improvements and approximately 5,198 linear feet of half-street widening. Work includes pavement improvements where required, new curb and gutter, drainage improvements, signing and striping, driveway and access tie-ins, temporary traffic control, and restoration within the project limits.
ST-086 Santa Fe Street, Devonshire
Avenue to Florida Avenue – Half Street
Widening
Department Public Works
Category Bridges, Streets, & Traffic
Location On Santa Fe Street between
Devonshire Avenue and Florida
Avenue
Size/Scope 7,920 LF half-widening; 640 LF
sidewalk & streetlight frontage;
standard in-ROW
improvements.
Total Cost $2,760,400
New Dev. % 65%
Availability 2036
Brief Description
Widen one side of Santa Fe Street from Devonshire Avenue to Florida Avenue, including approximately 7,920 linear feet of halfstreet widening and approximately 640 linear feet of sidewalk and streetlight frontage improvements. Work includes pavement improvements where required, new curb and gutter, drainage improvements, signing and striping, driveway and access tie-ins, temporary traffic control, and restoration within the project limits.
ST-087 Thornton Avenue, Lyon Avenue to
Santa Fe Street – Sidewalks & Streetlights
Department Public Works
Category Bridges, Streets, & Traffic
Location On Thornton Avenue between
Lyon Avenue and Santa Fe
Street
Size/Scope 5,090 LF sidewalk & streetlight
frontage; 1 ADA curb ramp;
Brief Description
Construct and upgrade sidewalks and street lighting along Thornton Avenue from Lyon Avenue to Santa Fe Street, including approximately 5,090 linear feet of frontage improvements, approximately 330 linear feet of additional frontage
improvements, and installation of approximately 1 ADAcompliant curb ramp. Work includes pavement improvements where required, new curb and gutter, drainage improvements, signing and striping, driveway and access tie-ins, temporary traffic control, and restoration within the project limits. 328
14.E.
Prepared by Revenue & Cost Specialists, LLC
standard in-ROW
improvements.
Total Cost $885,015
New Dev. % 25%
Availability 2036
ST-088 Warren Road – Half-Street
Widening, Local Share (Non-TUMF
Scope)
Department Public Works
Category Bridges, Streets, & Traffic
Location Warren Road corridor, City of
Hemet (local non-TUMF
widening segments)
Size/Scope Half-street widening, local DIF
share (non-TUMF scope)
Total Cost $2,499,600
New Dev. % 65%
Availability 2036
Brief Description
Provides the local non-TUMF share of half-street widening improvements along Warren Road. Scope includes one-side roadway widening, curb and gutter, sidewalk, pavement,
drainage, signing and striping, and related in-ROW
improvements attributable to new development. TUMFeligible portions are funded separately through the Western Riverside Council of Governments.
ST-089 Warren Road Bridge Widening –
Bridge/Structure (Local DIF Share)
Department Public Works
Category Bridges, Streets, & Traffic
Location Warren Road bridge structure,
City of Hemet
Size/Scope Bridge/structure widening,
local DIF share
Total Cost $5,000,000
New Dev. % 60%
Availability 2036
Brief Description
Provides the local DIF share of bridge/structure widening along Warren Road. Scope includes bridge deck expansion, structural improvements, approach work, and related
improvements necessary to accommodate growthgenerated traffic volumes. The local DIF share reflects the portion of bridge costs attributable to new development after TUMF coordination.
329
14.E.
Prepared by Revenue & Cost Specialists, LLC
Flood Control
Flood Control projects implement master-planned regional drainage improvements across five hydrologic basins to maintain the adopted storm drainage level of service as development increases impervious surface area and runoff.
Program Cost Allocation
Gross DIF-Eligible Program Cost $125,923,220
Less: Fund Balance Credit (6,864,347)
Net DIF-Eligible Program Cost $56,097,263
FC-001 Little Lake Basin Regional
Drainage Improvements
Department Public Works
Category Flood Control (Storm Drainage
Facilities)
Location Little Lake Basin within the City
of Hemet, including trunk and
lateral corridors along the
master-planned Line A, Line B,
Line C, Line D, and Line E
alignments, as shown in the
Little Lake Master Drainage
Plan.
Size/Scope Construction and upsizing of
master-planned storm drain
facilities in the Little Lake Basin,
including the Line A Storm
Drain System (with Lines A-2
and A-4), the Line B Storm
Drain System (with Line B-4),
the Line C Storm Drain System
(with Line C-1), the Line D
Storm Drain System
Total Cost $18,030,385
New Dev. % 50%
Availability 2026–2036
Brief Description
This project implements the regional storm drainage system for the Little Lake Basin as identified in the Little Lake Master Drainage Plan. The improvements include the primary trunk mains and laterals needed to collect runoff from existing neighborhoods and planned development, and to convey �lows toward the Little Lake outfall. The project addresses existing conveyance constraints, reduces localized flooding at key roadways, and provides the additional hydraulic capacity needed to serve buildout within the Little Lake Basin while maintaining the City’s adopted level of storm drainage service.
330
14.E.
Prepared by Revenue & Cost Specialists, LLC
FC-002 Southwest Hemet Basin Regional
Drainage Improvements
Department Public Works
Category Flood Control (Storm Drainage
Facilities)
Location Southwest Hemet Basin within
the City of Hemet, including
storm drain corridors along the
master-planned Line A and Line
B alignments, their associated
laterals, and other Southwest
Basin corridors as shown in the
Southwest Hemet Master
Drainage Plan.
Size/Scope Construction of the masterplanned Southwest Basin storm drain network, including Line A
and laterals A-1 through A-4,
Line B and laterals B-1 through
B-6, and additional basin
conveyance elements such as
Lines C, D, F, H, I, J, K, L, M, N, O,
and P, as identified in the
Southwest Hemet Master
Drainage Plan and summarized
in Appendix J.
Total Cost $28,468,776
New Dev. % 50%
Availability 2026–2036
Brief Description
This project implements the regional storm drainage system for the Southwest Hemet Basin as identified in the Southwest Hemet Master Drainage Plan. The improvements provide the trunk and lateral facilities required to convey runoff from existing and future development in the southwestern portion of the City to downstream regional outfalls. The project addresses existing gaps in the system, mitigates localized flooding along key corridors, and provides the hydraulic capacity needed to serve long-term residential and commercial buildout in the Southwest Basin.
331
14.E.
Prepared by Revenue & Cost Specialists, LLC
FC-003 San Jacinto Basin Regional
Drainage Improvements
Department Public Works
Category Flood Control (Storm Drainage
Facilities)
Location Corridors within the San Jacinto
Basin that lie inside the City of
Hemet, including segments
along Florida Avenue, Menlo
Avenue, State Street, Santa Fe
Street, and Esplanade Avenue,
as shown in the San Jacinto
Valley Master Drainage Plan.
Size/Scope Construction and upsizing of
San Jacinto Basin regional
storm drain facilities serving
the City of Hemet, including
Line A (Florida Avenue Storm
Drain), Line B-1 (E. Menlo
Avenue Storm Drain), Line C-4
(Santa Fe Street Storm Drain),
Line E-2 (State Street Regional
Trunk), and Line X (W.
Esplanade Avenue Regional
Trunk), as identified in the San
Jacinto Valley Master Drainage
Plan and summarized in
Appendix J.
Total Cost $22,804,321
New Dev. % 50%
Availability 2026–2036
Brief Description
This project implements the master-planned regional storm drain facilities within the City of Hemet that are tributary to the San Jacinto Basin, as identified in the San Jacinto Valley Master Drainage Plan. The improvements provide trunk conveyance along major corridors such as Florida Avenue, Menlo Avenue, State Street, Santa Fe Street, and Esplanade Avenue, allowing stormwater generated within and upstream of the City to be safely conveyed to downstream regional facilities. The project is needed to address existing capacity limitations, reduce localized �flooding, and provide sufficient conveyance for future development within the Hemet portions of the San Jacinto Basin. 332
14.E.
Prepared by Revenue & Cost Specialists, LLC
FC-004 West Hemet Basin Regional
Drainage Improvements
Department Public Works
Category Flood Control (Storm Drainage
Facilities)
Location West Hemet Basin within the
City of Hemet, including storm
drain corridors along
Devonshire Avenue, Cawston
Avenue, and adjacent streets,
and the Devonshire Retention
Basin, as shown in the West
Hemet Master Drainage Plan.
Size/Scope Construction and upsizing of
master-planned storm drain
facilities in the West Hemet
Basin, including the Line A
system (Lines A and A-1), the
Line E system (Lines E and E-1),
the Line C system (Lines C, C-1
through C-4, C-7, and C-8), the
Line D corridor, and
improvements to the
Devonshire Retention Basin, as
identi�ied in the West Hemet
Master Drainage Plan and
summarized in Appendix J.
Total Cost $41,161,577
New Dev. % 50%
Availability 2026–2036
Brief Description
This project implements the regional storm drainage system for the West Hemet Basin as identified in the West Hemet Master Drainage Plan. The improvements include major trunk storm drains and a regional detention facility that together form the backbone of flood control for the western portion of the City. The project addresses existing capacity constraints along key corridors, provides needed storage and attenuation at the Devonshire Retention Basin, and supplies adequate conveyance capacity to serve existing development and planned growth in the West Hemet Basin.
333
14.E.
Prepared by Revenue & Cost Specialists, LLC
FC-005 Hemet Main Basin Regional
Drainage Improvements
Department Public Works
Category Flood Control (Storm Drainage
Facilities)
Location Hemet Main Basin within the
City of Hemet, including storm
drain corridors along Florida
Avenue, Stetson Avenue,
Ramona Expressway, and
adjacent streets served by the
Line A, Line B, Line C-1, and
Line D systems, as shown in the
Hemet Area Master Drainage
Plan.
Size/Scope Construction and upsizing of
master-planned regional storm
drain facilities in the Hemet
Main Basin, including the feeeligible portions of the Line A Storm Drain System (the
Florida Avenue extension and
associated Lines A-2, A-3, A-6,
and A-7), the fee-eligible
portion of the Line B Storm
Drain System (B-1 and B-2, plus
the unconstructed mainline
segment), the Line C-1 reach,
and the Line D corridors (Lines
D-1 and D-6), as identified in
the Hemet Area Master
Drainage Plan and summarized
in Appendix J.
Total Cost $15,458,161
New Dev. % 50%
Availability 2026–2036
Brief Description
This project implements the regional storm drainage system for the Hemet Main Basin as identified in the Hemet Area Master Drainage Plan. The basin includes major conveyance routes along Florida Avenue, Stetson Avenue, and Ramona Expressway that together form the City’s primary storm drain backbone. The project completes missing segments, replaces interim facilities with ultimate improvements, and enlarges undersized reaches to meet current hydrologic design criteria. These improvements are necessary to address existing flooding constraints and to provide adequate capacity for long-term development in the central and southeastern portions of the City.
334
14.E.
Prepared by Revenue & Cost Specialists, LLC
Water System Facilities
Water System Facilities projects upsize distribution mains, add storage capacity, and extend service to maintain the adopted water system level of service as development increases demand on the City-owned water system.
Program Cost Allocation
Gross DIF-Eligible Program Cost $11,013,235
Less: Fund Balance Credit —
Net DIF-Eligible Program Cost $4,827,950
WT-001 Distribution System Upgrades (4″
to 8″ Mains, Various Locations)
Department Public Works
Category Water System Facilities
Location Citywide (segments identified
at design).
Size/Scope Program total 5,000 Linear Feet
(LF) of 8-inch main (five 1,000-
LF packages).
Total Cost $786,500
New Dev. % 83.8%
Availability 2026–2036
Brief Description
Upsize undersized 4-inch distribution mains to 8-inch in growthaffected areas to increase conveyance capacity, maintain operating pressures and fire-flow reliability, and preserve the City’s established level of service as development occurs.
Improvements are limited to capacity- increasing segments; routine repair or like-for-like replacement without added capacity is excluded.
WT-002 Echo Hills 2.0 million gallons
(MG) Storage Tank
Department Public Works
Category Water System Facilities
Location Echo Hills tank site.
Size/Scope 2.0 MG welded-steel tank with
site/civil, piping, Supervisory
Control and Data Acquisition
(SCADA), and fencing.
Total Cost $4,550,000
New Dev. % 5%
Availability 2026–2036
Brief Description
Construct a new 2.0-million-gallon welded-steel storage tank at the Echo Hills site to add operational and emergency storage needed under projected growth while maintaining service standards. Only the incremental capacity attributable to growth is included in the fee program.
335
14.E.
Prepared by Revenue & Cost Specialists, LLC
WT-003 Echo Hills Distribution Main
Upsizing
Department Public Works
Category Water System Facilities
Location Echo Hills service area
(alignment per design).
Size/Scope 6,283 LF upsizing (12″ to 18″).
Total Cost $1,225,185
New Dev. % 65.5%
Availability 2026–2036
Brief Description
Upsize approximately 6,283 LF of existing 12-inch main to 18- inch in the Echo Hills area to increase distribution capacity and maintain pressures and fire-flow under growth conditions. Work includes pipe, appurtenances, services/transitions, and pavement restoration.
WT-004 Groundwater Recharge Pipeline
(Dedicated Conveyance to Park Hill)
Department Public Works
Category Water System Facilities
Location Mountain Avenue / Esplanade
Avenue area to Park Hill storage
tanks.
Size/Scope 6,653 LF transmission main
with appurtenances and tie-ins.
Total Cost $1,513,550
New Dev. % 100%
Availability 2026–2036
Brief Description
Construct a new transmission main (approximately 6,653 linear feet) to convey treated potable water from the City’s distribution system in the Mountain Avenue / Esplanade Avenue area to the Park Hill storage tanks. The project improves operational flexibility, supports pressure management, and provides transmission capacity needed to serve projected growth while maintaining the City’s established level of water service. The pipeline does not convey recharge water and does not connect to or utilize Eastern Municipal Water District recharge facilities.
WT-005 Park Hill to Florida Avenue Water
Main Upsizing (14″ → 16″, 8,200 LF)
Department Public Works
Category Water System Facilities
Location Park Hill to Florida Avenue
corridor.
Size/Scope 8,200 LF upsizing (14″ to 16″).
Total Cost $1,865,500
New Dev. % 29.6%
Availability 2026–2036
Brief Description
Upsize approximately 8,200 LF of existing 14-inch transmission main to 16-inch between Park Hill and Florida Avenue to increase capacity for projected growth while maintaining pressures and fire-flow. Work includes pipe, appurtenances, services/transitions, and pavement restoration.
336
14.E.
Prepared by Revenue & Cost Specialists, LLC
WT-006 Stetson Avenue Distribution Main
(New 12″ Corridor Segment, 5,000 LF)
Department Public Works
Category Water System Facilities
Location Stetson Avenue corridor (exact
alignment refined at design).
Size/Scope 5,000 LF of new 12″ main.
Total Cost $1,072,500
New Dev. % 100%
Availability 2026–2036
Brief Description
Install a new 12-inch distribution main along the Stetson Avenue corridor to provide additional distribution capacity required by growth and maintain the City’s level of service. Work includes pipe, appurtenances, services/transitions, and pavement restoration.
337
14.E.
Prepared by Revenue & Cost Specialists, LLC
Wastewater System Facilities
Wastewater System Facilities projects construct new collection infrastructure and upsize existing mains and lift stations to maintain the adopted wastewater system level of service as development increases sewage flows.
Program Cost Allocation
Gross DIF-Eligible Program Cost $5,621,150
Less: Fund Balance Credit —
Net DIF-Eligible Program Cost $5,443,711
SW-001 Southeast Lift Station and Force
Main
Department Public Works
Category Wastewater (Sewer) System
Facilities
Location Southeast service area
Size/Scope New lift station with associated
force main; final sizing and
controls to be confirmed at
design.
Total Cost $2,867,150
New Dev. % 100%
Availability 2026–2036
Brief Description
Construct a new lift station and force main to provide
conveyance from the Southeast growth area where gravity service is not feasible, increasing downstream capacity and maintaining level of service as development proceeds.
SW-002 Southwest Service Area – New
Trunk Sewer Extension
Department Public Works
Category Wastewater (Sewer) System
Facilities
Location Southwest service area
Size/Scope New gravity trunk main;
alignment and diameter to be
finalized through hydraulic
design.
Total Cost $1,909,050
New Dev. % 100%
Availability 2026–2036
Brief Description