k. The heating value of the digester gas fuel as measured in accordance with Condition 3.h.
l. Records of the date and time of any leaks detected from the digesters, gas piping, pressure regulators, or pressure safety valves. Records of any repair actions taken to stop the leaks and the date and time that the leaks were stopped. m. The dates and times of any ambient H2S alarms, the cause of the alarms, and any corrective actions taken to stop the H2S release.
n. Fuel Meter Calibration Records. Copies of the most recent fuel use meter calibration. o. Source test reports shall be submitted to the District within 45 days of test completion.
6. Source Testing. The following source testing provisions shall apply:
a. The permittee shall conduct source testing of air emissions and process parameters listed in Table 5 of this permit. More frequent source testing may be required if the equipment does not comply with permitted limitations or if other compliance problems, as determined by the District, occur. Source testing shall be performed on a schedule identified in Table 4, using November 16 as the anniversary date.
After the third required compliance source test, the District may, at its discretion, allow the owner or operator of the unit to perform tune-ups in lieu of source testing per the requirements of Section G of Rule 361.
b. The permittee shall submit a written source test plan to the District for approval at least thirty (30) days prior to initiation of each source test. The source test plan shall be prepared consistent with the District's Source Test Procedures Manual (revised May 1990 and any subsequent revisions). The permittee shall obtain written District approval of the source test plan prior to commencement of source testing. The District shall be notified at least ten (10) calendar days prior to the start of source testing activity to arrange for a mutually agreeable source test date when District personnel may observe the test. c. Source test results shall be submitted to the District within forty-five (45) calendar days following the date of source test completion and shall be consistent with the requirements approved within the source test plan. Source test results shall document the permittee’s compliance status with mass emission rates in Table 1 and applicable permit conditions, rules and NSPS (if applicable). For determining compliance with daily emission limits, the applicable pounds per day value in Table 1 shall be divided by 24 to convert to a "pounds per hour equivalent limit". If the source test pounds per hour result for a pollutant exceeds the "pounds per hour equivalent limit", then the source is not in compliance with the pounds per day permitted limit for the applicable pollutant. All District costs associated with the review and approval of all plans and reports and the witnessing of tests shall be paid by the permittee as provided for by District Rule 210.
Permit to Operate 08390 - R11
d. A source test for an item of equipment shall be performed on the scheduled day of testing (the test day mutually agreed to) unless circumstances beyond the control of the operator prevent completion of the test on the scheduled day. Such circumstances include mechanical malfunction of the equipment to be tested, malfunction of the source test equipment, delays in source test contractor arrival and/or set-up, or unsafe conditions on site. Except in cases of an emergency, the operator shall seek and obtain District approval before deferring or discontinuing a scheduled test, or performing maintenance on the equipment item on the scheduled test day. If the test cannot be completed on the scheduled day, then the test shall be rescheduled for another time with prior authorization by the District. Once the sample probe has been inserted into the exhaust stream of the equipment unit to be tested (or extraction of the sample has begun), the test shall proceed in accordance with the approved source test plan. In no case shall a test run be aborted except in the case of an emergency or unless approval is first obtained from the District.
Failing to perform the source test of an equipment item on the scheduled test day without a valid reason and without District's authorization shall constitute a violation of this permit. If a test is postponed due to an emergency, written documentation of the emergency event shall be submitted to the District by the close of the business day following the scheduled test day.
The timelines in a, b, and c above may be extended for good cause provided a written request is submitted to the District at least three (3) days in advance of the deadline, and approval for the extension is granted by the District.
7. Inspection and Maintenance. The permittee shall implement the District-approved Inspection and Maintenance Plan (approved January 29, 2015). The permittee shall maintain the inspection and maintenance program for the pressure regulator vents, the pressure regulator seals, and other digester gas discharge piping, valves and flanges. The contents of the plan shall include, at a minimum, details on:
a. Spare parts to be kept on site.
b. Definition of emission concentration threshold level to be used to trigger repair or replacement.
c. Method of leak detection employed.
d. Time between leak detection and repair for each component. e. Recordkeeping procedure and data reporting format to be used. f. Quality assurance procedures.
Permit to Operate 08390 - R11
8. Emission and Digester Gas Monitoring Plan. The permittee shall implement the District-approved Emission and Digester Gas Monitoring Plan (approved January 29, 2015).
The contents of the District-approved plan shall be implemented and include, at a minimum, details on:
a. The pressure regulator settings for discharging digester gas to the flare(s). b. The pressure regulator settings for atmospheric venting of digester gas. c. The setting for triggering the high gas pressure alarm of the sensor in the digester dome top.
d. The ambient monitors capable of detecting and triggering an audio alarm when H2S concentrations 10 ppmv are detected.
e. The monitoring of atmospheric venting from the digester pressure regulators. f. The methods used to maintain operative gas meters and recorders for each digester gas discharge line.
9. Consistency with Analysis. Operation under this permit shall be conducted consistent with all data, specifications and assumptions included with the application and supplements thereof (as documented in the District's project file) and the District's analyses under which this permit is issued as documented in the Permit Analyses prepared for and issued with the permit.
10. Equipment Maintenance. The equipment listed in this permit shall be properly maintained and kept in good condition at all times. The equipment manufacturer’s maintenance manual, maintenance procedures and/or maintenance checklists (if any) shall be kept on site.
11. Compliance. Nothing contained within this permit shall be construed as allowing the violation of any local, state or federal rules, regulations, air quality standards or increments.
12. Severability. In the event that any condition herein is determined to be invalid, all other conditions shall remain in force.
13. Conflict Between Permits. The requirements or limits that are more protective of air quality shall apply if any conflict arises between the requirements and limits of this permit and any other permitting actions associated with the equipment permitted herein.
14. Access to Records and Facilities. As to any condition that requires for its effective enforcement the inspection of records or facilities by the District or its agents, the permittee shall make such records available or provide access to such facilities upon notice from the District. Access shall mean access consistent with California Health and Safety Code Section 41510 and Clean Air Act Section 114A.
Permit to Operate 08390 - R11
15. Equipment Identification. Identifying tag(s) or name plate(s) shall be displayed on the equipment to show manufacturer, model number, and serial number. The tag(s) or plate(s) shall be affixed to the equipment in a permanent and conspicuous position.
16. Emission Factor Revisions. The District may update the emission factors for any calculation based on USEPA AP-42 or District emission factors at the next permit modification or permit reevaluation to account for USEPA and/or District revisions to the underlying emission factors.
17. Nuisance. Except as otherwise provided in Section 41705 of the California H&SC, no person shall discharge from any source whatsoever such quantities of air contaminants or other material which cause injury, detriment, nuisance, or annoyance to any considerable number of persons or to the public, or which endanger the comfort, repose, health, or safety of any such persons or the public, or which cause, or have a natural tendency to cause, injury or damage to business or property.
18. Grounds for Revocation. Failure to abide by and faithfully comply with this permit or any Rule, Order, or Regulation may constitute grounds for revocation pursuant to California Health & Safety Code Section 42307 et seq.
19. Transfer of Owner/Operator. This permit is only valid for the owner and operator listed on this permit unless a Transfer of Owner/Operator application has been applied for and received by the District. Any transfer of ownership or change in operator shall be done in a manner as specified in District Rule 203. District Form –01T and the appropriate filing fee shall be submitted to the District within 30 days of the transfer.
20. Documents Incorporated by Reference. The documents listed below, including any District-approved updates thereof, are incorporated herein by reference and shall have the full force and effect of a permit condition for this permit. These documents shall be implemented for the life of the Project and shall be made available to District inspection staff upon request. a. Inspection and Maintenance Plan (approved January 29, 2015) b. Emission and Digester Gas Monitoring Plan (approved January 29, 2015)
AIR POLLUTION CONTROL OFFICER
DATE
September 29, 2021
Permit to Operate 08390 - R11
Attachments:
- Table 1 – Permitted Emission Limits
- Table 2 – Emission Standards
- Table 3 – Heat Input Limits
- Table 4 – Device Specific Requirements Summary
- Table 5 – Source Testing Requirements
- Permit Equipment List(s)
- Permit Evaluation for Permit to Operate 08390 - R11
Notes:
- Reevaluation Due Date: September 2024
- Stationary sources are subject to an annual emission fee (see Fee Schedule B-3 of Rule 210). - Annual reports are due by March 1st of each year.
- This permit supersedes Reeval 8390-R10 and PTO Mod 8390-02. \\sbcapcd.org\shares\Groups\ENGR\WP\Landfills & WWT\02077 City of Santa Maria WWTP\Reevals\Reeval 8390-R11\Reeval 08390 R11 - Final Permit - 9-28-2021.docx Permit to Operate 08390 - R11
NOx ROC CO SOx PM PM10 PM2.5
7.56 9.60 41.11 24.91 2.22 2.22 2.22
1.38 1.75 7.50 4.55 0.41 0.41 0.41
19.51 24.78 106.16 64.33 5.74 5.74 5.74
3.56 4.52 19.37 11.74 1.05 1.05 1.05
0.15 0.20 0.84 0.27 0.05 0.05 0.05
0.03 0.04 0.15 0.05 0.01 0.01 0.01
0.15 0.20 0.84 0.27 0.05 0.05 0.05
0.03 0.04 0.15 0.05 0.01 0.01 0.01
2.20 0.33 17.86 13.51 0.45 0.45 0.45
0.40 0.06 3.26 2.46 0.08 0.08 0.08
2.20 0.33 17.86 0.96 0.45 0.45 0.45
0.40 0.06 3.26 0.18 0.08 0.08 0.08
0.24 0.01
22.02 25.74 125.70 78.38 6.28 6.28 6.28
4.02 4.66 22.94 14.30 1.15 1.15 1.15
Notes:
2. Boiler (Propane)'s potential to emit is not included in the permit PTE total because the boiler is either fired on digester gas or propane. The NOx, ROC, CO, SOx, PM, PM10, and PM2.5 potential to emit while fired on digester gas are equal to or greater than when the boiler is fired on propane.
TPY
Boiler (Propane)
lb/day
1. Flare 1's potential to emit is not included in the permit PTE total because the combined heat input limit for the flares is 11.955 MMBtu/hr (Conditions 2.a's limit of 12.145 MMBtu/hr - lb/day
TPY
lb/day
TPY
Totals
lb/day
TPY
Table 1: Permit Potential to Emit
Flare 1
Iron Sponge Scrubber Fugitive Components
Flare 2
lb/day
TPY
Equipment
Flare 1 Pilot
Flare 2 Pilot
Boiler (Digester Gas)
lb/day
TPY
lb/day
TPY
lb/day
TPY
factors for all pollutants.
Flare 1's pilot heat input of 0.095 MMBtu/hr - Flare 2 pilot's heat input of 0.095 MMBtu/hr), which is equal to Flare 2's heat input. While both Flare 1 and Flare 2 are permitted to operation simultaneously, for the ease of emission calculations, only Flare 2's potential to emit was included since the resulting PTE would be identical regardless of how the heat input is divided between Flare 1 and Flare 2. Note that the flares have identical emission Permit to Operate 08390 - R11
TABLE 2. EMISSION STANDARDS
Device
ID # NOx CO Units Basis
104098 30 400 ppmvd @ 3% O2 Rule 361
TABLE 3. HEAT INPUT LIMITS
TABLE 4. DEVICE SPECIFIC REQUIREMENTS SUMMARY
Table Notes:
(a) Units subject to Rule 342 may comply with either the ppmvd or lb/MMBtu standards of the Rule. (b) NOx as NO2, SOx as SO2, lb/day = pounds per day, tpy = tons per year (c) Device ID # from permit equipment list.
(d) Emission data that round down to 0.00 has been set to a default of 0.01.
Device
ID # Fuel MMBtu/hr MMBtu/day MMBtu/yr
104098 Digester Gas, Propane 2.510 60.240 21,987.600
Device
ID #
Applicable
Rule
Source
Testing Tune-Ups Fuel Use Method
Low Use
Exemption BACT
104098 R361 Biennial Conditional Fuel Meter No No
Permit to Operate 08390 - R11
TABLE 5. SOURCE TESTING REQUIREMENTS
Emission &
Limit Test
Points
Pollutants Parameters Test Methods (a)
Boiler 1 Stack
(b)(c)(d)(e)
NOx ppmv, lb/hr EPA Method 7E, CARB 100
CO ppmv, lb/hr EPA Method 10, CARB 100
Sampling Point Det. EPA Method 1
Stack Gas Flow Rate EPA Method 2 or 19
O2, CO2, Dry MW EPA Method 3
Moisture Content EPA Method 4
Stack Temperature oF Calibrated Thermocouple
Fuel Gas Fuel Gas Flow Rate Fuel Gas Meter (f)
Higher Heating Value Btu/lb ASTM D 1826 or 3588
Total Sulfur Content ppmw ASTM D 1072 or 5504 (g)
Gas Composition CHONS%, F-factor ASTM 1945
Notes:
(a) Alternative methods may be acceptable on a case-by-case basis. (b) The emission rates shall be based on EPA Methods 2 and 4, or Method 19 along with the heat input rate. (c) For NOx, CO and O2 a minimum of three 30-minute runs shall be obtained during each test. (d) See Tables 1 and 2 for the emission standards to be measured against during the test. Measured NOx and CO shall not exceed the limit specified in the applicable Rule (e.g., Rule 361, Rule 342). (e) All emission determinations shall be made in the as-found operating condition, at the maximum attainable firing rate to be approved by the source test plan. No determination of compliance shall be established within two hours after a continuous period in which fuel flow to the unit is shut off for 30 minutes or longer.
(f) Fuel meter shall meet the calibration requirements prior to testing. (g) Total sulfur content fuel samples shall be obtained using EPA Method 18 with Tedlar Bags (or equivalent) equipped with Teflon tubing and fittings. Turnaround time for laboratory analysis of these samples shall be no more than 24 hours from sampling.
Equipment List for Permit to Operate 08390 - R11
PERMIT EQUIPMENT LIST - TABLE A
Reeval 08390 R11 / FID: 02077 City of Santa Maria WWTP / SSID: 02077
A PERMITTED EQUIPMENT
1 Anaerobic Digesters
1.1 Anaerobic Digester 1
Device ID # 104084 Device Name Anaerobic Digester 1
Rated Heat Input Physical Size 92,876.00 Cubic Feet
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Standard operating pressure of 5.5 - 10.5" water column, pressure alarm sounds at 12 - 15" water column, equipped with 4" Varec Model 2010B PRV (Serial Number: 15122407) set at pressure of 15" water column and vacuum of 2" water column
1.2 Anaerobic Digester 2
Device ID # 104085 Device Name Anaerobic Digester 2
Rated Heat Input Physical Size 47,112.00 Cubic Feet
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Standard operating pressure of 5.5 - 10.5" water column, pressure alarm sounds at 12 - 15" water column, equipped with 4" Varec Model 2010B PRV (Serial Number: 15122408) set at pressure of 15" water column and vacuum of 2" water column
Equipment List for Permit to Operate 08390 - R11
1.3 Anaerobic Digester 3
Device ID # 104629 Device Name Anaerobic Digester 3
Rated Heat Input Physical Size 47,112.00 Cubic Feet
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Standard operating pressure of 5.5 - 10.5" water column, pressure alarm sounds at 12 - 15" water column, equipped with 4" Varec Model 2010B PRV (Serial Number: 15122409) set at pressure of 15" water column and vacuum of 2" water column
1.4 Anaerobic Digester 4
Device ID # 112446 Device Name Anaerobic Digester 4
Rated Heat Input Physical Size 82,300.00 Cubic Feet
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Standard operating pressure of 5.5 - 10.5" water column, pressure alarm sounds at 12 - 15" water column, equipped with two Varec Model 5810B62 6" PSVs set at 12 inches of water column, equipped with Varec Model 450 6" flame arrestor
2 Waste Gas Flare 1
Device ID # 114679 Device Name Waste Gas Flare 1
Rated Heat Input 4.725 MMBtu/Hour Physical Size 4.725 MMBtu/Hour Manufacturer Varec Operator ID
Model 239-A Serial Number
Location Note
Device
Description
Waste gas design capacity of 4.630 MMBtu/hr (0.1852 MMscf/day of 600 Btu/scf gas), pilot gas design capacity of 0.095 MMBtu/hr (0.00009 MMscf/day of propane), dimensions: 4” D x 11’ H, equipped with an automatic reigniting pilot fired on propane, flare tip equipped with a wind shroud
Equipment List for Permit to Operate 08390 - R11
3 Waste Gas Flare 2
Device ID # 008696 Device Name Waste Gas Flare 2
Rated Heat Input 12.050 MMBtu/Hour Physical Size 12.050 MMBtu/Hour Manufacturer Varec Operator ID
Model 244W Serial Number
Location Note
Device
Description
Waste gas design capacity of 11.955 MMBtu/hr (0.4782 MMscf/day of 600 Btu/scf gas), pilot gas design capacity of 0.095 MMBtu/hr (0.00009 MMscf/day of propane), dimensions: 6” D x 15’ H, equipped with an automatic reigniting pilot fired on propane, flare tip equipped with a wind shroud
4 Hydrogen Sulfide Ambient Monitoring System
Device ID # 104086 Device Name Hydrogen Sulfide
Ambient Monitoring
System
Rated Heat Input Physical Size
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Hydrogen sulfide ambient monitoring system with three remote sensors 5 Iron Sponge Scrubber
Device ID # 104089 Device Name Iron Sponge Scrubber
Rated Heat Input Physical Size
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Dimensions: 10’ D x 7’ H, welded construction with a manway cover and vessel cover bolted in place, contains 5’ of wood shavings impregnated with iron oxide supported on a removable tray
Equipment List for Permit to Operate 08390 - R11
6 Ferrous Chloride Injection System
Device ID # 104087 Device Name Ferrous Chloride
Injection System
Rated Heat Input Physical Size 0.25 Horsepower
(Electric Motor)
Manufacturer Operator ID
Model Serial Number
Location Note
Device
Description
Hydrogen sulfide control system, ferrous chloride injection system equipped with a pump powered by a 0.25 horsepower electric motor 7 Boiler 1
Device ID # 104098 Device Name Boiler 1
Rated Heat Input 2.510 MMBtu/Hour Physical Size 2.510 MMBtu/Hour Manufacturer Cleaver Brooks Operator ID
Model CB 700-60 Serial Number L-103264
Location Note
Device
Description
Fueled by digester gas, propane gas used as backup, equipped with a Cleaver Brooks low emission kit and a fuel meter, complies with the Rule 361 emission requirements of 30 ppmv NOx at 3% oxygen and 400 ppmv CO at 3% oxygen
Equipment List for Permit to Operate 08390 - R11
B EXEMPT EQUIPMENT
1 Aerobic Equipment
Device ID # 104100 Device Name Aerobic Equipment
Rated Heat
Input
Physical Size
Manufacturer Operator ID
Model Serial Number
Part 70 Insig? No District Rule Exemption:
202.L.11 Aerobic Wastewater Treatment Equipment
Location Note
Device
Description
Aerobic equipment not used for digester gas combustion or the control of air emissions
2 Boiler 2
Device ID # 104101 Device Name Boiler 2
Rated Heat
Input
0.960 MMBtu/Hour Physical Size
Manufacturer Operator ID
Model Serial Number
Part 70 Insig? No District Rule Exemption:
202.G.1 Combustion Equipment <= 2 MMBtu/hr
Location Note
Device
Description
Installed prior to October 17, 2003, fired on propane gas
PERMIT EVALUATION FOR
PERMIT TO OPERATE 08390 - R11
1.0 BACKGROUND
1.1 General: This PTO is the triennial reevaluation of the Permit to Operate and contains an updated rule review. This reevaluation incorporates the updated equipment list description and emission calculations found in PTO Mod 8390-02.
1.2 Permit History:
PERMIT FINAL ISSUED PERMIT DESCRIPTION
Reeval 08390 R10 10/16/2018 Permit reevaluation for wastewater treatment plant.
PTO Mod 08390 02 07/05/2019 Modify permit to comply with Rule 361 ATC 15547 01/11/2021 Two 2014 Deutz prime engines rated at 74 bhp each.
Reeval 13046 R4 03/05/2021 Permit reevaluation for E/S diesel-fired IC engine.
1.3 Compliance History:
VIOLATION TYPE NUMBER ISSUE DATE DESCRIPTION OF VIOLATION NOV 11453 01/11/2019 Violation of Rule 206
2.0 ENGINEERING ANALYSIS
2.1 Equipment/Processes: This facility treats wastewater for the City of Santa Maria. The sludge from the biochemical treatment process is anaerobically decomposed in the digesters. The gases produced during this process are burned in a boiler or one of two flares. A ferrous chloride injection system controls hydrogen sulfide production, with an iron sponge scrubber used as necessary for further hydrogen sulfide control.
2.2 Emission Controls: Digester gas is burned in the waste gas flare. A ferrous chloride injection system controls hydrogen sulfide production. An iron sponge scrubber is used in addition to the ferrous chloride injection system if further gas treatment is necessary. Boiler 1 was source tested and certified to meet the 30 ppmv NOx and 400 ppmv CO emissions standards of Rule 361.
2.3 Emission Factors: Emission factors are documented in the Attachment A.
2.4 Reasonable Worst Case Emission Scenario: The operating scenario is summarized as follows:
Worst Case:
• Maximum digester gas flow to Flare 1 = 185,200 scf/day • Maximum digester gas flow to Flare 2 = 478,200 scf/day
PERMIT EVALUATION FOR
PERMIT TO OPERATE 08390 - R11
• Propane pilot gas flow rate to Flares 1 = 900 scf/day • Propane pilot gas flow rate to Flares 2 = 900 scf/day • Flare pilots are continuously operated
• Maximum combined heat input to the waste gas flares and pilots is 12.145 MMBtu/hr, 291.480 Btu/day, and 106,390.200 MMBtu/year
• Maximum heat input to the boiler is 2.510 MMBtu/hr
• Boiler is fired on either digester gas or propane
• Worst-case emissions from the boiler occur when combusting digester gas. • Total sulfur content of digester gas shall not exceed 796 ppmv (as H2S) • High heat value (HHV) of digester gas = 600 Btu/scf
• Total sulfur content of propane gas shall not exceed 239 ppmv (as H2S) • High heat value (HHV) of propane = 2,522 Btu/scf
• Plant operates 24 hours/day, 8,760 hours/year
2.5 Emission Calculations: Detailed emission calculation spreadsheets may be found in the Attachment A. These emissions define the Potential to Emit for the permitted equipment.
2.6 Special Calculations: There are no special calculations.
2.7 BACT Analyses: Best Available Control Technology was not required for this project.
2.8 Enforceable Operational Limits: The permit has enforceable operating conditions that ensure the equipment is operated properly.
2.9 Monitoring Requirements: Monitoring of the equipment’s operational limits is required to ensure that these are enforceable.
2.10 Recordkeeping and Reporting Requirements: The permit requires that the data which is monitored be recorded and reported to the District.
3.0 REEVALUATION REVIEW
3.1 Compliance Summary: Since the last permit reevaluation, this facility has been inspected on November 21, 2019.
3.2 Notes from Inspector: No notes from the inspector.
3.3 Changes to Applicable Rules (or new rules): None.
3.4 Changes/Revisions to Engineering Analysis (EF updates, etc.): There have been no changes to the Engineering Analysis.
3.5 Changes/Revisions to Monitoring, Recordkeeping & Reporting: Monitoring, recordkeeping and reporting requirements from PTO Mod 8390-02 have been incorporated into this permit.
PERMIT EVALUATION FOR
PERMIT TO OPERATE 08390 - R11
3.6 Other Changes/Corrections Made: The permit reflects the most current template.
4.0 REGULATORY REVIEW
4.1 Partial List of Applicable Rules:
Rule 201. Permits Required
Rule 202. Exemptions to Rule 201
Rule 205. Standards for Granting Permits
Rule 301. Circumvention
Rule 302. Visible Emissions
Rule 303. Nuisance
Rule 304. Particulate Matter - Northern Zone
Rule 306. Dust and Fumes - Northern Zone
Rule 311. Sulfur Content of Fuels
Rule 360. Boilers, Water Heaters, and Process Heaters (0.075 – 2 MMBtu/hr) Rule 361. Small Boilers, Steam Generators, and Process Heaters Rule 801. New Source Review- Definitions and General Requirements Rule 802. New Source Review
Rule 809. Federal Minor Source New Source Review
Rule 810. Federal Prevention of Significant Deterioration
4.2 Rules Requiring Review:
4.2.1 Rule 202 - Exemptions to Rule 201: Section G.1.b exempts combustion equipment with a maximum heat input less than 2.000 MMBtu/hour when fired exclusively on liquefied petroleum gas, which meets Gas Processors Association Standards. Boiler 2 fired on propane satisfies this requirement.
4.2.2 Rule 311 - Sulfur Content of Fuels: Section C of this rule limits burning, within the Northern Zone of Santa Barbara County, of any gaseous fuel containing sulfur compounds in excess of 50 grains per 100 cubic feet (calculated as hydrogen sulfide at standard conditions) or any liquid or solid fuel having a sulfur content in excess of 0.5 percent by weight. This rule applies to the digester gas burned in the flares and any other equipment at the facility.
5.0 AQIA
The project is not subject to the Air Quality Impact Analysis requirements of Regulation VIII.
6.0 OFFSETS/ERCs
6.1 Offsets: The emission offset thresholds of Regulation VIII are not exceeded.
6.2 ERCs: This source does not generate emission reduction credits.
PERMIT EVALUATION FOR
PERMIT TO OPERATE 08390 - R11
7.0 AIR TOXICS
An air toxics health risk assessment was not performed for this permitting action.
8.0 CEQA / LEAD AGENCY
This project is exempt from CEQA pursuant to the Environmental Review Guidelines for the Santa Barbara County APCD (revised April 30, 2015). Appendix A (APCD Projects Exempt from CEQA and Equipment or Operations Exempt from CEQA) provides an exemption specifically for permits to operate and reevaluations thereof. No further action is necessary.
9.0 SCHOOL NOTIFICATION
A school notice pursuant to the requirements of Health and Safety Code Section 42301.6 was not required.
10.0 PUBLIC and AGENCY NOTFICATION PROCESS/COMMENTS ON DRAFT PERMIT
10.1 This project was not subject to public notice.
10.2 The permittee had no comments on the draft permit.
11.0 FEE DETERMINATION
Fees for the District’s work efforts are assessed on a fee basis. The Project Code is 520000 (External Combustion). See Attachment C for the fee calculations.
12.0 RECOMMENDATION
It is recommended that this permit be granted with the conditions as specified in the permit.
Kevin Brown September 28, 2021 9/28/2021
AQ Engineer/Technician Date Supervisor Date
13.0 ATTACHMENT(S)
A. Emission Calculations
B. IDS Tables
C. Fee Statement
Permit to Operate 08390 - R11
ATTACHMENT A
Emission Calculations
Attachment: A-1
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Fuel Information
Data Value Units Reference
Flare Throughput……………………. 0.185 MMscf/day
Gas Heat Content………………….. 600 Btu/scf
Sulfur Content………………………. 796 ppmv as H2S
Heat Input Data
Value Units Reference
4.630 MMBtu/hour Daily divided by 24 hr/day
111.120 MMBtu/day Permit Application
40,558.800 MMBtu/year Daily times 365 days/yr
Emission Factors
Pollutant lb/MMBtu Reference
NOx 0.0680
ROC 0.0864 APCD Emission Factor Guidance (ver 1.1, 7/13/1998) CO 0.3700
SOx 0.2242
PM 0.0200
PM10 0.0200
PM2.5 0.0200
Pollutant lb/day TPY
NOx 7.56 1.38
ROC 9.60 1.75
CO 41.11 7.50
SOx 24.91 4.55
PM 2.22 0.41
PM10 2.22 0.41
PM2.5 2.22 0.41
Processed By: KMB Date: August 10, 2021
FLARE 1 EMISSION CALCULATIONS (Ver. 2.0)
Flare Potential to Emit
Permit Application
Permit Application
Permit Application
AP-42, Table 13.5-1
Mass Balance Calculation
SBCAPCD
AP-42, Chapter 1.4
AP-42, Chapter 1.4
AP-42, Table 13.5-1
Permit to Operate 08390 - R11
ATTACHMENT A
Emission Calculations
Attachment: A-2
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Fuel Information
Data Value Units Reference
Flare Throughput……………………. 0.478 MMscf/day
Gas Heat Content………………….. 600 Btu/scf
Sulfur Content………………………. 796 ppmv as H2S
Heat Input Data
Value Units Reference
11.955 MMBtu/hour Daily divided by 24 hr/day
286.920 MMBtu/day Permit Application
104,725.800 MMBtu/year Daily times 365 days/yr
Emission Factors
Pollutant lb/MMBtu Reference
NOx 0.0680
ROC 0.0864 APCD Emission Factor Guidance (ver 1.1, 7/13/1998) CO 0.3700
SOx 0.2242
PM 0.0200
PM10 0.0200
PM2.5 0.0200
Pollutant lb/day TPY
NOx 19.51 3.56
ROC 24.78 4.52
CO 106.16 19.37
SOx 64.33 11.74
PM 5.74 1.05
PM10 5.74 1.05
PM2.5 5.74 1.05
Processed By: KMB Date: August 10, 2021
AP-42, Table 13.5-1
FLARE 2 EMISSION CALCULATIONS (Ver. 2.0)
Permit Application
Permit Application
Permit Application
AP-42, Table 13.5-1
Mass Balance Calculation
SBCAPCD
AP-42, Chapter 1.4
AP-42, Chapter 1.4
Flare Potential to Emit
Permit to Operate 08390 - R11
ATTACHMENT A
Emission Calculations
Attachment: A-3
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Fuel Information
Data Value Units Reference
Flare Throughput……………………. 0.0009 MMscf/day
Gas Heat Content………………….. 2,522 Btu/scf
Sulfur Content………………………. 239 ppmv as H2S
Heat Input Data
Value Units Reference
0.095 MMBtu/hour Daily divided by 24 hr/day
2.270 MMBtu/day Permit Application
828.477 MMBtu/year Daily times 365 days/yr
Emission Factors
Pollutant lb/MMBtu Reference
NOx 0.0680
ROC 0.0864 APCD Emission Factor Guidance (ver 1.1, 7/13/1998) CO 0.3700
SOx 0.1206
PM 0.0200
PM10 0.0200
PM2.5 0.0200
Pollutant lb/day TPY
NOx 0.15 0.03
ROC 0.20 0.04
CO 0.84 0.15
SOx 0.27 0.05
PM 0.05 0.01
PM10 0.05 0.01
PM2.5 0.05 0.01
Processed By: KMB Date: August 10, 2021
SBCAPCD
AP-42, Chapter 1.4
AP-42, Chapter 1.4
Flare Potential to Emit
FLARE 1 PILOT EMISSION CALCULATIONS (Ver. 2.0)
Permit Application
Permit Application
Permit Application
AP-42, Table 13.5-1
AP-42, Table 13.5-1
Mass Balance Calculation
Permit to Operate 08390 - R11
ATTACHMENT A
Emission Calculations
Attachment: A-3
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Fuel Information
Data Value Units Reference
Flare Throughput……………………. 0.0009 MMscf/day
Gas Heat Content………………….. 2,522 Btu/scf
Sulfur Content………………………. 239 ppmv as H2S
Heat Input Data
Value Units Reference
0.095 MMBtu/hour Daily divided by 24 hr/day
2.270 MMBtu/day Permit Application
828.477 MMBtu/year Daily times 365 days/yr
Emission Factors
Pollutant lb/MMBtu Reference
NOx 0.0680
ROC 0.0864 APCD Emission Factor Guidance (ver 1.1, 7/13/1998) CO 0.3700
SOx 0.1206
PM 0.0200
PM10 0.0200
PM2.5 0.0200
Pollutant lb/day TPY
NOx 0.15 0.03
ROC 0.20 0.04
CO 0.84 0.15
SOx 0.27 0.05
PM 0.05 0.01
PM10 0.05 0.01
PM2.5 0.05 0.01
Processed By: KMB Date: August 10, 2021
Mass Balance Calculation
SBCAPCD
AP-42, Chapter 1.4
AP-42, Chapter 1.4
Flare Potential to Emit
AP-42, Table 13.5-1
FLARE 2 PILOT EMISSION CALCULATIONS (Ver. 2.0)
Permit Application
Permit Application
Permit Application
AP-42, Table 13.5-1
Permit to Operate 08390 - R11
ATTACHMENT A
Emission Calculations
Attachment: A-5
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Heater Input Data
Information Value Units Reference
Maximum Hourly Heat Input…………… 2.510 MMBtu/hr
Daily Operating Schedule...................... 24 hrs/day Maximum Daily Heat Input……………. 60.240 MMBtu/day Calculated value Yearly Load Factor (%)......................................... 100 % Maximum Annual Heat Input………….. 21,987.600 MMBtu/yr Calculated value Fuel Information
Information Value Units Reference
Fuel........................................................... Digester Gas N/A High Heating Value......................................... 600 Btu/scf Sulfur Content of Fuel.................................... 796.00 ppmvd as H2S Emission Factors
Pollutant Value Units Reference
NOx Emission Factor...................................... 0.0365 lb/MMBtu ROC Emission Factor................................. 0.0054 lb/MMBtu CO Emission Factor............................................ 0.2965 lb/MMBtu SOx Emission Factor..................................... 0.2242 lb/MMBtu PM Emission Factor ........................................... 0.0075 lb/MMBtu PM10 Emission Factor.......................................... 0.0075 lb/MMBtu PM2.5 Emission Factor........................................... 0.0075 lb/MMBtu Pollutant lb/day TPY
NOx 2.20 0.40
ROC 0.33 0.06
CO 17.86 3.26
SOx 13.51 2.46
PM 0.45 0.08
PM10 0.45 0.08
PM2.5 0.45 0.08
Processed By: Date: August 10, 2021
AP-42, Section 1.4
KMB
BOILER FIRED ON DIGESTER GAS EMISSION CALCULATIONS (Ver. 7.0) Boiler/Steam Generator Potential to Emit
Permit Application
Permit Application
Permit Application
Permit Application
Permit Application
Permit Application
Rule 361 (30 ppmv @ 3% O2)
AP-42, Section 1.4
Rule 361 (400 ppmv @ 3% O2)
Mass Balance Calculation
AP-42, Section 1.4
AP-42, Section 1.4
Permit to Operate 08390 - R11
ATTACHMENT A
Emission Calculations
Attachment: A-6
Permit Number: Reeval 8390-R11
Facility: Santa Maria WWTP
Heater Input Data
Information Value Units Reference
Maximum Hourly Heat Input…………… 2.510 MMBtu/hr
Daily Operating Schedule...................... 24 hrs/day Maximum Daily Heat Input……………. 60.240 MMBtu/day Calculated value Yearly Load Factor (%)......................................... 100 % Maximum Annual Heat Input………….. 21,987.600 MMBtu/yr Calculated value Fuel Information
Information Value Units Reference
Fuel........................................................... Propane N/A High Heating Value......................................... 2,522 Btu/scf Sulfur Content of Fuel.................................... 239.00 ppmvd as H2S Emission Factors
Pollutant Value Units Reference
NOx Emission Factor...................................... 0.0365 lb/MMBtu ROC Emission Factor................................. 0.0054 lb/MMBtu CO Emission Factor............................................ 0.2965 lb/MMBtu SOx Emission Factor..................................... 0.0160 lb/MMBtu PM Emission Factor ........................................... 0.0075 lb/MMBtu PM10 Emission Factor.......................................... 0.0075 lb/MMBtu PM2.5 Emission Factor........................................... 0.0075 lb/MMBtu Pollutant lb/day TPY
NOx 2.20 0.40
ROC 0.33 0.06
CO 17.86 3.26
SOx 0.96 0.18
PM 0.45 0.08
PM10 0.45 0.08
PM2.5 0.45 0.08
Processed By: Date: August 10, 2021
AP-42, Section 1.4
AP-42, Section 1.4
Boiler/Steam Generator Potential to Emit
KMB
Permit Application
Rule 361 (30 ppmv @ 3% O2)
AP-42, Section 1.4
Rule 361 (400 ppmv @ 3% O2)
Mass Balance Calculation
AP-42, Section 1.4
Permit Application
BOILER FIRED ON PROPANE EMISSION CALCULATIONS (Ver. 7.0) Permit Application
Permit Application
Permit Application
Permit Application
Permit to Operate 08390 - R11
ATTACHMENT B
IDS Tables
PERMIT POTENTIAL TO EMIT
NOx ROC CO SOx PM PM10 PM2.5
lb/day 22.02 25.74 125.70 78.38 6.28 6.28 6.28
lb/hr
TPQ
TPY 4.02 4.66 22.94 14.30 1.15 1.15 1.15
FACILITY POTENTIAL TO EMIT
NOx ROC CO SOx PM PM10 PM2.5
lb/day 83.88 29.68 179.00 78.47 7.43 7.43 7.43
lb/hr
TPQ
TPY 6.27 4.79 25.26 14.31 1.16 1.16 1.16
STATIONARY SOURCE POTENTIAL TO EMIT
NOx ROC CO SOx PM PM10 PM2.5
lb/day 83.88 29.68 179.00 78.47 7.43 7.43 7.43
lb/hr
TPQ
TPY 6.27 4.79 25.26 14.31 1.16 1.16 1.16
Notes:
(1) Emissions in these tables are from IDS.
(2) Because of rounding, values in these tables shown as 0.00 are less than 0.005, but greater than zero.
Permit to Operate 08390 - R11
ATTACHMENT C
Fee Statement
FEE STATEMENT
PTO No. 08390 - R11
FID: 02077 City of Santa Maria WWTP / SSID: 02077
Device Fee
Device
No. Device Name
Fee
Schedule
Qty of Fee
Units
Fee
per
Unit
Fee
Units
Max or
Min. Fee
Apply?
Number
of Same
Devices
Pro Rate
Factor
Device
Fee
Penalty
Fee?
Fee
Credit
Total Fee
per Device
104084 Anaerobic Digester 1 A6 694.761 4.33
Per 1000
gallons No 1 1.000 3,008.32 0.00 0.00 3,008.32
104085 Anaerobic Digester 2 A6 352.422 4.33
Per 1000
gallons No 1 1.000 1,525.99 0.00 0.00 1,525.99
104629 Anaerobic Digester 3 A6 352.422 4.33
Per 1000
gallons No 1 1.000 1,525.99 0.00 0.00 1,525.99
112446 Anaerobic Digester 4 A6 615.647 4.33
Per 1000
gallons No 1 1.000 2,665.75 0.00 0.00 2,665.75
114679 Waste Gas Flare 1 A3 4.725 566.34
Per 1 million
Btu input No 1 1.000 2,675.96 0.00 0.00 2,675.96
008696 Waste Gas Flare 2 A3 12.050 566.34
Per 1 million
Btu input No 1 1.000 6,824.40 0.00 0.00 6,824.40
104086 Hydrogen Sulfide Ambient Monitoring System A1.a 1.000 75.49 Per equipment No 1 1.000 75.49 0.00 0.00 75.49 104089 Iron Sponge Scrubber A1.a 1.000 75.49 Per equipment No 1 1.000 75.49 0.00 0.00 75.49 104087 Ferrous Chloride Injection System A2 0.250 39.14 Per total rated
hp Min 1 1.000 75.00 0.00 0.00 75.00
104098 Boiler 1 A3 2.510 566.34
Per 1 million
Btu input No 1 1.000 1,421.51 0.00 0.00 1,421.51
Device Fee Sub-Totals = $19,873.89 $0.00 $0.00
Device Fee Total = $19,873.89
Permit Fee
Fee Based on Devices $19,873.89
Fee Statement Grand Total = $19,873
Notes:
(1) Fee Schedule Items are listed in District Rule 210, Fee Schedule "A". (2) The term "Units" refers to the unit of measure defined in the Fee Schedule.
Certified Mail
Return Receipt Requested
Re: Notice of Final Permit to Operate 08390 - R11 Issuance Fee Due: $ 19,873
Dear Ms. Griffith:
Enclosed is the final Permit to Operate (PTO) No. 08390 - R11 for a wastewater treatment plant at 601 Black Road in Santa Maria.
Please carefully review the enclosed documents to ensure that they accurately describe your facility and that the conditions are acceptable to you.
This PTO is for the triennial (every three years) reevaluation of existing air quality permits at your facility, as required by Air Pollution Control District (District) Rule 201. This permit may contain new conditions added to ensure compliance with current laws and updated regulations.
You should become familiar with all District rules pertaining to your facility. This permit does not relieve you of any requirements to obtain authority or permits from other governmental agencies.
This permit requires you to:
• Pay a fee of $19,873, which is due immediately and is considered late after 30 calendar days from the date stamped on the permit. Pursuant to District Rule 210.IV.B, no appeal shall be heard unless all fees have been paid. See the attached invoice for more information. • Follow the conditions listed on your permit. Pay careful attention to the recordkeeping and reporting requirements.
• Ensure that a copy of the enclosed permit is posted or kept readily available near the permitted equipment.
• Promptly report changes in ownership, operator, or your mailing address to the District.
Alexandra Griffith
City of Santa Maria
2065 E. Main Street
Santa Maria, CA 93454
FID: 02077
Permit: P 08390 - R11
SSID: 02077
September 29, 2021 9171 9690 0935 0268 3953 34
If you are not satisfied with the conditions of this permit, you have thirty (30) calendar days from the date of this permit issuance notice to appeal this permit to the Air Pollution Control District Hearing Board (ref: California Health and Safety Code, §42302.1). Any contact, discussions, or meetings with District staff regarding the terms of this permit during or after permit issuance do not constitute an appeal under Rule 209 or the California H&SC and will not stop or alter the 30-day appeal period. Only a formal application to the Hearing Board can initiate an appeal. You may contact the Clerk of the Hearing Board for specific information concerning appeal initiation and procedures.
Please include the facility identification (FID) and permit numbers as shown at the top of this letter on all correspondence regarding this permit. If you have any questions, please contact Kevin Brown of my staff at (805) 961-8826.
Sincerely,
David Harris, Division Manager
Engineering Division
enc: Final PTO 08390 - R11
Final Permit Evaluation
Invoice # R 08390 - R11
cc: City of Santa Maria WWTP 02077 Project File
Engr Chron File
Accounting (Invoice only)
Kevin Brown (Cover letter only)
\\sbcapcd.org\shares\Groups\ENGR\WP\Landfills & WWT\02077 City of Santa Maria WWTP\Reevals\Reeval 8390-R11\Reeval 08390 R11 - Final Letter - 9-28-2021.docx 260 N. San Antonio Rd, Suite A
Santa Barbara, CA 93110-1315
Invoice: R 08390 - R11
Date:
Terms: Net 30 Days
520000/6600/3282
\\sbcapcd.org\shares\Groups\ENGR\WP\Landfills & WWT\02077 City of Santa Maria WWTP\Reevals\Reeval 8390-R11\Reeval 08390 R11 - Invoice - 8-10- 2021.docx District Federal TIN 77-0384167
INVOICE
BILL TO: FACILITY:
Accounts Payable
City of Santa Maria (000361)
2065 E. Main Street
Santa Maria, CA 93454
City of Santa Maria WWTP
02077
601 Black Road
Santa Maria
Permit: Permit to Operate (PTO) No. 08390 - R11
Fee Type: Permit Reevaluation Fee (see the Fee Statement in your permit for a breakdown of the fees) Amount Due: $ 19,873
REMIT PAYMENTS TO THE ABOVE ADDRESS
Please indicate the invoice number R 08390 - R11
on your remittance.
IF YOU HAVE ANY QUESTIONS REGARDING YOUR INVOICE PLEASE CONTACT OUR ADMINISTRATION DIVISION AT (805) 961-8800
The District charges $25 for returned checks. Other penalties/fees may be incurred as a result of returned checks and late payment (see District Rule 210). Failure to pay this Invoice may result in the cancellation or suspension of your permit. Please notify the District regarding any changes to the above information 09/29/2021
CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 11: Capital Improvement
Program and Implementation
FINAL / October 2026
CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 11: Capital Improvement
Program and Implementation
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.
Date: 2026.10.24 11:25:32-07'00'
VOLUME 11 / CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/Master Plan/Volume 11/_Cover_TOC_Abbrevs_AppxCovers.docx Contents
CHAPTER 1 CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION
1.1 Purpose 1-1
1.2 Background and Methodology 1-1
1.2.1 Short-Term Projects 1-2
1.2.2 Medium-Term Projects 1-2
1.2.3 Long-Term Projects 1-2
1.3 Project List 1-2
1.3.1 Short-Term Projects 1-2
1.3.2 Medium-Term Projects 1-6
1.3.3 Long-Term Projects 1-6
1.4 Preliminary CIP Schedule 1-8
1.5 Summary of CIP Projects 1-8
CHAPTER 2 PROJECT DELIVERY
2.1 Introduction 2-1
2.1.1 Purpose and Background 2-1
2.1.2 Project Drivers 2-1
2.2 Project Delivery Methods 2-2
2.2.1 Design-Bid-Build 2-3
2.2.2 Construction Manager General Contractor 2-3
2.2.3 Progressive Design-Build 2-4
2.2.4 Fixed-Price Design-Build 2-4
2.3 Delivery Method Evaluation and Recommendations 2-7
2.3.1 Evaluation Criteria 2-7
2.3.2 Recommended Project Delivery Method 2-11
Appendices
APPENDIX A SHORT-TERM CAPITAL IMPROVEMENT PROGRAM PROJECTS TO MAINTAIN EXISTING WWTP
APPENDIX B WORKSHOP NO. 7 - PROJECT DELIVERY
Tables
Table 1.1 Detailed Summary of CIP 1-9
Table 2.1 Project Delivery Methods 2-3
Table 2.2 Advantages and Disadvantages of Delivery Methods 2-5 Table 2.3 Considerations for Alternative Project Delivery 2-7 VOLUME 11 / CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Figures
Figure 1.1 Preliminary Layout of Proposed Percolation Pond Project 1-3 Figure 1.2 Phase 1 WWTP Facilities Planning Level Layout 1-5 Figure 1.3 Phase 2 WWTP Preliminary Facilities Layout 1-7 Figure 1.4 Planning Level Schedule for First 13 Years of the Proposed CIP 1-8 Figure 1.5 Projected Annual CIP Outlay Through Fiscal Year 2036/2037 1-10 Figure 1.6 Projected Total CIP Through 2060 for all Major Identified Projects 1-11 Figure 2.1 Traditional DBB Approach for Phase 1 Delivery 2-12 Figure 2.2 Option for Refinement of the Project Delivery Approach After 30% Design 2-13 Figure 2.3 At 60% Design, There is Flexibility to Stay With CMGC or Switch Back to DBB 2-14 Figure 2.4 Final Choice to Complete the Project via CMGC or DBB 2-14 VOLUME 11 / CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iii
Abbreviations
ADWF average dry weather flow
BODR Basis of Design Report
Carollo Carollo Engineers
CIP Capital Improvement Program
City City of Santa Marian
CMAR Construction Manager-At-Risk
CMGC Construction Manager/General Contractor
DB Design-Build
DBB design-bid-build
FPDB Fixed Price Design-Build
FY fiscal year
GMP guaranteed maximum price
mgd million gallons per day
O&M operations and maintenance
PDB Progressive Design-Build
SB Senate Bill
WWTP wastewater treatment plant
VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-1
CHAPTER 1 CAPITAL IMPROVEMENT PROGRAM AND
IMPLEMENTATION
1.1 Purpose
The purpose of this chapter is to present the Capital Improvement Program (CIP) developed from the recommendations identified throughout this Master Plan. The CIP provides an implementation framework for the recommended improvements through 2060. The City of Santa Maria (City) operates on a July 1 to June 30 fiscal year (FY), so for example FY 26/27 begins July 1, 2026 and ends June 30, 2027.
The preceding volumes and chapters of this Master Plan identify project needs, planning-level costs, and technical justifications. This chapter consolidates those recommendations into a prioritized implementation program and identifies anticipated City expenditures by FY.
1.2 Background and Methodology
The CIP was developed using recommendations from the facility planning, process evaluation, condition assessment, capacity evaluation, and regulatory compliance analyses presented throughout this Master Plan. Each project was evaluated based on the following considerations:
Regulatory compliance requirements.
Operational reliability.
Asset condition.
Treatment capacity needs.
Long-term growth projections.
Sequencing and interdependencies with other improvements.
Planning-level project costs were developed in the respective technical chapters where the projects were identified. The basis that was used to develop the planning-level cost estimates is detailed in Volume 2, Chapter 6.
This chapter incorporates those costs into an implementation strategy that supports continued reliable operation of the Santa Maria Wastewater Treatment Plant (WWTP) through 2060, incorporating appropriate plant modifications and improvements to address effluent permitting requirements, growth, and rehabilitation.
To facilitate project prioritization and implementation planning, projects were grouped into the following three implementation periods based on anticipated facility needs, project sequencing, and dependencies between major capital improvements.
VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-2
1.2.1 Short-Term Projects
Short-term projects are recommended to address immediate facility needs, maintain reliable plant operation, and implement the first phase of treatment facility improvements identified in this Master Plan.
Short-term projects are anticipated to begin immediately (FY 26/27) and be completed over the following ten years, by FY 36/37.
This category includes the major Phase 1 Expansion project.
Note that in some Volumes of the Master Plan there were references made to so-called Near-Term projects, in order to differentiate them from longer-term projects. These are now included in the short-term projects.
1.2.2 Medium-Term Projects
Medium-term projects focus on maintaining the performance and reliability of critical wastewater treatment infrastructure following implementation of the Phase 1 improvements. Medium-term projects are anticipated to begin in FY 37/38.
1.2.3 Long-Term Projects
Long-term projects are intended to support future treatment capacity needs, maintain critical infrastructure, and accommodate long-range planning objectives. Long-term projects are anticipated to begin in FY 52/53.
1.3 Project List
Based on recommendations developed throughout this Master Plan, smaller projects were grouped into five “major projects” and recommended for implementation through FY 59/60. These major projects are:
CIP Projects to Maintain the Existing WWTP
Percolation Pond Expansion Project
Phase 1 Expansion Project
Percolation Pond Rehabilitation Project
Phase 2 Expansion Project
These five projects were organized according to the implementation periods described in Section 1.2 and are described in more detail below.
1.3.1 Short-Term Projects
1.3.1.1 CIP Projects to Maintain Existing WWTP
Several CIP projects were identified and recommended to maintain plant reliability and support continued operation prior to and during the construction and completion of the Phase 1 facilities. Volume 4 of the Master Plan provided a compiled set of projects to be undertaken in the short-term prior to Phase 1 upgrades. These projects were based on findings from a condition assessment performed on all of the VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-3
facilities at the WWTP. Appendix A lists details and project costs of each individual upgrade/rehabilitation project. These projects are anticipated to occur between FY 26/27 and FY 30/31.
1.3.1.2 Percolation Pond Expansion Project
The Percolation Pond Expansion Project is recommended as a short-term improvement to provide additional percolation capacity and support current and future wastewater flows. This project will construct six additional percolation ponds for a total of 42 acres of percolation ponds and associated facilities on City-owned land east of Black Road. Figure 1.1 shows the preliminary layout of the Percolation Pond Expansion Project. Design and implementation are anticipated between FY 26/27 and FY 29/30. For additional details regarding this project, refer to Volume 6, Chapter 6 of the Master Plan.
Figure 1.1 Preliminary Layout of Proposed Percolation Pond Project VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-4
1.3.1.3 Phase 1 Expansion Project
The Phase 1 Project represents the first major treatment facility expansion recommended by the Master Plan. This project provides the foundation for future treatment improvements and is a key component of the overall implementation strategy to enable the plant to meet the new General Permit effluent limits.
Once completed, the Phase 1 improvements will take the facility through 2052 with 10 million gallons per day (mgd) average dry weather flow (ADWF) of hydraulic capacity at the projected loading rates for this expansion’s horizon.
The project is anticipated to begin advanced planning and design activities in FY 26/27, followed by construction beginning in FY 31/32 and completion in FY 36/37. Figure 1.2 illustrates the facilities that will be upgraded as part of the Phase 1 project. For additional details regarding this project, refer to Volume 6 of the Master Plan.
VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA WASTEWATER TREATMENT PLANT MASTER PLAN 1-5 Figure 1.2 Phase 1 WWTP Facilities Planning Level Layout VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-6
1.3.2 Medium-Term Projects
1.3.2.1 Percolation Pond Rehabilitation Project
The City currently percolates all its secondary effluent into 15 separate percolation ponds. A 2024 soils investigation, further detailed in Volume 7, Chapter 2 of the Master Plan, resulted in several recommendations for rehabilitation of the ponds to improve and sustain performance. The Percolation Pond Rehabilitation Project is recommended to maintain long-term performance and reliability of the percolation pond system.
The rehabilitation work would include removing the top 3 to 5 feet of soil in each of the existing 15 ponds, "cleaning" it to remove unwanted clay and organic matter, and placing it back in the ponds. The operation is expected to take about 5 years to complete, based on completing three ponds per year during the drier summer months, and, for CIP planning purposes, it is anticipated that this work would be repeated periodically as pond percolation rates begin to decline. The actual timeframe for repeating this major pond rehabilitation work will be determined based on performance, and, because the Phase 1 upgrades should result in a much lower solids load to the ponds, it is possible that the timeframe could be extended considerably. For this CIP it was assumed that two rehabilitation projects would be completed within a 15-year period, which is considered to be conservative.
1.3.3 Long-Term Projects
1.3.3.1 Phase 2 Project
The Phase 2 Project represents the final major treatment facility expansion identified in the Master Plan.
Phase 2 construction will provide a total plant capacity of 12-mgd ADWF, to take the City beyond 2060 in terms of the projected flow and loading needs. The project is anticipated to begin planning activities around FY 52/53 and be complete by FY 59/60, and is intended to provide additional treatment capacity required to meet future planning conditions. Figure 1.3 illustrates the facilities that will be upgraded as part of the Phase 2 project.
VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA WASTEWATER TREATMENT PLANT MASTER PLAN 1-7 Figure 1.3 Phase 2 WWTP Preliminary Facilities Layout
VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-8
1.4 Preliminary CIP Schedule
Figure 1.4 presents a planning level schedule for the first 13-years of the proposed CIP and covers the implementation of the Short-Term Projects and the start of the Medium-Term Project. As indicated, the three short term projects are expected to be complete by the end of 2036, which includes the Percolation Pond Expansion Project and the large Phase 1 Expansion Project. The other Short-Term project that is underway is on-going maintenance of the existing WWTP to keep it performing as efficiently as possible.
The Medium-Term project is focused on rehabilitation of the existing percolation ponds, and that is expected to get underway in 2035, although the timing for this will depend on the status of the construction of the Phase 1 Expansion and the performance of the existing and new ponds. The new ponds are expected to be on-line in 2030.
Planning for the future Long-Term Phase 2 Expansion project is not expected to start until about 2052, which is well beyond the timeline shown in Figure 1.4.
Figure 1.4 Planning Level Schedule for First 13 Years of the Proposed CIP
1.5 Summary of CIP Projects
Table 1.1 summarizes the five major recommended CIP projects, covering the short-term, medium-term and long-term implementation periods, and planning-level project costs. Project costs were developed in the corresponding technical chapters of this Master Plan and are presented herein for implementation planning purposes. Actual project costs should be refined during subsequent planning, design, and budgeting efforts. As indicated, the total anticipated expenditure for all major projects identified through FY 59/60 is approximately $935 million. Graphical representations of the values in Table 1.1 are presented below.
VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA WASTEWATER TREATMENT PLANT MASTER PLAN 1-9 Table 1.1 Detailed Summary of CIP
Project Name
CIP Cost
Estimate Total
($)
CIP Cost by FY and Phase ($)
Short-Term Medium-Term Long-Term
WWTP Maintenance; Percolation Pond Expansion; Phase 1 Project Pond Rehabilitation Phase 2 Project FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32 FY 32/33 FY 33/34 FY 34/35 FY 35/36 FY 36/37 FY 37/38 – 41/42 FY 42/43 – 46/47 FY 47/48 – 51/52 FY 52/53 – 59/60 Short-Term Projects to Maintain WWTP Operation(1,2,3)
Project 100 - Septage Station Rehabilitation $27,000 $27,000 Project 200 - Headworks Rehabilitation - Phase 1 $386,000 $279,000 $89,000 $18,000 Project 250 - Headworks Rehabilitation - Phase 2 $112,000 $112,000 Project 300 - Primary Trickling Filter, Pump Station, and Primary Clarifier Rehabilitation $411,000 $107,000 $9,000 $257,000 $38,000 Project 400 - Secondary Trickling Filter Rehabilitation $181,000 $47,000 $134,000 Project 500 - Secondary Clarifier Rehabilitation $144,000 $22,000 $122,000 Project 600 - Digester Rehabilitation - Phase 1 $580,000 $569,000 $11,000 Project 650 - Digester Rehabilitation - Phase 2 $156,000 $156,000 Project 700 - Plant Facilities Projects - Phase 1 $459,000 $450,000 $9,000 Project 750 - Plant Facilities Projects - Phase 2 $118,000 $118,000 Percolation Pond Expansion Project(4,5) $76,209,000 $1,540,000 $12,524,000 $35,745,000 $26,400,000 Phase 1 Expansion Project(4,6,7) $536,000,000 $1,258,000 $5,922,000 $9,945,840 $14,684,680 $14,173,680 $42,065,520 $109,108,720 $118,265,840 $118,265,840 $88,954,880 $19,929,000 Phase 2 Expansion Project(4,8) $274,524,000 $274,524,000 Percolation Pond Rehabilitation $46,000,000 $23,000,000 $23,000,000 TOTAL COST(7) $935,307,000 $3,527,000 $19,289,000 $45,966,840 $41,615,680 $14,368,680 $42,065,520 $109,108,720 $118,265,840 $118,265,840 $88,954,880 $19,929,000 $23,000,000 $0 $23,000,000 $274,524,000 Notes: (1) Project costs are in February 2024 dollars. Los Angeles Engineering News-Record Construction Cost Index for February 2024 is 15,214. (2) Total project cost includes a 30 percent contingency, 10 percent for general conditions, 15 percent for general contractor, and 8.75 percent for sales tax based on 50 percent of the baseline cost plus contingency. (3) Total project cost includes a 30 percent markup of the estimated construction cost that accounts for engineering, management, and legal fees. (4) Total project cost includes a 30 percent contingency; 12.5 percent for general conditions; 15 percent for general contractor; 8.75 percent for sales tax based on 50 percent of the baseline cost plus contingency; 15 percent for engineering support during design, 7 percent for construction management; and 9 percent for legal, administrative, and regulatory fees. (5) Project cost has been escalated to midpoint of construction. The midpoint of construction is 2028. (6) Project cost has been escalated to midpoint of construction. The midpoint of construction is 2034. (7) Project totals may not add up due to rounding. (8) Project cost has been escalated to midpoint of construction. The midpoint of construction is 2057.
VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-10
Figure 1.5 presents the projected annual CIP expenditures for the two major short-term projects, namely the Percolation Pond Expansion Project and the Phase 1 WWTP Expansion Project. All costs for the short-term projects, including the projects to maintain WWTP operations are included, but the latter have not been broken out into individual cost items in the figure. As indicated, fiscal year expenditure is expected to peak at close to $120 million per year at the height of the construction of the Phase 1 Expansion Project in FYs 33/34 and 34/35.
Figure 1.5 Projected Annual CIP Outlay Through Fiscal Year 2036/2037 Figure 1.6 presents the overall CIP based on identified projects through 2060. This includes all projects shown in Figure 1.5 as well as the Percolation Pond Rehabilitation project, projected to begin around FY 37/38, and the future Phase 2 expansion of the WWTP projected to begin around FY 52/53. The total anticipated CIP for major project identified through 2060 is expected to total around $935 million, as noted above in Table 1.1.
$0
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
$140,000,000
FY
26/27
FY
27/28
FY
28/29
FY
29/30
FY
30/31
FY
31/32
FY
32/33
FY
33/34
FY
34/35
FY
35/36
FY
36/37
CIP Expenditure ($)
Fiscal Year
PROJECTED ANNUAL CIP OUTLAY
Percolation Pond Expansion Project Phase 1 Expansion Project CIP TOTAL PER FY VOLUME 11 / CHAPTER 1: CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-11
Figure 1.6 Projected Total CIP Through 2060 for all Major Identified Projects TOTAL CIP THROUGH 2060 ~ $935 Million
Short-Term Projects to Maintain WWTP Operation Percolation Pond Expansion Project Phase 1 Expansion Project Phase 2 Expansion Project
Percolation Pond Rehabilitation
8 %
29 %
5 %
57 %
<1 %
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-1
CHAPTER 2 PROJECT DELIVERY
2.1 Introduction
2.1.1 Purpose and Background
Chapter 2 of Volume 11 provides an overview as well as the relative strengths, weaknesses, and applicability of various project delivery methods the City will consider for implementation of the Phase 1 Project. In addition, this chapter describes the evaluation factors the City is considering in selecting the project delivery method, and also recommends the initial direction regarding the selected project delivery approach.
When considering a project delivery method, owners generally follow this structured approach in order to reach a supportable decision:
1. Confirm Project Drivers - Identify and confirm the key project drivers and success factors that the chosen project delivery method must address.
2. Identify Applicable Delivery Methods - Identify traditional and alternative project delivery methods, consider their inherent strengths and weaknesses, and establish the applicability of these methods to the owner's legal requirements, characteristics, values, and needs, as well as their applicability to the project drivers specifically.
3. Develop Evaluation Criteria - Develop and define key project drivers and appropriate considerations to be used in the evaluation.
4. Evaluate Delivery Methods - Compare the project delivery methods based on the key project drivers and evaluation criteria.
2.1.2 Project Drivers
A myriad of potential drivers come into play on any large capital improvement project. Typical examples include:
Schedule - Does the Project need to be operational to comply with regulatory and/or funding deadlines?
Cost - Is the owner facing affordability challenges for the Project, requiring minimization of capital and life-cycle costs?
Innovation - Does the Project require a unique technical approach? Are there construction challenges related to the site?
Operations and Maintenance (O&M) Coordination - What requirements or constraints need to be addressed from an operational perspective?
Political - Do the owner's elected officials have particular goals or concerns that must be addressed? Community - Does the community have concerns regarding cost, aesthetics, odor, noise, etc.? Risk Transfer - Does the owner wish to allocate Project risk to other parties? VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-2
When considering project delivery approaches, owners need to carefully consider these drivers and weigh their relative importance in order to select the optimal delivery approach, as each methodology possesses certain tradeoffs among its advantages. For example, certain delivery methods can create schedule efficiencies, yet sacrifice owner control. Others can provide a very high level of owner control, yet sacrifice market price competitiveness. As discussed later in this chapter, the evaluation of project delivery methods needs to involve thoughtful criteria that directly reflect project drivers.
2.2 Project Delivery Methods
A range of project delivery methods is available and regularly utilized in the public infrastructure industry for vertical construction and water/wastewater projects. While traditional "design-bid-build" (DBB) has been the preferred delivery method for water/wastewater projects for many decades, owners have been increasingly turning to alternative project delivery approaches that may offer certain owner and project benefits over DBB. To date, the City has used the DBB delivery method exclusively, and the planned Phase 1 Project represents the largest capital project that the City has undertaken to date.
The most common alternative delivery methods in use for water/wastewater projects include Construction Manager At-Risk (CMAR) and two different variants of the Design-Build (DB) method. As described later in this chapter, each method possesses specific advantages and disadvantages that can make it more or less applicable to different organizations and projects. On October 11, 2025, California Governor Gavin Newsom approved Senate Bill (SB) 598, which added Section 22199.5 to the California Public Contract Code that authorizes the use of the Construction Manager/General Contractor (CMGC) project delivery method for water and wastewater infrastructure projects. CMGC is synonymous with CMAR, the latter term now obsolete in California; CMGC will be used for the rest of this chapter.
As such, the following delivery methods for this evaluation were initially deemed the most relevant to the City's Project:
Design-Bid-Build (DBB).
Construction Manager/General Contractor (CMGC).
Progressive Design-Build (PDB).
Fixed Price Design-Build (FPDB).
Other delivery methods, such as Design-Build-Operate/Finance, Engineer-Procure-Construct, Job Order Contracting, etc., are not considered applicable to the delivery of the Project because the City intends to own, operate, and finance the Phase 1 Project once complete, and so these methods were eliminated from further consideration.
Table 2.1 presents a summary of the delivery methods applicable to the Phase 1 Project and the familiarity of each to the City.
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-3
Table 2.1 Project Delivery Methods
Delivery Method City Experience General Method Application Design-Bid-Build (DBB) Traditional delivery method,
well understood and used
extensively for City capital
projects.
DBB is the most common delivery method for
construction projects regardless of location and type.
Construction Manager/
General Contractor (CMGC)
None. Less common than DBB. Used for transportation and vertical construction projects when contractor input is required early in design. CMGC is gaining acceptance in the water/wastewater industry, and there are projects
underway in the region using this approach.
Progressive Design-Build
(PDB)
None. Providing similar benefits as CMGC, PDB is becoming more common in the water/wastewater industry.
Fixed-Price Design-Build
(FPDB)
None FPDB was the first alternative project delivery method used in the water/wastewater industry and remains
widely accepted.
Key differences between the project delivery methods lie in the contractual and working relationships employed, and in how and when project costs are established. The following sections provide a brief description of the four delivery methods described in Table 2.1.
2.2.1 Design-Bid-Build
DBB is the most commonly utilized project delivery method. For most projects, the owner and/or its design consultant completes the design and develops construction documents, from which bids are solicited. The selection of the contractor is based on the lowest responsive bid, and the contractor serves as a single point of responsibility for construction. As mentioned, this is the delivery approach that the City has used exclusively to date for completing capital projects.
In the DBB structure, there is no contractual relationship between the designer and the contractor. The engineer typically prepares cost estimates throughout the design of the project, but the construction cost is not established until the lump sum bids are received. Because the design is completed by the owner or its consultants, the owner/engineer retains the design risk for the project. Change orders tend to be more common under DBB than other project delivery variants, as there are no mechanisms built into this delivery method to react to or incorporate necessary project adjustments or deviations without a change order, and also because the design typically does not receive contractor review until the procurement stage. However, owners typically set aside a contingency amount to cover anticipated changes.
2.2.2 Construction Manager General Contractor
The CMGC delivery approach is contractually similar to the DBB method in that the designer and the contractor are contracted as separate entities. Like DBB, the project design may be completed by the owner/owner's consultant, but the model is more commonly administered using a third-party designer.
The primary difference between CMGC and DBB is that the contractor is selected early in the design process based on a best-value selection process that incorporates qualifications, experience, and minimal project cost information. During the preconstruction phase services period, the contractor provides input during the design process to develop more detailed cost estimates as the project progresses. This VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-4
ultimately leads to a negotiated guaranteed maximum price (GMP) generally established between 60 to 90 percent design completion. This delivery method also allows for certain portions of the project to be released for construction (i.e., "early construction packages") before the entire design is complete, which can facilitate a reduction in overall project schedule. While the City still retains the design risk associated with this project delivery method, exposure to change orders is generally reduced due to the contractor's involvement during design. In addition, risks associated with exceeding the construction budget can be shifted to the contractor.
2.2.3 Progressive Design-Build
PDB is essentially identical to the CMGC delivery approach, with the exception being the use of a "single entity" contracting method. While under CMGC, the owner executes separate agreements with the design engineer and the contractor, in PDB, the owner executes a single agreement with the PDB entity (generally a contracting firm or joint venture). Because the design-builder is a single point of responsibility for both design and construction, it assumes both design and construction liability. Like CMGC, under PDB, the design-builder is selected through a qualifications-based, or best-value, selection process.
PDB allows the owner to maintain an influence over the design, similar to CMGC, but in the case of PDB, the design-builder owns the design risk – a key differentiator over CMGC. Similar to CMGC, construction cost estimates are prepared throughout the design process, and a GMP is typically negotiated between the 60 percent to 90 percent design completion.
Early work packages are also possible under this model, facilitating schedule efficiencies, and the contractor's involvement during design reduces owner exposure to change orders. It is worth noting that under the PDB model, the design engineer is working for and being paid by the contractor. So, the typical owner-engineer relationship in which the engineer is looking after the interests of the owner is no longer there.
2.2.4 Fixed-Price Design-Build
FPDB is a "single entity" project delivery method that provides the same design and construction risk transfer benefits as the PDB approach. However, unlike PDB (and CMGC), FPDB is not a collaborative delivery method wherein the design engineer and construction contractor work together to advance the design and construction cost estimate until a GMP can be reached.
Instead, as the name implies, FPDB incorporates a best-value procurement process where the owner provides proposers with technical bridging documents developed to the degree necessary to solicit fixed pricing for the project. Selection of the FPDB team involves a best-value evaluation, which considers the fixed pricing element. While this delivery model offers the owner price certainty, its use requires thorough consideration of the project's technical requirements, particularly those impacting operations, in order to avoid costly change orders. To this end, owners typically produce designs that are at the 10 to 30 percent completion level together with detailed design criteria and "minimum" technical specifications to incorporate as many of the owner's preferences as possible prior to issuing the package for bidding.
A summary of advantages and disadvantages of each of the applicable delivery methods is provided in Table 2.2. In addition, Appendix B includes presentation slides provided to the City during a workshop in August 2025 (Workshop No. 7) in which these delivery methods were discussed in more detail.
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-5
Table 2.2 Advantages and Disadvantages of Delivery Methods Method Advantages Disadvantages
Design
Bid-Build (DBB)
Institutional familiarity and well-understood contracting relationships
High level of control over design elements
Project scope fully defined at commencement of construction Competitive bidding environment
Some control over contractor quality when qualifications based evaluation criteria are used in the bid process
Owner legal exemption is not needed
Familiar to local contracting community
Sequential design-bid-build process typically extends schedule Owner warrants design to contractor (assumes design risk) No contractor input during design
Cost certainty not obtained until after design is complete and the project has been bid
Increased potential for change orders
Greater potential for disputes
Little control of contractor selection (i.e., lowest responsive bid dictates selection)
Managing multiple contracts (i.e., separate design and construction contracts)
Construction
Manager/General
Contractor
(CMGC)
Design can be completed by the owner or by a consultant based on resource availability
Qualifications-based selection of designer and/or contractor High level of owner design control
Cost certainty can be established earlier in the project if CMGC procured early in design
Contractor input during design
Opportunities for collaboration between parties
Potentially shortened schedule
Significant opportunity for owner input/review (control over quality)
Flexibility to off-ramp if GMP not considered realistic Design packages must be sufficient to mitigate change orders Negotiating GMP sometimes difficult
Managing multiple contracts (i.e., separate design and construction contracts)
Much of the design risk is still assigned to the owner since the designer is contracted separately from the contractor, although some risk is mitigated by early involvement by the contractor
May not result in lowest possible cost, but cost competitiveness is gained through "open book" negotiations and bidding of subcontract work Performance guarantees not available from contractor
Less familiar to local contracting community and owner's elected officials and stakeholders
Requires additional owner resources to manage project delivery VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-6
Method Advantages Disadvantages
Progressive
Design-Build
(PDB)
Qualifications-based selection
Potentially shortened project schedule
Increased owner control over project (relative to other design-build variants) Transfer of design-related risk to design-build team
Implemented in phases or task orders to save time and keep the project moving
Single contract between owner and design-builder (single point of accountability)
Potential for increased competition relative to other project delivery variants due to lower proposal costs
Innovation from design-build team allows potential cost savings (i.e., works well when the project is complex or lacks definition) Early cost determination
Flexibility to design to budget
Allocation of risk flexibility
Owner does not hold design contract
Owner has little control over development of design elements as design engineer now works for the contractor
Construction costs are unknown when initial contract is signed Public perception of higher costs since they are negotiated rather than "hard bid"
Negotiating the GMP can be more difficult if the design-builder is self-performing a significant amount of the work Less familiar to local contracting community and owner's elected officials and stakeholders
Requires additional owner resources to manage project delivery Fixed-Price
Design-Build
(FPDB)
Best-value based selection of contractor
Has potential for accelerated project schedule
Provides design-builder with significant flexibility to develop innovative designs, which can result in maximum potential for cost savings
Early establishment of construction cost and construction schedule
Transfer of design-related risk to design-builder
Competitive process at the bidding stage
Performance guarantees available (i.e., works well when the project can be defined using performance metrics)
Single contract between owner and design-builder (single point of accountability)
Owner has little control over development of design elements Engineer works for the contractor
Potential for increased life-cycle costs (due to selection of lower capital cost equipment that may have higher O&M costs)
Determining exactly what the owner expects relative to overall performance is key to obtaining an acceptable product
Complex procurement process
Existing conditions and permitting uncertainty prior to design-build contract
Potential for decreased competition due to cost of preparing proposal (can be offset by providing a stipend to proposers, which adds cost for the owner)
Less familiar to local contracting community and owner's elected officials and stakeholders
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-7
2.3 Delivery Method Evaluation and Recommendations
2.3.1 Evaluation Criteria
Table 2.3 presents the more common criteria owners consider when selecting a project delivery method.
The application of these considerations to the various delivery methods is presented in the subsection that follows.
Table 2.3 Considerations for Alternative Project Delivery Consideration Definition
Level of Control
Design The ability of the owner to exercise control of project design.
Project Quality The ability of the owner to exercise control of the contractor's approach towards ensuring quality of the work.
Owner Resources The degree to which the delivery method impacts owner staffing and/or administrative needs.
Schedule
Project Phase Duration The extent to which the delivery method impacts the procurement and project implementation schedule/duration.
Cost
Cost Efficiency The degree to which the delivery method impacts price competitiveness and resulting project cost efficiencies.
Cost Certainty The point at which the delivery method provides cost certainty at contract execution and beyond.
Cost Transparency The degree to which the delivery model allows owner review of the construction procurement process and resulting cost estimates.
Flexibility to Control Costs The extent to which the delivery method allows for flexibility to change scope to control costs.
Risk Allocation
Design and Construction
Risk
The extent to which the delivery method transfers project design risk to the contracting entity.
Project Performance Risk The extent to which the delivery method promotes the transfer of risk for overall project performance.
Political Risk The extent to which the local contracting community and governing bodies are familiar with delivery method (i.e., less familiarity can result in greater political risk).
2.3.1.1 Level of Control
Evaluating the comparative level of control among delivery methods involves considering the owner's control over project design and the ability to mandate specific quality requirements.
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-8
Design
The DBB approach provides the owner with the largest degree of design control. This is due to the direct contractual relationship with the design engineer, coupled with the advancement of the design via various review submittals to obtain owner input to 100 percent completion.
CMGC provides a similar degree of design control via direct contracting with the designer. Once the GMP is reached and agreed upon, generally around 60 to 90 percent, owner control over the final design product may be reduced.
PDB provides less design control as the design engineer is not under direct contract with the owner and may be influenced by competing objectives of the construction contractor who holds the PDB contract.
Lastly, under FPDB, design control is limited to the content of the procurement's technical bridging documents, which generally includes a design advancement of approximately 30 percent. The FPDB is free to complete the design as it sees fit.
DBB will result in quality materials and equipment being utilized by the contractor since the contract documents (drawings and specifications) are prepared by the owner to reflect quality preferences.
However, the owner's selection of a contractor is based solely on a low bid (pre-qualification of contractors or use of the owner's provision to consider other factors than cost can provide some control).
Additionally, limited opportunity exists for owner involvement in subcontractor procurement through DBB, so poorly qualified subcontractors could potentially affect the quality of construction.
Conversely, both CMGC and PDB allow for the City to control the quality of the contractor by mandating the use of a best-value/qualifications-based selection process, and to potentially be involved in the pre-qualification process for subcontractors. FPDB quality prescription is limited by what is contained in the procurement technical bridging documents.
One criticism of alternative delivery methods, compared to DBB, is the poorer quality of record drawings and general project documentation. Assigning such tasks to a third-party construction manager may be a way to provide higher quality finished products for the owner.
Owner Resources
Level of control and owner resources requirements go hand in hand. CMGC and PDB require additional owner staff resources or a consultant to assist with the procurement and oversight during the preconstruction phase services, as the design is advanced and the cost model is developed. These additional costs are not required for traditional DBB or FPDB methods, where lump sum costs are established without the negotiation step. FPDB requires considerable owner involvement during the procurement process.
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-9
2.3.1.2 Schedule
In general, no project delivery model is inherently faster or slower than others. The various approaches contain differing opportunities for schedule efficiency during both the procurement and delivery phases, based on the parameters identified below.
Procurement Duration - The PDB approach can provide the greatest procurement schedule efficiency, as there is usually no need for advanced technical bridging documents, and the owner is soliciting a single contracting entity. CMGC requires an extra procurement step for selection of the separately-contracted design engineer. The procurement under DBB is relatively straightforward, yet the duration is dependent on the required effort in completing the design. Under FPDB, procurement duration is directly related to the level of design completion in the technical bridging documents.
Contract negotiation durations tend to be longest under FPDB, followed by CMGC, PDB, and DBB. Preconstruction Phase Services - Unique to the CMGC and PDB delivery models, the "preconstruction phase services" consist of the advancement of the project design to approximately 60 percent and the concurrent development of the GMP cost model. It is during this phase that schedule efficiency can vary dramatically. Misalignment between the design engineer and the contractor can lead to time-consuming iterations of work products, delaying the development of the GMP. Additionally, owner-created inefficiencies (e.g., multiple design review efforts, excessive review durations, etc.) during the preconstruction phase can also slow the process. Construction Phase Services - Both single-entity variants of project delivery options (PDB and FPDB) offer the greatest opportunity for schedule efficiency during construction due to the potential overlap of design and construction activities. Typically, another schedule advantage of CMGC and PDB is the capability to shorten the overall construction schedule through the issuance of early construction packages, which requires accelerating certain design components.
The DBB approach, on the other hand, carries a larger potential risk of schedule delay due to the model's vulnerability to change orders and the requirement of 100 percent design drawings and specifications completion before bidding. However, change orders do provide a mechanism to make adjustments in the field, and owners typically hold some amount of contingency for this. Also, the level of change orders is highly dependent on the quality of the plans and specifications.
2.3.1.3 Cost
Cost considerations can also vary widely among the project delivery methods and fall into the categories discussed below.
Cost Efficiency - As with the schedule criterion discussed above, it is difficult to draw absolute conclusions regarding the ability of the various project delivery methods to provide cost savings.
Generally speaking, DBB and FPDB provide the best opportunity for cost savings due to the fact that the project cost is competitively procured and influenced by market price competition. Conversely, under the collaborative delivery methods of CMGC and PDB, despite the use of "open book" pricing, true price competition is generally not available. Instead, the owner must require the CMGC/PDB contractor to implement a procurement plan for subcontractors and equipment that facilitates market price competition, for example, requiring a certain number of bids, using standardized bidding forms, etc.
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-10
Cost Certainty - Under DBB and FPDB, cost certainty is provided at the procurement stage in the form of a "hard bid" under DBB, or a "fixed DB price" under FPDB. The owner receives the project cost information prior to executing the contract. Under CMGC and PDB, the owner only receives guaranteed pricing for the preconstruction phase services, with the project GMP not being provided until those services are completed (typically at 60 percent design). The owner retains the right to "off ramp" should the GMP be unacceptable, but some owners and/or stakeholders are uncomfortable executing a contract without knowing the ultimate project construction cost. Cost Transparency - Despite lacking price competition and initial cost certainty, CMGC and PDB provide an extremely transparent project costing approach. Under these collaborative models, the CMGC or PDB team develops a procurement plan for approval by the owner, identifying the approach that will be implemented to secure subcontractor services and equipment purchases. The procurement plan will also address self-performance and provide the owner with the ability to mandate the bidding of any/all project elements. All documents prepared and all pricing information received is shared with the owner, i.e., provided "open book." Additionally, the GMP developed under these models will clearly identify various cost contingency amounts and the assumptions regarding their calculation. DBB and FPDB do not offer cost transparency for either project pricing or contingency. However, most owners typically allocate an internal contingency sum to account for differing site conditions and/or change orders.
Cost Control - Project delivery methods vary in their ability to provide cost control via their ability to adjust in response to potential budget challenges. Because the collaborative models of CMGC and PDB involve the daylighting of project cost information as early as the Basis of Design Report (BODR) stage, future design efforts at 30 percent and 60 percent can incorporate value engineering, constructability considerations, and/or other project scoping adjustments to reduce project cost prior to GMP. These approaches allow owners to avoid the "bid surprise" which can occur under DBB and FPDB.
2.3.1.4 Risk Allocation
When considering risk allocation under various project delivery methods, industry best practice dictates that risk should be allocated to the party best able to manage the risk. The most common risks, as well as mitigation and pricing considerations, are summarized below. Design and Construction Risk - Single-entity project delivery models such as PDB and FPDB provide the ability to transfer all design and construction risk to the contracting entity. Under these models, the DB contractor is responsible for any deficiencies in the project design and any associated construction challenges. Conversely, under DBB and CMGC, because the owner owns the design contract, the construction contractors under those two delivery models are insulated from design deficiencies and/or incongruence with construction requirements. However, under these approaches, the owner still retains a contract with the design engineer who would be responsible for errors and omissions.
Project Performance Risk - Directly related to design and construction risk allocation, under FPDB and PDB, the owner is also able to transfer the risk of the overall ability of the project to meet all operational performance requirements of the project. Again, because DBB and CMGC are not single-entity contract instruments, the owner's ability to transfer performance risk is a little more VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-11
difficult, but as mentioned, a contract will be in place with the design engineer for errors and omissions.
Political Risk - Political risk is also a consideration when selecting a project delivery method. While collaborative delivery approaches such as CMGC and PDB have been in use for over 20 years, many owners are uncomfortable moving away from their proven use of the DBB model. The application of a new, unfamiliar project delivery approach will inevitably require an owner to dramatically change its contracting and procurement approach and philosophy. Further, as discussed above, CMGC and PDB do not provide project cost certainty at contract execution—a concept some owners and other stakeholders find uncomfortable.
2.3.2 Recommended Project Delivery Method
2.3.2.1 Initial Considerations
During the August 27, 2025, Workshop No. 7, Carollo Engineers (Carollo) facilitated a discussion to apply the evaluation criteria described above and other considerations to the specific objectives and risks of the Phase 1 Project. While the City and Carollo did not conduct a formal, weighted evaluation of the four project delivery methods discussed, the relative importance of the evaluation criteria were discussed, and the following conclusions were reached:
City legal counsel must opine on state and City legal authorization for CMGC and both DB variants. The City wishes to possess a high degree of control over Project design. The individual qualifications and experience of the design engineer and construction contractor should be considered in the procurement processes.
Involvement by City O&M personnel will be instrumental in the development of the Project design. The Project construction approach must take into account coordination with the ongoing O&M requirements of those existing plant facilities that will remain in operation during and after Project construction.
City Council must be educated on the various project delivery approaches and how they differ from the traditional DBB approach historically implemented by the City. Overall Project schedule duration is not the most important criterion for this Project when considering the delivery method.
The group concluded that, based on the above assessment, the most appropriate project delivery models to consider for the Phase 1 project are DBB and CMGC.
2.3.2.2 Project Delivery Update
As mentioned, SB 598 was approved in October 2025, which authorizes the use of the CMGC project delivery method for water and wastewater infrastructure projects. While the City should seek the opinion of legal counsel, it is highly probable that CMGC can be used by the City to deliver the Project.
2.3.2.3 Proposed Project Delivery Scenario
During a follow-up meeting with the City on May 20, 2026, the City and Carollo again discussed the possible paths forward for selecting the project delivery method. Because the Phase 1 Project is such a VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-12
significant endeavor and will take eight or nine years to design and construct, it is important that the City does not get locked into a delivery method early on that limits flexibility. Accordingly, the focus of the discussion was "how to keep the City moving ahead with the Phase 1 design while retaining flexibility to adjust the project delivery method if and when deemed appropriate". Each of the two preferred delivery methods of DBB and CMGC was discussed, and the following scenario was developed.
Figure 2.1 presents an approximate timeline for delivery of the design portion of the Phase 1 project via the traditional DBB approach, expected to take about three and a half years to complete. As shown, the City would procure a design engineer in 2027 to provide preliminary design services. For the purposes of this discussion, a design level of approximately 30 percent was selected as a reasonable point to potentially refine the delivery method, as discussed below. However, this does not prevent the City from choosing to refine the delivery approach at any point prior to reaching the 30 percent level.
A design level of approximately 30 percent was chosen as a starting point because this would represent a sizable engineering design contract for a project of this magnitude and will take considerable time to complete.
Figure 2.1 Traditional DBB Approach for Phase 1 Delivery Upon completion of the "preliminary design" (30 percent or less), the City would have the flexibility to refine the delivery method. As shown in Figure 2.2, the City would have the choice to continue with the traditional DBB approach, as shown along the bottom of the graphic, or switch to the alternative CMGC delivery method, shown on the top.
If the City decides to continue with the DBB approach, the design engineer (or a new design engineer) would proceed with completing the design to 60 percent, 90 percent, and 100 percent. Alternatively, if the CMGC route is chosen, a general contractor would be selected using a qualifications-based approach to work with the City's design engineer to complete the design to 60 percent. The City would sign a Preconstruction Phase services contract with the selected contractor.
CAROLLO / 7
updatefooter0323.pptx/7 SantaMaria-052026-FlowDiagram-Graphic
PRELIMINARY
DESIGN 30%
C
O
N
S
T
R
U
C
T
I
O
N
2028 2029 2030
Select
Designer
for PDR
DBB
60%
Design
90%
Design
100%
Design
BID
Consider
Offramp
Consider
Offramp
2027 2031 2032
Refine
Delivery
Method
Option
to
Refine
Delivery Method
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-13
Figure 2.2 Option for Refinement of the Project Delivery Approach After 30% Design If the CMGC route is selected, then, as shown in Figure 2.3, the CMGC contractor will prepare a GMP after completion of the 60 percent Design. At this point, the City can again consider its options:
1. If the GMP submitted by the contractor seems reasonable and the City feels committed to working with the contractor for the duration of the Phase 1 project, then the City could accept the GMP and sign a Construction Phase services Amendment with the contractor, and the CMGC would proceed with finishing the design and move into construction.
2. If, on the other hand, the City is not comfortable with the GMP number, the City could:
a. Tell the CMGC (through a separate contract amendment and additional cost) to advance the design to 90 percent and submit another more competitive GMP, or b. Turn to its designer, who is under a separate contract, and instruct him to complete the design, in which case the project would be finalized and delivered by DBB.
CAROLLO / 8
updatefooter0323.pptx/8 SantaMaria-052026-FlowDiagram-Graphic
PRELIMINARY
DESIGN 30%
C
O
N
S
T
R
U
C
T
I
O
N
2028 2029 2030
Select
Designer
for PDR
DBB
60%
Design
90%
Design
100%
Design
BID
Consider
Offramp
Consider
Offramp
2027 2031 2032
Refine
Delivery
Method
Option
to
Refine
Delivery Method
CMGC
60%
Design
GMP
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-14
Figure 2.3 At 60% Design, There is Flexibility to Stay With CMGC or Switch Back to DBB If the option to stick with the CMGC is selected, then, as shown in Figure 2.4, there is one more opportunity to adjust the delivery method. Once the CMGC reaches the 90 percent design level and issues its final GMP, the City will have the same choice as before:
1. Accept the updated GMP and sign an Amendment with the contractor for the Construction Phase services to complete the design and construction of the Phase 1 project, or
2. Ask the design engineer to complete the design and switch back to the DBB approach. Once the design is completed, the project will be competitively bid.
Figure 2.4 Final Choice to Complete the Project via CMGC or DBB CAROLLO / 9
updatefooter0323.pptx/9 SantaMaria-052026-FlowDiagram-Graphic
PRELIMINARY
DESIGN 30%
C
O
N
S
T
R
U
C
T
I
O
N
2028 2029 2030
Select
Designer
for PDR
DBB
90%
Design
100%
Design
BID
Consider
Offramp
Consider
Offramp
2027 2031 2032
Refine
Delivery
Method
Consider
Offramp
CMGC
60%
Design
GMP
VOLUME 11 / CHAPTER 2: PROJECT DELIVERY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-15
2.3.2.4 Discussion
The above scenario may be a little cumbersome with the back and forth between delivery methods and the associated additional project costs, but the purpose is to illustrate an approach that the City could use to deliver the Phase 1 Project. The benefit would be a highly flexible approach that does not limit the City's ability to make adjustments to the delivery approach if certain conditions present themselves. The design process itself, irrespective of delivery method, is expected to take about three and a half years to complete. Much can change in the water/wastewater construction market during this period, hence the proposed methodology to keep the delivery approach flexible.
Based on the delivery scenario presented above, the following concluding points can be made:
1. The City can begin the procurement for design services for the Phase 1 project and complete the design to about a 30 percent level and still retain final project delivery flexibility.
2. Once the 30 percent design level is reached, the City will have the flexibility to switch to the CMGC alternative delivery approach or continue on with the traditional DBB approach and competitively bid the project. By reassessing the delivery method after completion of the preliminary design, the City would be able to gather more information regarding the relative strengths and weaknesses of the chosen approach based on project-specific considerations.
Note that once the design gets beyond the 30 percent level, the benefits of switching to CMGC diminish, so this would likely be the final opportunity to switch to CMGC. But the flexibility to switch back to DBB from CMGC would remain until a GMP is accepted.
3. If at the 30 percent design level a switch is made to the CMGC approach, then the design will proceed to the 60 percent level with two contracts in place: one with the design engineer and the other with the selected contractor.
4. At the 60 percent level and assuming the CMGC delivery method, the contractor would issue a GMP to the City. If this is acceptable, the City will sign the Construction Phase services agreement with the Contractor, and the CMGC will continue to complete the design and construction.
5. If, at 60 percent design, the GMP is not acceptable, then the City can either ask the CMGC to proceed to 90 percent completion and issue another GMP, by issuing an amendment, or the City could retain the design engineer to complete the design via the DBB approach.
6. If the CMGC is asked to proceed to 90 percent and submit another GMP, then, based on the outcome of the updated GMP, the City can again either elect to complete the project via the CMGC approach or retain the design engineer to complete the design, and the project would be competitively bid and delivered by DBB.
Finally, this approach allows the City to begin the design of the Phase 1 project using the familiar approach of DBB but offers the flexibility to change the delivery method if that is seen to be in the best interests of the City.
VOLUME 11 / CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX A SHORT-TERM CAPITAL IMPROVEMENT
PROGRAM PROJECTS TO MAINTAIN
EXISTING WWTP
FY 2024-2028 FY 2029-2031 Notes
Priority
100 Area 1 3 Septage Station Rehabilitation $ 27,000 $ - $ 27,000 Low priority 200 Area 2- 1A, Area 2- 1B, Area 2- 1C, Area 2-1E 1 Headworks Rehabilitation - Phase 1 $ 386,000 $ 18,000 $ 368,000250 Area 2-1D 3 Headworks Rehabilitation - Phase 2 $ 112,000 $ - $ - $ 112,000 May defer to Phase 1 Contractor's Scope 300 Area 3- 1A, Area 3-1B, Area 3-1C, Area 3-1D, Area 4-1A, Area 4-1B, Area 4- 1C 2 Primary Trickling Filter, Pump Station, and Primary Clarifier Rehabilitation $ 411,000 $ 154,000 $ - $ 257,000 400 Area 5-1A, Area 5-1B, Area 5-1C, Area 5-1D 1 Secondary Trickling Filter Rehabilitation $ 181,000 $ - $ 181,000 $ - 500 Area 6-1A, Area 6-1B, Area 6-1C 2 Secondary Clarifier Rehabilitation $ 144,000 $ - $ 144,000 $ - 600 Area 7-1A, Area-7-1D 2 Digester Rehabilitation - Phase 1 $ 580,000 $ 11,000 $ 569,000 $ - 650 Area 7-1B, Area 7-1C 3 Digester Rehabilitation - Phase 2 $ 156,000 $ - $ - $ 156,000 700 Area 8-1A, Area 8-1D 2 Plant Facilities Projects - Phase 1 $ 459,000 $ 9,000 $ 450,000 $ - 750 Area 8-1B, Area 8-1C 3 Plant Facilities Projects - Phase 2 $ 118,000 $ - $ - $ 118,000 Area 1 Area 1 3 Septage Station - Clean and coat Columns $ 27,000 $ - $ - $ 27,000 Area 2 - 1A Area 2 - 1A 1 Headworks - Repairs to slab and provide backfill $ 234,000 $ - $ 234,000 $ - Area 2 - 1B Area 2 - 1B 1 Grit Chamber Structure - Repairs to expansion joints $ 89,000 $ - $ 89,000 $ - Area 2 - 1C Area 2 - 1C See O&M Clean and Replace Sump Pump #1 $ 18,000 $ - budget incorporated into routine O&M Area 2 - 1D Area 2 - 1D 2 Clean and Replace Proportional Butterfly Valve $ 112,000 $ - $ - $ 112,000 Maintain until Phase 1 expansion Area 2 - 1E Area 2 - 1E 2 Proportional Valve Actuator $ 45,000 $ - $ 45,000 $ - Area 3- 1A Area 3- 1A 3 Intermediate Clarifier Structure $ 45,000 $ - $ - $ 45,000 Changed to Low Priority Area 3 - 1B Area 3 - 1B 3 Intermediate Clarifier Drive $ 20,000 $ - $ - $ 20,000 Changed to Low PriorityArea 3 - 1C Area 3 - 1C See O&M Primary Sludge Building Blowers $ 47,000 budget incorporated into routine O&M Area 3 - 1D Area 3 - 1D 3 Primary Sludge Building Structure $ 27,000 $ - $ - $ 27,000 Area 3- 1E Area 3- 1E - Primary Sludge Pump #1 $ - $ - $ - $ - Project complete Area 4 - 1A Area 4 - 1A 3 PTF #1 Structure $ 89,000 $ - $ - $ 89,000 Monitor, reassess biannually. Area 4 - 1B Area 4 - 1B 1 PTF Pump Station Structure $ 76,000 $ - $ - $ 76,000Area 4 - 1C Area 4 - 1C See O&M PTF Pump Station Operators $ 107,000 $ - budget incorporated into routine O&M Area 4- 1D Area 4- 1D - PTF #1 Rotary Distributor $ - $ - $ - $ - Project complete Area 5 -1A Area 5 -1A 1 STF #1 Structure $ 67,000 $ - $ 67,000 $ - Area 5-1B Area 5-1B 1 STF #2 Structure $ 67,000 $ - $ 67,000 $ - Area 5 - 1C Area 5 - 1C 1 STF Pump Station Structure $ 27,000 $ - $ 27,000 $ - Area 5 - 1D Area 5 - 1D 1 STF Pump Pipe Supports $ 20,000 $ - $ 20,000 $ - Change to High Priority for grouping Area 5-1E Area 5-1E - Secondary Sludge Pumps 1 and 3 $ - $ - $ - $ - Project complete Area 5-1F Area 5-1F - Secondary Sludge Pump 2 $ - $ - $ - $ - Project complete Area 6 - 1A Area 6 - 1A 1 Secondary Clarifier #1 Structure $ 22,000 $ - $ 22,000 $ - Area 6 -1B Area 6 -1B 1 Secondary Clarifier #2 Structure $ 22,000 $ - $ 22,000 $ - Area 6 - 1C Area 6 - 1C 2 Mechanical Pumps and Drives $ 100,000 $ - $ 100,000 $ - Area 7-1A Area 7-1A 1 Digester #1 and 3 Structures $ 569,000 $ - $ 569,000 $ - Minimized expenditure on Dig #3 Area 7-1B Area 7-1B 3 Sludge Thickener #1 Structure and Catwalk $ 78,000 $ - $ - $ 78,000 ST #1 is from 1961 Area 7-1C Area 7-1C 3 Sludge Thickener #2 Structure and Catwalk $ 78,000 $ - $ - $ 78,000 Area 7-1D Area 7-1D See O&M Digester Control Building $ 11,000 $ - budget incorporated into routine O&M Area 8-1A Area 8-1A 2 Storage Building Structure $ 450,000 $ - $ 450,000 $ - Area 8-1B Area 8-1B 3 Maintenance Shop Structure $ 31,000 $ - $ - $ 31,000 Area 8-1C Area 8-1C 3 Maintenance Shop Structure $ 87,000 $ - $ - $ 87,000 Area 8-1D Area 8-1D See O&M Facility Drainage Sump Pumps $ 9,000 $ - budget incorporated into routine O&M CIP Total $ 2,574,000 $ 192,000 $ 1,712,000 $ 670,000
O&M costs $ 192,000
Phase Totals $ 2,382,000 -- $ 1,712,000 $ 670,000
Table Detailed Capital Improvement Program
City of Santa Maria
Short-Term Improvements for WWTP
WASTEWATER TREATMENT PLANT PROGRAM
Proposed CIP Project Number Individual Project Identifiers CIP Cost Estimate(1, 2,3) ($) Cost to O&M budget CIP Cost by Fiscal Year and Phase ($) List of Individual Projects
Notes:(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 4.375% for sales tax of the baseline cost. (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Priority (1 (high)
to 3 (low) scale) Project Name
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 1
Project Name: Septage Station - Clean and coat ColumnsSystem Type: WastewaterProject Description:
$ 12,000 $ 21,000 $ 27,000 2030
Project Detail:
Percent Cost ($)
100% 27,000$
0% $ - 100% 27,000$
Notes on Cost Estimation:Reimbursement Category
Existing Users
Total
Future UsersCoat columns of existing Overhang structure. Place protective curb around the base to prevent water infiltration.Project Details:
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
Project Element ($/ft)
Project Cost Allocation:
Notes:(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project
Schedule
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Miscellaneous
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 2 - 1A
Project Name: Headworks - Repairs to slab and provide backfillSystem Type: WastewaterProject Description:
$ 105,000 $ 180,000 $ 234,000 2026
Project Detail:
Percent Cost ($)
100% 234,000$
0% $ - 100% 234,000$
Notes on Cost Estimation:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 This project involves sealing cracks in the top slab. Restore grouting for bar screen supports at the deck.
Backfill the subgrade of the headworks structure on the south end with pumped slurry. Stabilization of the slope with a retaining wall may be necessary. Add coating to headworks automatic valve actuators.
Project Details:Project Element
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Miscelaneous Repairs
Notes:
Existing Users
Future UsersTotal
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 2 - 1B
Project Name: Grit Chamber Structure - Repairs to expansion jointsSystem Type: WastewaterProject Description:
$ 40,000 $ 69,000 $ 89,000 2027
Project Detail:
Percent Cost ($)
100% 89,000$
0% $ - 100% 89,000$
Notes on Cost Estimation: Future UsersTotal
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
Existing Users
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Reseal all expansion joints along the east and south side of the structure. The east and south side between the slab on grade and the retaining wall have failed sealants. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Miscelaneous Repairs
Notes:
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 2 - 1C
Project Name: Clean and Replace Sump Pump #1System Type: WastewaterProject Description:
Replace 1 $ 8,000 $ 14,000 $ 18,000 2030
Project Detail:
Percent Cost ($)
100% 18,000$
0% $ - 100% 18,000$
Notes on Cost Estimation:
Notes:
Exterior of Sump Pump #1 needs to be cleaned. Included cost assumes full replacement by the project date.CProject Element Proposed
Power
(hp)
Proposed
Capacity
(gpm)
Replace/
New
Proposed
Number
of Pumps Unit Cost(1)
($/gpm)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Pump
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Cost from Santa Maria provided Cost tables. Previous cost based on 2013 estimate. Replacement should occur by 2030 Project Cost Allocation:
Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 2 - 1D
Project Name: Clean and Replace Proportional Butterfly Valve System Type: WastewaterProject Description:
$ 50,000 $ 86,000 $ 112,000 2030
Percent Cost ($)
100% 112,000$
0% $ - 100% 112,000$
Notes on Cost Estimation:Clean exterior and monitor performance. Replace at failure, expected in 2030. Butterfly valve is 36". Will require a complete shutdown to replace. May defer to Phase 1 contractor scope. Project Element Notes:
Project Details:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Butterfly Valve
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation: Project Detail:
Reimbursement Category
Existing Users
Future Users
Total
https://www.ferguson.com/category/valves/butterfly-valves/?customsort=sku_sales_i%20desc&prefn1=sku_Valve_Size_ss&prefv1=36%2Bin&srsltid=AfmBOoqvxNvT6vzuGV7WwVRRCSjIohD96a2dK9o9aPJbWNtcmvWyPqK- Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 2 - 1E
Project Name: Proportional Valve Actuator
System Type: WastewaterProject Description:
$ 20,000 $ 34,000 $ 45,000 2026
Project Detail:
Percent Cost ($)
100% 45,000 $
0% $ - 100% 45,000 $
Notes on Cost Estimation:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Due to age, clean exterior and monitor frequently for performance. Replace if failure occurs.Project Details:
Project Element
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Miscallenous
Notes:
Future UsersTotal
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
Existing Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 3 - 1A
Project Name: Intermediate Clarifier StructureSystem Type: WastewaterProject Description:
$ 20,000 $ 34,000 $ 45,000 2029
Project Detail:
Percent Cost ($)
100% 45,000 $
0% $ - 100% 45,000 $
Notes on Cost Estimation:
Seal cracks along concrete exterior to prevent moisture ingress. Monitor concrete condition and repair with high strength mortar as needed.
Concrete Repairs
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Details:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Project Element Schedule
Notes:
Total
Project Cost Allocation:
Reimbursement Category
Existing Users
Future Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 3 - 1B
Project Name: Intermediate Clarifier DriveSystem Type: WastewaterProject Description:
$ 9,000 $ 15,000 $ 20,000 2029
Percent Cost ($)
100% 20,000 $
0% $ - 100% 20,000 $
Notes on Cost Estimation:Project Element
Notes:
Clean rust on the exteror and epoxy coat the drive. Monitor performance due to ageProject Details:
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Miscallenous repairs
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation: Project Detail:
Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 3 - 1C
Project Name: Primary Sludge Building BlowersSystem Type: WastewaterProject Description:
$ 4,000 $ 7,000 $ 9,000 2028
$ 17,000 $ 29,000 $ 38,000 2030
Percent Cost ($)
100% 47,000$
0% $ - 100% 47,000$
Notes on Cost Estimation:Project Element
Notes:
Blowers leak oil and experience frequent downtime. Repair blowers per O&M methods manual requirements if downtime issues persist. Monitor performance consistently.Project Details:
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Mechanical repairsReplacement
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation: Project Detail:
Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 3 - 1D
Project Name: Primary Sludge Building Structure
System Type: WastewaterProject Description:
$ 12,000 $ 21,000 $ 27,000 2029
Project Detail:
Percent Cost ($)
100% 27,000 $
0% $ - 100% 27,000 $
Notes on Cost Estimation:
Project
Project Element Schedule
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Notes:
Joints sealants on the sidewalk have failed. Provide new joint sealants and adjust sidewalk to slab interface. Address basement vent fan, access hatch and eave issues Miscallenous
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
Existing Users
Future Users
TotalProject Details:
Proposed
Diameter
(in)
Replace/
New
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 3 - 1E
Project Name: Primary Sludge Pump #1System Type: WastewaterProject Description:
$ 11,000 $ 19,000 $ 25,000 2029
Percent Cost ($)
100% 25,000$
0% $ - 100% 25,000$
Notes on Cost Estimation:Project Element
Notes:
Clean exterior and monitor the corrosion. The advanced age of this pump may result in a failure; monitor frequently for performance. Project complete in 2024. Project Details:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Miscallenous Repairs
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation: Project Detail:
Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 4 - 1A
Project Name: PTF #1 StructureSystem Type: WastewaterProject Description:
$ 40,000 $ 69,000 $ 89,000 2029
Project Detail:
Percent Cost ($)
100% 89,000 $
0% $ - 100% 89,000 $
Notes on Cost Estimation: Future UsersTotal
assumes 50$/SF per Carollo projects. About 1780 SF would be repaired in this scenario from 7918 SF of structure (2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
Notes:
Repair spalls and cracks on exterior. Rebuild exterior and interior parapet wall surface with high-strength mortar and protective coating. Assumes half surface is covered at 50$/SF. Structure is 60ft in diameter with 12ft media height. Full replacement may not be required at current level of severity .
Monitor and reassess biannually.
Concrete Repairs
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Existing Users
Capital
Improvement
Cost(3)
($)
Project
Project Element Schedule
Replace/
New
Project Details:
Proposed
Capacity
(gpm)
Unit Cost(1)
($)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 4 - 1B
Project Name: PTF Pump Station Structure
System Type: WastewaterProject Description:
$ 34,000 $ 58,000 $ 76,000 2029
Project Detail:
Percent Cost ($)
100% 76,000 $
0% $ - 100% 76,000 $
Notes on Cost Estimation:
Existing Users
Future Users
Total
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Examine interior concrete for corrosion and coatings. Repair interior with high-strength mortar and apply protective coatings. Interior is badly corroded. Will require bypass and coordination. Reapirs of inside concrete walls will require reinstallation of all media. Monitor and re-assess. Replacement of media may not be justified considering structure to be demolished in Phase 1Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete repairs
Notes:
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 4 - 1C
Project Name: PTF Pump Station Operators
System Type: WastewaterProject Description:
$ 48,000 $ 82,000 $ 107,000 2027
Project Detail:
Percent Cost ($)
100% 107,000 $
0% $ - 100% 107,000 $
Notes on Cost Estimation:Clean exterior and monitor the corrosion. Moderate corrosion observed on the operators. Replace in the near-term. 3 repairs needed. Cost reflects rehab of some operators and pump replacement.Project Details:
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
Project Element ($/ft)
Project Cost Allocation:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Miscallenous
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project
Schedule
Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 4 - 1D
Project Name: PTF #1 Rotary DistributorSystem Type: WastewaterProject Description:
$ 112,000 $ 192,000 $ 250,000 2025
Percent Cost ($)
100% 250,000$
0% $ - 100% 250,000$
Notes on Cost Estimation:Project Element
Notes:
The City has begun replacing this. Severe corrosion and welding failures. Parts have been ordered and cost reflects actual price. Project complete in 2024/2025Project Details:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Distributor
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
Existing Users
Future Users
Total actual cost provided by City.
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5- 1A
Project Name: STF #1 Structure
System Type: WastewaterProject Description:
$ 30,000 $ 51,000 $ 67,000 2028
Project Detail:
Percent Cost ($)
100% 67,000 $
0% $ - 100% 67,000 $
Notes on Cost Estimation:Repair cracks and spalls along STF Structures #1 and #2 with high-strength mortar. Monitor and track water penetration occurring on the perimeter of each structure. Repair and rebuild interior surfaces of the effluent boxes exiting from each structure with protective coatings and high-strength mortar. Coat bypass manhole structures.Project Details:
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
Project Element ($/ft)
Project Cost Allocation:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Concrete Repairs
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project
Schedule
Reimbursement Category
Existing Users
Future Users
TotalAssumes 50$/SF. The size of the STF is 180 ft diameter with 3.3 ft of height. Assumes about 1800 SF of repairs required.
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5- 1B
Project Name: STF #2 StructureSystem Type: WastewaterProject Description:
$ 30,000 $ 51,000 $ 67,000 2028
Project Detail:
Percent Cost ($)
100% 67,000$
0% $ - 100% 67,000$
Notes on Cost Estimation:
Capital
Improvement
Cost(3)
($)
Project
Schedule
Repair cracks and spalls along STF Structures #1 and #2 with high-strength mortar. Monitor and track water penetration occurring on the perimeter of each structure. Repair and rebuild interior surfaces of the effluent boxes exiting from each structure with protective coatings and high-strength mortar.Project Details:Project Element Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
STF #2 Structure
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5 - 1C
Project Name: STF Pump Station Structure
System Type: WastewaterProject Description:
$ 12,000 $ 21,000 $ 27,000 2027
Project Detail:
Percent Cost ($)
100% 27,000 $
0% $ - 100% 27,000 $
Notes on Cost Estimation:Repairs cracking on top deck.Inspect interior of pump station for coatings. Flow cannot be shut down to the effluent box - shutdown would send untreated water to disposal ponds. Will need to assess work sequence when this work is scheduled.Project Details:
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
Project Element ($/ft)
Project Cost Allocation:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Concrete
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project
Schedule
Reimbursement Category
Existing Users
Future Users
Total
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5 - 1D
Project Name: STF Pump Pipe Supports
System Type: WastewaterProject Description:
$ 9,000 $ 15,000 $ 20,000 2027
Project Detail:
Percent Cost ($)
100% 20,000 $
0% $ - 100% 20,000 $
Notes on Cost Estimation:Corrosion has begun to occur. Clean exterior and coat supports with protective coatings.
Project
Schedule
Project Cost Allocation:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Miscallenous
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Details:
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Total
Unit Cost(1)
Project Element ($/ft)Reimbursement Category
Existing Users
Future Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5 - 1E
Project Name: Secondary Sludge Pumps 1 and 3System Type: WastewaterProject Description:
$ 11,000 $ 19,000 $ 25,000 2030
Project Detail:
Percent Cost ($)
100% 25,000 $
0% $ - 100% 25,000 $
Notes on Cost Estimation:Project Element
Notes:
Clean exterior and monitor the corrosion. 2 pumps. Project completed in 2024/2025. Removed from O&M budget.Project Details:
Capacity (MG)
Replace/
New
Capacity
(MG)
Unit Cost(1)
($/gallon)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Replacement
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
Existing Users
Future Users
Total25k provided by City
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 5 - 1F
Project Name: Secondary Sludge Pumps 2System Type: WastewaterProject Description:
$ 9,000 $ 15,000 $ 20,000
Percent Cost ($)
100% 20,000 $
0% $ - 100% 20,000 $
Notes on Cost Estimation:
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost).
Replace secondary sluge pump #2. Project completed in 2024/2025. Removed from O&M budget.Project Details:
Project Element Capacity (MG)
Replace/
New
Capacity
(MG)
Unit Cost(1)
($/gallon)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Replacement
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Total25k provided by City
(3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
Existing Users
Future Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 6 - 1A
Project Name: Secondary Clarifier #1 StructureSystem Type: WastewaterProject Description:
$ 10,000 $ 17,000 $ 22,000 2027
Project Detail:
Percent Cost ($)
100% 22,000 $
0% $ - 100% 22,000 $
Notes on Cost Estimation:Repair cracks and spalls along Secondary Clarifier Structures #1 and #2 with high-strength mortar. Install kickplates on the access guardrail
Project
Schedule
Project Cost Allocation:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
miscallenous
Notes:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Details:
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Total
Unit
Cost(1)
Project Element ($/ft)Reimbursement Category
Existing Users
Future Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 6 - 1B
Project Name: Secondary Clarifier #2 StructureSystem Type: WastewaterProject Description:
$ 10,000 $ 17,000 $ 22,000 2028
Project Detail:
Percent Cost ($)
100% 22,000 $
0% $ - 100% 22,000 $
Notes on Cost Estimation:
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Repair cracks and spalls along STF Structures #1 and #2 with high-strength mortar. Install kickplates on the access guardrail Project Details:Project Element
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit
Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
concrete repairs
Notes:
Future UsersTotal
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
Existing Users
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 6 - 1C
Project Name: Mechanical Pumps and DrivesSystem Type: WastewaterProject Description:
$ 45,000 $ 77,000 $ 100,000 2028
Project Detail:
Percent Cost ($)
100% 100,000 $
0% $ - 100% 100,000 $
Notes on Cost Estimation: Future UsersTotal
(3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
Existing Users
Notes:
Clean exterior and monitor/replace coatings. Annual maintenance required. Rehab of pumps required in next few years.
Miscallenous
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost).
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Project Element Schedule
Project Details:
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 7-1A
Project Name: Digester #1 and 3 StructuresSystem Type: WastewaterProject Description:
$ 255,000 $ 438,000 $ 569,000 2027
Project Detail:
Percent Cost ($)
100% 569,000 $
0% $ - 100% 569,000 $
Notes on Cost Estimation:
Existing Users
Future Users
TotalDigester #1 is in worse condition and thus it is assumed 20% of the surface will need coating (2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Repair exterior, spalls and cracks with high-strength mortar. Inspect the interior of Digester #1 and #3 during an offline period. Apply protective coatings to the interior. Monitor for leaks when in service.
Includes gas valve, sludge valving, feed piping and gas handling maintenance.
Project requires repair of Digester 3 first to allow for Digester 1 repair, and Digester 3 operation. Then, once Digester 1 is maintained, Digester 3 will ramp down and be demolished in Phase 1. Limit expenditure on Digester #3. Digester 1 to be converted a sludge holding tank as part of Phase 1. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Demolition
Notes:
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 7-1B
Project Name: Sludge Thickener #1 Structure and CatwalkSystem Type: WastewaterProject Description:
$ 35,000 $ 60,000 $ 78,000 2029
Project Detail:
Percent Cost ($)
100% 78,000 $
0% $ - 100% 78,000 $
Notes on Cost Estimation:
Existing Users
Future Users
Totalcost includes coating and some potential valve replacement (2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Clean exterior, replace corroded bolts or anchors, and monitor corrosion. Repair exterior, spalls and cracks with high-strength mortar. Replace 6 valves in sludge thickenerProject Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Notes:
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 7-1C
Project Name: Sludge Thickener #2 Structure and CatwalkSystem Type: WastewaterProject Description:
$ 35,000 $ 60,000 $ 78,000 2029
Project Detail:
Percent Cost ($)
100% 78,000 $
0% $ - 100% 78,000 $
Notes on Cost Estimation:
Existing Users
Future Users
Totalcost includes coating and some potential valve replacement (1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement CategoryClean exterior, replace corroded bolts or anchors, and monitor corrosion. Repair exterior, spalls and cracks with high-strength mortar.Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Notes:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 7-1D
Project Name: Digester Control BuildingSystem Type: WastewaterProject Description:
$ 5,000 $ 9,000 $ 11,000 2028
Project Detail:
Percent Cost ($)
100% 11,000 $
0% $ - 100% 11,000 $
Notes on Cost Estimation:
Existing Users
Future Users
Total
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category Replace anchors, bolts and other components with stainless steel.
Project Details:Project Element
Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Notes:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 8-1A
Project Name: Storage Building StructureSystem Type: WastewaterProject Description:
$ 201,500 $ 346,000 $ 450,000 2026
Project Detail:
Percent Cost ($)
100% 450,000 $
0% $ - 100% 450,000 $
Notes on Cost Estimation:
Existing Users
Future Users
Total
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement CategoryFull roof replacement required. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Notes:
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 8-1B
Project Name: Maintenance Shop StructureSystem Type: WastewaterProject Description:
$ 14,000 $ 24,000 $ 31,000 2029
Project Detail:
Percent Cost ($)
100% 31,000 $
0% $ - 100% 31,000 $
Notes on Cost Estimation:
Existing Users
Future Users
Total
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Southern half of the roof has no roof drain. Add roof drain and replace corroded scuppers. Repair mid-span of the lintel above the roll-up door. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Notes:
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 8-1C
Project Name: Maintenance Shop StructureSystem Type: WastewaterProject Description:
$ 39,000 $ 67,000 $ 87,000 2029
Project Detail:
Percent Cost ($)
100% 87,000 $
0% $ - 100% 87,000 $
Notes on Cost Estimation:
Existing Users
Future Users
Total
system is 30 x 60 ft - 180 ft of perimeter, with pipe supports and 4 columns to have corrosion repair. pipe support replacement estimated at 175$ per ft (direct cost, labor and materials only). 15ft tall column repair estimated at 125$/ft (4 columns) (2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Replace corroded pipe supports of metal structure over the boiler. Provide structural bracing on the exhaust stack. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Notes:
Short-Term Projects to Maintain WWTP | CITY OF SANTA MARIA Project Number: Area 8-1D
Project Name: Facility Drainage Sump PumpsSystem Type: WastewaterProject Description:
$ 4,000 $ 7,000 $ 9,000 2027
Project Detail:
Percent Cost ($)
100% $ 9,000
0% $ - 100% $ 9,000
Notes on Cost Estimation:
Existing Users
Future Users
Total
(2) Estimated Construction Cost includes a 30% contingency, 10% for general conditions, 15% for general contractor, and 8.75% sales tax applied to materials only (assumed 50% of the baseline cost). (3) Total project cost includes a 30% markup of the estimated construction cost that accounts for engineering, management, and legal fees.
Project Cost Allocation:
Reimbursement Category
(1) Los Angeles ENR Construction Cost Index for February 2024 is 15,214 Clean exterior, replace corroded bolts or anchors, and monitor corrosion. Project Details:Project Element Proposed
Diameter
(in)
Replace/
New
Length
(ft)
Unit Cost(1)
($/ft)
Baseline
Construction
Cost
($)
Estimated
Construction
Cost(2)
($)
Capital
Improvement
Cost(3)
($)
Project
Schedule
Concrete
Notes:
VOLUME 11 / CAPITAL IMPROVEMENT PROGRAM AND IMPLEMENTATION OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX B WORKSHOP NO. 7 - PROJECT DELIVERY
6/1/2026
1 WORKSHOP No. 7 / AUGUST 27, 2025
City of Santa Maria
Workshop No. 7
Wastewater Treatment Plant
Goals for Workshop No. 7
1 2
6/1/2026
2 C A R O L L O / 3
updatefooter0323.pptx/3 86STM0623i1.pptx/3
Goals for Workshop No. 7
• Gain a general understanding of project delivery approaches • Identify project-specific criteria to apply to project delivery decision • Achieve general agreement on best delivery method(s) to apply to project(s) • Identify next steps necessary for confirming delivery method(s) decision Volume 11 – CIP and
Implementation Plan
Project Delivery
3 4
6/1/2026
3 C A R O L L O / 5
updatefooter0323.pptx/5 86STM0623i1.pptx/5
Project Delivery Methods
C A R O L L O / 6
updatefooter0323.pptx/6 86STM0623i1.pptx/6
Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.
Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer Contractor
Owner
Designer Contractor
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
5 6
6/1/2026
4 C A R O L L O / 7
updatefooter0323.pptx/7 86STM0623i1.pptx/7
Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.
Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer CM
Owner
Designer Contractor
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
C A R O L L O / 8
updatefooter0323.pptx/8 86STM0623i1.pptx/8
Design-Bid-Build
Contracting Process
8 Procurement
• 100% drawings/specs
• Standard front-ends
• Construction contract
• Lowest responsible bid
• Contract negotiations
Construction
• Construct to drawings/specs
• Project Commissioning
• Project Start-up / Acceptance
7 8
6/1/2026
5 C A R O L L O / 9
updatefooter0323.pptx/9 86STM0623i1.pptx/9
Design-Bid-Build
Pricing Process
Design Engineer
0% 30% 60% 90% 100%
Cost
Estimate
Cost
Update
Cost
Update
Bid
Estimate
Contractor
Bid
Design Definition
BODR
C A R O L L O / 1 0
updatefooter0323.pptx/10 86STM0623i1.pptx/10
Design-Bid-Build
Advantages Disadvantages
Level of Control
• Owner & Contractor familiarity
• High level of Owner control over design elements
• Project scope fully defined at construction
commencement
Cost
• Construction cost determined at bid time (Engineer’s
estimate along the way)
• Selection based on low-bid contractor (qualified?)
• Greater potential for disputes and change orders
• Competitive bidding environment
Schedule
• Sequential schedule
Risk Allocation
• No contractor input during design
• Owner warrants design to Contractor
9 10
6/1/2026
6 C A R O L L O / 1 1
updatefooter0323.pptx/11 86STM0623i1.pptx/11
Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.
Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer Contractor
Owner
Designer Builder
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
C A R O L L O / 1 2
updatefooter0323.pptx/12 86STM0623i1.pptx/12
Construction Manager At-Risk
Contracting Process
12 Construction
Phase
Preconstruction
Phase
Procurement
• Design Engineer Procurement (single stage)
• CMAR Contractor Request for Qualifications (optional) • Statements of Qualification Evaluation/ Shortlisting (optional) • CMAR Contractor Request for Proposals
• Draft CMAR Contract
• Proposal Evaluation
• CMAR Team Interviews
• CMAR Selection
• CMAR Contract Negotiation (Preconstruction Phase Services) 11 12
6/1/2026
7 C A R O L L O / 1 3
updatefooter0323.pptx/13 86STM0623i1.pptx/13
Construction Manager At-Risk
Contracting Process
13 Construction
Phase
Preconstruction
Phase
Procurement
• BODR Development
• 30% Design Development
• 60% Design Development
• Value Engineering (continuous)
• Constructability Review (continuous)
• Cost Model Development (BODR/30%/60%)
• Guaranteed Maximum Pricing
C A R O L L O / 1 4
updatefooter0323.pptx/14 86STM0623i1.pptx/14
Construction Manager At-Risk
Contracting Process
14 Construction
Phase
Preconstruction
Phase
Procurement
• Early Works Construction (TBD)
• Design Finalization
• Project Construction
• Project Commissioning
• Project Start-up / Acceptance
13 14
6/1/2026
8 C A R O L L O / 1 5
updatefooter0323.pptx/15 86STM0623i1.pptx/15
Construction Manager At-Risk
Pricing Process
CMAR Contractor
Design Engineer
0% 30% 60% 90% 100%
Design Definition
Design Development / Review / Value Engineering
75%
Cost Model Development
Guaranteed Maximum Price
BODR
C A R O L L O / 1 6
updatefooter0323.pptx/16 86STM0623i1.pptx/16
Construction Manager At-Risk
Advantages Disadvantages
Level of Control
• Qualifications-based designer and contractor selection • Owner manages multiple contracts** • Owner substantially involved in design phase
• Traditional owner-designer relationship**
Cost
• CMAR contract price established after contract award
eliminating market price competition
• Negotiating GMP sometimes difficult due to “us vs.
them” relationship**
• Cost model developed by CMAR early in project
• Ability to design and deliver project to fixed budget Schedule
• Extended schedule potential depending on degree of
design advancement for GMP
• Dual contract model can be less efficient**
• Shortened schedule potential depending on degree of
design advancement for GMP
Risk Allocation
• Involvement of CMAR during design does not relieve
owner of design risk**
• Performance guarantees generally not available**
• Collaborative relationship
• High degree of Contractor input into design
**Key differentiator from PDB
15 16
6/1/2026
9 C A R O L L O / 1 7
updatefooter0323.pptx/17 86STM0623i1.pptx/17
Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.
Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer CM
Owner
Designer Builder
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
C A R O L L O / 1 8
updatefooter0323.pptx/18 86STM0623i1.pptx/18
Progressive Design-Build
Contracting Process
18 Construction
Phase
Preconstruction
Phase
Procurement
• Request for Qualifications (optional)
• Statements of Qualification Evaluation / Shortlisting (optional) • Request for Proposals
• Draft PDB Contract
• Proposal Evaluation
• PDB Team Interviews
• PDB Selection
• PDB Contract Negotiation (Preconstruction Phase Services) 17 18
6/1/2026
10 C A R O L L O / 1 9
updatefooter0323.pptx/19 86STM0623i1.pptx/19
Progressive Design-Build
Contracting Process
19 Construction
Phase
Preconstruction
Phase
Procurement
• BODR Development
• 30% Design Development
• 60% Design Development
• Value Engineering (continuous)
• Constructability Review (continuous)
• Cost Model Development (BODR/30%/60%)
• Guaranteed Maximum Pricing
C A R O L L O / 2 0
updatefooter0323.pptx/20 86STM0623i1.pptx/20
Progressive Design-Build
Contracting Process
20 Construction
Phase
Preconstruction
Phase
Procurement
• Early Works Construction (TBD)
• Design Finalization
• Project Construction
• Project Commissioning
• Project Start-up / Acceptance
19 20
6/1/2026
11 C A R O L L O / 2 1
updatefooter0323.pptx/21 86STM0623i1.pptx/21
Progressive Design-Build
Pricing Process
PDB Contractor
PDB
Design Engineer
0% 30% 60% 90% 100%
Design Definition
Design Development / Review / Value Engineering
75%
Cost Model Development
Guaranteed Maximum Price
BODR
C A R O L L O / 2 2
updatefooter0323.pptx/22 86STM0623i1.pptx/22
Progressive Design-Build
Advantages Disadvantages
Level of Control
• Inability to separately select designer or contractor (single entity contract)**
• Owner does not hold design contract**
• Qualifications-based designer and contractor selection • Single contract to manage**
• Owner substantially involved in design phase
Cost
• PDB contract price established after contract award
eliminating market price competition
• Establishing GMP sometimes difficult due to internal
misalignment of PDB team**
• Cost model developed by PDB early in project
• Innovation from PDB allows potential cost savings**
• Ability to design and deliver project to fixed budget • Efficient procurement process
Schedule
• Extended schedule potential depending on degree of
design advancement for GMP
• Shortened schedule potential depending on degree of
design advancement for GMP
Risk Allocation
• Existing conditions and permitting uncertainty prior to PDB contract**
• Collaborative relationship
• Transfer of design-related risk to PDB**
• Single point of responsibility**
• Performance guarantees available**
**Key differentiator from CMAR
21 22
6/1/2026
12 C A R O L L O / 2 3
updatefooter0323.pptx/23 86STM0623i1.pptx/23
Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.
Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer CM
Owner
Designer Builder
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
C A R O L L O / 2 4
updatefooter0323.pptx/24 86STM0623i1.pptx/24
Fixed-Price Design-Build
Contracting Process
24 Design /
Construction
Phase
Procurement
• Request for Qualifications
• Statements of Qualification
Evaluation / Shortlisting
• Request for Proposals
• Draft FPDB Contract
• Proposal Evaluation
• FPDB Team Interviews
• FPDB Selection
• FPDB Contract Negotiation
• Design Completion / Finalization
• Early Works Construction (TBD)
• Project Construction
• Project Commissioning
• Project Start-up / Acceptance
23 24
6/1/2026
13 C A R O L L O / 2 5
updatefooter0323.pptx/25 86STM0623i1.pptx/25
Fixed Price Design-Build
Pricing Process
Owner Advisor
0% 30% 60% 90%
Cost
Estimate
Cost
Estimate
Cost
Estimate
DB Team Provides Fixed Price Proposal
Design Definition (Bridging Documents)
BODR
C A R O L L O / 2 6
updatefooter0323.pptx/26 86STM0623i1.pptx/26
Fixed-Price Design-Build
Advantages Disadvantages
Level of Control
• Owner does not hold design contract
• Procurement/selection of DB more complicated than
DBB
• Design control limited to specificity of technical bridging documents
• Qualifications inclusion selection
• Single contract to manage
Cost
• Design-Builder contract price established prior to design completion necessitating pricing of some risks
• Innovation from Design-Builder allows potential cost
savings
• Early cost determination
Schedule
• Shortened schedule potential
Risk Allocation
• Existing conditions and permitting uncertainty prior to DB contract
• Transfer of design-related risk to Design-Builder
• Single point of responsibility
• Performance guarantees available
25 26
6/1/2026
14 C A R O L L O / 2 7
updatefooter0323.pptx/27 86STM0623i1.pptx/27
Summary Comparison
DBB CMAR PDB FPDB
Level of Control
• Reduced level of owner
control over design elements
for non-specified items
• Inability to separately select
designer or construction
contractor (single-entity
contract)
• Slightly reduced level of
owner control over design
elements
• Inability to separately select
designer or construction
contractor (single-entity
contract)
• High level of Owner control
over design elements
• Traditional owner-designer
relationship
• Qualifications-based
designer and contractor
selection (dual contracts)
• High level of owner control
over design elements
• Traditional owner-designer
relationship
• Little or no ability to select
based on contractor
quals/experience
Cost
• Early cost certainty through
fixed-pricing during
procurement
• PDB team generally
determines design
advancement for negotiated
GMP
• Owner directs design
advancement for negotiated
GMP
• Market price competition
Schedule
• Sequential approach • Schedule efficiencies vary • Schedule efficiencies vary • Schedule efficiencies likely Risk Allocation
• FPDB assumes design and
non-inflation price risk
• Potential for performance
guarantees
• PDB assumes design risk
• Potential for performance
guarantees
• Involvement of CMAR during
design does not relieve
owner of design risk
• Owner assumes design risk
C A R O L L O / 2 8
updatefooter0323.pptx/28 86STM0623i1.pptx/28
Delivery Model Schedule Comparison
(Hypothetical Project)
28 27
28 6/1/2026
15 C A R O L L O / 2 9
updatefooter0323.pptx/29 86STM0623i1.pptx/29
• No delivery method procurement process is inherently faster than another • Design-Bid-Build schedule impacted by:
»Extended design period
»Bid protests
• Progressive Design-Build and CMAR schedules impacted by:
»Extended preconstruction phase and GMP negotiations
»Inefficient coordination among designer/contractor/owner • Fixed Price Design-Build schedule impacted by:
»Degree of design prescription in bridging documents
Delivery Model Procurement Schedule
Considerations
Break
29 30
6/1/2026
16 C A R O L L O / 3 1
updatefooter0323.pptx/31 86STM0623i1.pptx/31
Meeting Agenda
Discussion
Lead
Item Description Approx. Time
1.0 Welcome and Introductions 8:30 – 8:32 Graham
2.0 Project Management – Action Items and Schedule 8:32 – 8:43 Graham
3.0 Goals for Workshop No. 7 8:43 – 8:45 Graham
4.0 Volume 11 – Project Delivery 8:45 – 10:15 Kyle
Break 10:15 – 10:30
5.0 Volume 11 – Project Delivery….continued 10:30 – 11:30 Kyle
6.0 Discussion 11:30 – 12:00 All
Wrap up and Next Steps 12:00 – 12:05 Graham
- Lunch
7.0 C A R O L L O / 3 2
updatefooter0323.pptx/32 86STM0623i1.pptx/32
Project Delivery Evaluation
31 32
6/1/2026
17 C A R O L L O / 3 3
updatefooter0323.pptx/33 86STM0623i1.pptx/33
Project Delivery Method Evaluation Criteria
• Legal authority for delivery method
• Project schedule
» Procurement
» Design and construction
• Degree of design control
• Transfer of risk
• Project cost considerations
» Efficiency
» Certainty
» Transparency
• Technical innovation
• Designer / contractor qualifications
• Other…?
C A R O L L O / 3 4
updatefooter0323.pptx/34 86STM0623i1.pptx/34
Project Delivery Method Evaluation Criteria
Weighting
Criterion (High / Med/ Low)
Procurement schedule
Project schedule (design and construction)
Design control
Transfer of risk
Cost efficiency
Cost certainty
Cost transparency
Technical innovation
Designer/contractor qualifications and experience
Other…?
33 34
6/1/2026
18 C A R O L L O / 3 5
updatefooter0323.pptx/35 86STM0623i1.pptx/35
Initial Thoughts? - Project Delivery Approaches
Owner
Design/
Builder
Design-Bid-Build
(DBB)
Construction
Manager-at-Risk
(CMAR)
Fixed-Price
Design-Build
(FPDB)
“Progressive”
Design-Build
(PDB)
Design-Build-Operate/
Finance, etc.
Traditional Delivery Alternative or Collaborative Delivery Owner
Design/
Builder
Owner
Designer CM
Owner
Designer Builder
Owner
Design/
Builder/
Operator
Design/
Builder Operator
Working Relationship
Contractual Relationship
Work & Service Contracts Public-Private
Partnerships
C A R O L L O / 3 6
updatefooter0323.pptx/36 86STM0623i1.pptx/36
Summary Comparison
DBB CMAR PDB FPDB
Level of Control
• Reduced level of owner
control over design elements
for non-specified items
• Inability to separately select
designer or construction
contractor (single-entity
contract)
• Slightly reduced level of
owner control over design
elements
• Inability to separately select
designer or construction
contractor (single-entity
contract)
• High level of Owner control
over design elements
• Traditional owner-designer
relationship
• Qualifications-based
designer and contractor
selection (dual contracts)
• High level of owner control
over design elements
• Traditional owner-designer
relationship
• Little or no ability to select
based on contractor
quals/experience
Cost
• Early cost certainty through
fixed-pricing during
procurement
• PDB team generally
determines design
advancement for negotiated
GMP
• Owner directs design
advancement for negotiated
GMP
• Market price competition
Schedule
• Sequential approach • Schedule efficiencies vary • Schedule efficiencies vary • Schedule efficiencies likely Risk Allocation
• FPDB assumes design and
non-inflation price risk
• Potential for performance
guarantees
• PDB assumes design risk
• Potential for performance
guarantees
• Involvement of CMAR during
design does not relieve
owner of design risk
• Owner assumes design risk
35 36
6/1/2026
19 C A R O L L O / 3 7
updatefooter0323.pptx/37 86STM0623i1.pptx/37
Typical Roles and Responsibilities
DBB CMAR PDB FPDB
City / Owner
• Administers PM/OA services
contract
• Administers design-build contract
• May administer construction
management contract
• Administers PM/OA services
contract
• Administers design-build contract
• May administer construction
management contract
• Administers PM/OA services
contract
• Administers design contract
• Administers CMAR construction
contract
• May administer construction
management contract
• Administers design contract
• Administers construction contract
• Administers construction
management contract
Owner’s Advisor
• Develops preliminary to advanced
design for bridging documents
• Implements design-build
procurement
• Provides project controls support
• May provide construction
management services
• Develops preliminary design
• Implements design-build
procurement
• Provides project controls support
• May provide construction
management services
• Develops preliminary design
• Implements designer and CMAR
contractor procurements
• Provides project controls support
• May provide construction
management services
• May provide program
management support for
procurement and controls
Design Engineer
• Advances design from bridging
level to facilitate fixed pricing
• Completes design after contract
execution
• Completes design to +/- 60% for
CMAR guaranteed maximum
pricing (Phase 1)
• Completes design (Phase 2)
• Completes design to +/- 60% for
CMAR guaranteed maximum
pricing (GMP) (Phase 1)
• Completes design (Phase 2)
• Completes 100% design
• Supports bidding process
• May provide construction
management services
Construction Contractor
• Contractor arm of DB team
constructs project in accordance
with design
• Contractor entity of DB team
develops GMP (Phase 1)
• Contractor entity of DB team
constructs project (Phase 2)
• CMAR contractor develops GMP
(Phase 1)
• CMAR contractor constructs
project (Phase 2)
• Constructs project in accordance
with 100% design
Discussion
37 38
CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 12: Funding Opportunities
FINAL / October 2026
CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 12: Funding Opportunities
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.
Date: 2026.10.24 11:26:39-07'00'
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
p6w://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/Master Plan/Volume 12/Ch01.docx Contents
CHAPTER 1 FUNDING
1.1 Federal and State Funding 1-1
1.2 Funding Considerations 1-1
1.3 Funding Opportunities 1-3
1.4 Recommendations 1-6
1.4.1 Timing 1-6
1.4.2 Application and Costs to Apply 1-7
1.4.3 Reporting Requirements 1-8
1.5 Other Funding Programs Considered 1-8
1.6 Summary and Conclusion 1-9
Appendices
APPENDIX A CALIFORNIA CWSRF PRIORITY SCORING
Tables
Table 1.1 Federal Funding Programs 1-3
Table 1.2 State Funding Programs 1-5
Figures
Figure 1.1 General Loan Program Application Timelines 1-6 Figure 1.2 Loan Application Timeline and Project Schedule 1-7 VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Abbreviations
AIS American Iron and Steel
BABA Build America, Buy America
CDS Congressional Direct Spending
CEDS Comprehensive Economic Development Strategy
CPF Community Project Funding
CWSRF Clean Water State Revolving Fund
DAC Disadvantaged Community
DB Davis Bacon
DBE Disadvantaged Business Enterprise
EAA Economic Adjustment Assistance
EDA Economic Development Administration
EPA Environmental Protection Agency
FY fiscal year
GO General Obligation
M million
MHI median household income
NOFO Notice of Funding Opportunity
NPDES National Pollutant Discharge Elimination System
OSHA Occupational Safety and Health Act
PF principal forgiveness
Q quarter
SRF State Revolving Fund
USACE United State
USBR United States Bureau
USDA United States Department of Agriculture
WIFIA Water Infrastructure Finance and Innovation Act
WRDA Water Resources Development Act
WWTP wastewater treatment plant
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-1
CHAPTER 1 FUNDING
1.1 Federal and State Funding
Federal, state, and local grant and low-interest loan sources are available for the planning, design, and construction of water, wastewater, stormwater, and other public infrastructure projects. These programs have become more competitive due to an overall increased interest in alternate funding options and federal/state budget constraints, coupled with a nationwide, consistent increase in construction costs.
Many programs have challenging qualification processes, specific timeframes in which funds can be used, and eligibility restrictions. For example, funding sources often exclude standard maintenance projects from being eligible in order to focus on improvement projects.
With the new federal administration in 2025, there is uncertainty about the future of federal funding opportunities for water, wastewater, stormwater, and other water-related infrastructure projects. As federal agencies and departments conduct reviews to ensure grant and loan funding align with the current administration's priorities, delays in project award processing are anticipated. At this time, it is assumed that the funding opportunities highlighted in this funding matrix will continue to be available.
1.2 Funding Considerations
Examples of federal and state agencies that provide funding opportunities include the Environmental Protection Agency (EPA), Economic Development Administration (EDA), United States Bureau of Reclamation (USBR), Department of Energy, United States Army Corps of Engineers (USACE), United States Department of Agriculture, Department of Housing and Urban Development, State Revolving Funds (SRFs), and Congress, among others. Locally, the State of California's SRF program provides one of the best avenues for securing a large source of loan funding. Programs under the EPA, EDA, USACE, and others can provide sources of grant funding. Grant funding has the obvious advantage over loans in that it does not require repayment. However, these programs also typically require matching funds and are more competitive to secure.
Because of the constraints of federal and state grant and loan programs, many agencies begin by securing low-interest loan financing for the majority of the project from programs like the Water Infrastructure Finance and Innovation Act (WIFIA) and SRF. This allows the project to proceed with certainty in its financing while pursuing grants that will either provide additional funding or offset loan funding. In addition, loan funding can sometimes be used to satisfy matching fund requirements (with attention to federal funding limits). Smaller grants can also be pursued as they are helpful in building relationships with funding agencies and reducing the overall financial burden. There are numerous factors that should be considered in the pursuit of external low-interest loans and grant funding, including:
Specific Project Priorities: Most low-interest loan and grant programs target a specific type of project or have clear purposes, priorities, and goals for their funds to be awarded. Therefore, a project should be aligned with these to be competitive. Common program goals that many grant programs focus on are that the project should:
» Build regional partnerships.
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-2
» Enhance water conservation or efficiency.
» Protect groundwater resources.
» Provide renewable energy improvements or energy efficiency. » Address risk and resiliency.
» Demonstrate consistency with the state and regional policies and objectives. » Demonstrate regional cooperation and partnerships with partners and stakeholders. » Serve a Disadvantaged Community (DAC).
» Help create both construction and post-construction related employment. Does Not Cover Full Project Cost: Most grant programs do not cover the full cost of the project, requiring the sponsoring agency to provide a cost share ranging from 25 to 75 percent (in-kind donations are applicable matches).
Demonstration of Ability to Pay for Ongoing Project Expenses: Funding agencies typically require the proposed grant applicant to demonstrate the ability to operate and maintain the project without external funding.
Funding Restrictions: Few programs allow for the retroactive funding of design and construction work, and some programs will only fund activities that are conducted post-selection for award or even require entering into an agreement prior to starting work activities. Application Timelines: Application timing is critical for most grant and loan programs. Typically, grant programs release funding announcements once per year with a 45- to 60-day window to apply, and available funding varies from year to year pending Congressional appropriations. Low-interest loan programs typically accept applications on a rolling basis (e.g., WIFIA, SRF); however, they may require submission of pre-application materials by a prescribed date. Award Timing: With the increased interest in external funding and limited funding agency staff availability, the review, selection, and execution of a funding agreement can take an average of 12 months (sometimes longer). In general, agencies should plan on submitting a loan application 6 to 12 months in advance of when funding will be needed and prior to construction start. Project and Documentation Readiness: Applications may require multiple documents (e.g., engineering, environmental, and financial) to show the readiness level of the project. Assessing project document readiness early on is important to ensure the appropriate level of documentation is available to support the funding application.
Grant Reimbursement: Most grants are reimbursements, not upfront cash. This may require that a separate source of funding (i.e., bridge loan) be available as an entity awaits reimbursement of submitted payment receipts if they do not have the cash flow to support the project. Grant reimbursements are subject to annual budget and appropriations processes and thus disbursement of grant funds on schedule is not guaranteed.
Federal Compliance Requirements: Federal funding sources require compliance with federal requirements (also called cross cutters) including, but not limited to, American Iron and Steel (AIS), Davis Bacon (DB) Wage Determinations, anti-lobbying, Disadvantaged Business Enterprise (DBE), Build America, Buy America (BABA), Williams-Steiger Occupational Safety and Health Act (OSHA), and environmental, archeological, procurement, and reporting requirements. These conditions may add to the project's overall cost, influence project schedules, and increase the administrative burden on the borrower.
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-3
1.3 Funding Opportunities
Tables 1.1 and 1.2 below detail several federal and state funding programs that are a possible fit for the City of Santa Maria's (City) Phase 1 Wastewater Treatment Plant Upgrade.
Table 1.1 Federal Funding Programs
Program Agency Type Description Deadlines/Next Steps Constraints Priority WIFIA EPA Loan WIFIA provides low-cost, flexible loans for water infrastructure projects, supports most aspects of project design, planning, construction, land and equipment acquisition, and more. The program provides loan funds for investments in water and wastewater infrastructure of national and regional significance by offering loans to creditworthy borrowers for up to 49 percent of eligible project costs.
Project eligibility is divided into two categories: small and large communities. A population of over 25,000 is considered a large community, and eligible projects are those that cost more than $20 million (M). Projects can be combined and submitted as a group of projects and funded under one loan if they serve a similar purpose and will be repaid from the same revenue stream. The maximum loan term is 35 years (including 5-year repayment deferment).
The interest rate is equal to the United States Treasury rate of a similar maturity, which is about 4.2 percent as of Q2 2025. Application fees apply (average $200,000 - $300,000 pending reviews and legal negotiations). The most recent notice of funding opportunity was published in Sept. 2024; it stated a funding capacity of $6.5 billion.
Applications are accepted on a rolling
basis until funding is depleted, or a
new announcement of funding ability is
announced. Begin by submitting a
letter of inquiry.
WIFIA Website
There are no direct grant
opportunities through WIFIA, but
grants can be used as match
funding as long as no more than
80 percent of the project costs
are covered by federal funds.
High
WIFIA is one of the best options for
low-interest loan funding for a
wastewater project of this size.
Community Project
Funding (CPF) and
Congressional Direct
Spending (CDS)
U.S. Congress Grant CPF and CDS are mechanisms by which members of Congress can request funding for specific projects in their home state that directly serve the public and have been submitted for consideration by state and local government entities and nonprofits to their respective congressmember or senators. Congressional District Representatives may request funding for up to 15 projects in their community under CPF, and Senators have more flexibility in the number of CDS requests, although only a handful may be funded overall. Projects with demonstrated community support are typically considered. Overall, earmarked funds are limited to no more than 1 percent of discretionary spending.
State/local match may be required.
Congressman Carbajal participates in the CPF program and has submitted large requests for regional projects, including the nearby City of Solvang's Wastewater Treatment Plan Upgrade Project in FY25 (among other programs). Senator Alex Padila has a long history of submitting Congressional Direct Spending requests. Senator Adam Schiff made CDS requests during his first term, which began in 2024.
Projects are ultimately selected by the House and Senate. If approved, the budgetary entity funding the program may request submission of an application or submission of other project information, and funds are then distributed as part of the federal appropriations process the next FY (October through September). Funds are to be spent within 1 year. Water and wastewater projects typically have a 20 percent match requirement, and municipal and private non-profit systems are eligible. Compliance with federal requirements applies.
As the FY26 opportunity has closed,
there is currently no application
available. Senators and
representatives typically post
information about the opportunities in
the first quarter of each year, and
deadlines are generally in late April.
If interested in this avenue of funding,
the City should reach out to their
congressional representative or
senators to begin soliciting support for
their project.
Link to Senate Appropriations
Link to House Appropriations
1+ year process to get
recommendation, then
dependent upon congressional
decision, which could be
improved through lobbying
efforts.
Funds must be spent within
1 year of receipt.
Federal requirements apply.
Low
All local representatives participate
in these programs.
Appropriations Requests &
Community Project Funding | U.S.
Representative Salud Carbajal
Appropriations - Senator Schiff
Appropriations - Senator Alex
Padilla
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-4
Program Agency Type Description Deadlines/Next Steps Constraints Priority Public Works and EAA
Programs
EDA Grant The program promotes long-term economic development through assistance in the construction of public works and the development of facilities needed to initiate and support the creation or retention of permanent private sector jobs in areas experiencing long-term economic deterioration and distress. The program provides funding for the construction and/or design of infrastructure to enable them to become more economically competitive. Water and sewer system improvements have historically been funded through this program.
Eligible projects must: be consistent with the region's current Comprehensive Economic Development Strategy (CEDS) or equivalent EDA-accepted regional economic development strategy, be consistent with at least one of EDA's investment priorities, lead to the creation or retention of long-term jobs that provide living wages (preferably, not seasonal), and be located in areas that meet at least one of the following criteria: low per-capita income, unemployment above the national average, or "special need" as determined by EDA.
The City's Wastewater Treatment Plant (WWTP) project would fall into the Public Works grants category, for which the average grant awards have been approximately $1.4M, with an award ceiling of $30M. Although not a defined rule, applicants may receive $15,000 per job created. Federal/non-federal cost share is 50/50 or 80/20 based on unemployment or criteria alignment. Federal requirements apply. Funding is typically awarded 6 months after a complete application is submitted.
The President's proposed FY2026 budget proposed funding cuts to EDA programs, so the future of the program is uncertain.
Applications are accepted on an
ongoing basis, if funding is available.
The FY24 Notice of Funding
Opportunity (NOFO) is the most
current, and applications are still
accepted under this NOFO.
Reach out to EDA regional
representative to discuss project and
confirm applicability.
Contact: Jeff Hays at [email protected],
(206)999-2079
Public Works and EAA Program
Website
Link to 2024 NOFO
Funded projects must be part of
an EDA-certified CEDS or
equivalent EDA-accepted
regional economic development
strategy.
Projects must be able to provide
measurable business/job growth
in the area.
The area must be considered a
low per-capita income, less than
80 percent of the national
average. The unemployment rate
must be 1 percent higher than
the national average. The City
currently meets both criteria.
Low
While the City meets the EDA's
distress criteria, the project must
show that it creates measurable
business/job growth. If the project
or a specific portion of the project
can show that, this could be a good
fit for additional grant funding.
Section 219:
Environmental
Infrastructure Program
U.S. Army Corps of
Engineers
Grant Section 219 authorizes the USACE to provide assistance to non-federal interests (e.g., local communities, water districts, sanitation districts, etc.) for carrying out water and sewer-related environmental infrastructure and resource protection and development projects. This includes projects that address emerging contaminants.
The program requires a minimum cost share of 25 percent non-federal funds. Federal funding ranges based on project type and priority, up to 75 percent federal funding. The application is a two-step process, with Congressional authorization through the Water Resources Development Act (WRDA) processed bi-annually, followed by appropriation of funds through the USACE budgetary process which requires the submission of a letter of interest, financial certification, and workplan.
This program authorized USACE to design and construct the listed project with the funding identified in the WRDA Act. The non-federal entity would not bid or complete the project construction. Rather, USACE would design and/or construct the project identified by the entity, and USACE would be in charge of managing the funding to pay for contractors and/or staff to complete the project.
The Corps must have authorization
from Congress to begin a project or
study. Must contact Regional Army
Corps representative for more
information.
Contact:
[email protected]
.mi
The City would need to work with
a Congressperson to secure
congressional authorization for
USACE to work on the project
through the next WRDA bill.
Low
Securing funding through WRDA is
a lengthy process, and the City
would give control of the portion of
the project funded to the USACE.
Notes:
CDS - Congressional Direct Spending; CEDS - Comprehensive Economic Development Strategy; CPF - Community Project Funding; EAA - Economic Adjustment Assistance; FY - fiscal year; M - million; NOFO - Notice of Funding Opportunity; Q - quarter; WRDA - Water Resources Development Act; WWTP - wastewater treatment plant
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-5
Table 1.2 State Funding Programs
Program Agency Type Description Deadlines/Next steps Constraints Priority Clean Water State Revolving Fund
(CWSRF)
California State
Water Resources
Control Board
Loan CWSRF provides low-interest loans that can also include loan forgiveness for eligible borrowers. Projects funded by the CWSRF include the construction, repair, or replacement of wastewater treatment facilities, stormwater management systems, and wastewater recycling systems. Priority is given to projects that address violations of waste discharge requirements or National Pollutant Discharge Elimination System (NPDES) permits, and projects that connect previously unsewered areas or join communities to regionalize wastewater treatment works. CWSRF also supports projects that reduce energy consumption, increase security at publicly owned treatment works, and otherwise help conservation efforts.
CWSRF loans are capped at $50M per project, but there is no limit to the percentage of project costs they can cover.
The loan rate is one-half of the most recent State General Obligation (GO) Bond Rate at the time of approval. Terms are available for up to 30 years. Principal forgiveness (PF) for a portion of the loan may be available to disadvantaged borrowers or borrowers that incorporate sustainability into projects. PF is also available for public health projects, estuary projects, water recycling, and stormwater projects.
Projects will be scored and prioritized based in part on the project's readiness to begin construction. If plans are greater than 49 percent complete on December 31, then the project will receive 1 "construction readiness point." If greater than 89 percent complete on December 31, then 2 points are given. If plans are less than 50 percent, no points are given.
Applications should be submitted by
December 31st each year to be
reviewed for inclusion on the fundable
list in the following year's Intended Use
Plan.
Review the project's priority score
based on the guidelines in Section IV.C.
of the Policy for Implementing the Clean
Water State Revolving Fund.
Competitive projects are generally
those that score a 13 or above. See
appendix A for an estimated priority
score for this project.
CWSRF Website
All federal requirements (such
as BABA) apply to this funding.
More funding is focused on
areas with low to moderate
income communities and/or
small communities.
Projects that are primarily for
growth are generally ineligible.
High
CWSRF is one of the
few funding programs
focused on wastewater
improvements and can
provide up to $50M in
funding per project.
Notes:
CWSRF - Clean Water State Revolving Fund; GO - General Obligation; National Pollutant Discharge Elimination System; PF - principal forgiveness VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-6
1.4 Recommendations
Based on the size of the project and the available funding sources, seeking low-interest loan funding for this project through the CWSRF and WIFIA program is the strategy with the highest likelihood of success.
The WIFIA program is a flexible source of low-interest loan funding and will provide up to 49 percent of the project's cost as a low-interest loan. The CWSRF program is also a low-interest loan; however, the program is capped at $50M per project. If the City decides to pursue these two programs, the City could receive up to $311M in low-interest loan funding.
1.4.1 Timing
The general application timelines of the primary recommended funding sources for this project, CWSRF and WIFIA, are included in Figure 1.1.
As shown in the figure below, the funding process for CWSRF takes about a year and a half (dates are not specific to this project; they are meant to provide a clearer idea of the timeline with a requirement to submit applications by December each year).
The WIFIA process can take up to two years, depending on how long the negotiation of loan terms takes.
The following are a few examples of factors that will speed up the WIFIA loan closing process:
Projects for WIFIA loans are established at 30-90 percent design (either preliminary or final design stage).
Borrower is highly rated and familiar with using debt. Environmental studies and consultations are complete or currently underway. Borrower has dedicated person(s) to spearhead the WIFIA process and make decisions. Borrower largely agrees to template loan terms.
Figure 1.1 General Loan Program Application Timelines
With those timelines in mind, Figure 1.2 shows the approximate timing of loan applications in comparison to the project schedule.
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-7
Figure 1.2 Loan Application Timeline and Project Schedule The WIFIA program recommends beginning the application process when the project is at 30 percent preliminary design. The flexibility of the WIFIA program makes it an ideal first funding source for a large project. For example, if interest rates fall, WIFIA allows for a one-time realignment of the interest rate on the loan. The program also allows for custom repayment schedules that can work around rate increases and other financial realities.
For CWSRF however, the City should wait to apply until the project final design reaches 90 percent completion to obtain the highest possible score on the priority scoring worksheet. See Appendix A for an estimate of where the project will score. In an ideal scenario, the project would be reaching 90 percent of final design near the end of the calendar year since applications are due by December 31st to be included in the following year's intended use plan. In Figure 1.2, the timeline assumes a December 2028 application date with the final design at 90 percent.
1.4.2 Application and Costs to Apply
Budgeting for both the time and cost of applying to these programs and accounting for closing costs on loan funds is important in this process. Applications for both the CWSRF and WIFIA are extensive and will require significant time to prepare. It is estimated that an experienced funding team would need around 300 to 350 labor hours to complete a full application. It is proposed that the City budget approximately $110,000 for this effort for each loan application.
Closing costs and administrative fees are also important to budget for when applying to these programs.
For the CWSRF program in California, there is an administrative service charge of up to 1 percent of the outstanding loan balance. This fee is pulled from the interest rate payments and does not add an additional fee to the loan.
The WIFIA program requires a down payment of $100,000 at the time of application submission. The application will not be evaluated until the down payment has been paid. The down payment goes toward any external counsel used to assess the project and loan conditions and is credited to the credit processing fee. The credit processing fee reimburses EPA for its costs to provide a loan. The credit processing fee varies for each transaction and is determined by a variety of factors, including the complexity of the transaction, borrower history with the WIFIA program, and the extent of legal negotiations. After the application down payment, the WIFIA program estimates the remaining costs due after loan closing to be between $50,000 to $150,000 per applicant. Therefore, the application down payment and credit processing fee could cost up to $250,000.
The WIFIA program also charges borrowers an annual loan servicing fee that accounts for activities such as credit accounting, collections, maintenance of documents, financial reporting, and construction VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-8
monitoring. In the period prior to substantial completion of the project, the annual loan servicing fee will range from $10,000 to $25,000. After substantial completion, the annual loan servicing fee is typically under $10,000 for all borrowers.
1.4.3 Reporting Requirements
CWSRF Reporting Requirements
If awarded a loan through CWSRF, the recipient must submit progress reports at least quarterly. The reports should detail the status of project activities, starting with the issuance of the executed Financing Agreement and ending on final reimbursement, and must contain at least the following information:
A summary of progress to date, including a description of progress since the last report, percent complete, percent invoiced, and percent schedule elapsed. A listing of Change Orders, including amount, description of work, and change in contract amount and schedule.
Any problems encountered, proposed resolutions, schedule for resolutions, and status of previous problem resolutions.
A summary of compliance with environmental conditions, if applicable.
WIFIA Reporting Requirements
The WIFIA program requires that borrowers submit financial condition reports to:
Provide an oversight tool for ensuring each borrower's compliance with the provisions of the loan agreement.
Monitor the overall status of the project and the WIFIA program. Assist it in identifying any changes to the credit risk posed to the federal government under individual loan agreements.
WIFIA loan agreements will specify scheduled (e.g., monthly, quarterly, annual, or project milestone) reporting requirements, as well as any other periodic reporting requirements. These reporting requirements are included in the loan agreement and are tailored to the characteristics and risks of the project and the borrower. Disbursement requests may be made as frequently as once per month.
1.5 Other Funding Programs Considered
In addition to the list of funding opportunities discussed above, Carollo Engineers' (Carollo) funding team conducted research into many other funding programs and agencies. A few main factors precluded the City's project from being eligible for many of these funding programs.
The City's population is about 109,000 people, which therefore precludes the project from being eligible for any program that focuses on small communities. For example, the United States Department of Agriculture (USDA) Water and Waste Disposal Loan and Grant Program provides funding to rural communities of less than 10,000 people.
A second factor is the median income in the area, which is low enough to qualify for some programs like the Public Works and EAA Programs, but too high to be considered disadvantaged/low income for other VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-9
programs. For example, the City does not qualify for principal forgiveness through the CWSRF because the median income of the City is higher than 80 percent of the state median income (which is around $77,000).
The focus of the project also makes it difficult to qualify for funding. Most funding programs that fund wastewater projects are generally geared towards supporting water recycling efforts. The lack of a water recycling program rules out many programs, including most funding opportunities, though the United States Bureau of Reclamation and other large grant programs, such as the Water Recycling Funding Program through the State of California.
1.6 Summary and Conclusion
Pursuing low interest loans for this project has the highest likelihood of successfully securing the funding needed.
WIFIA:
» The WIFIA program is the funding opportunity with the highest chance of success for obtaining a large low-interest rate loan for this project. The City held a virtual meeting with a WIFIA program representative in September 2025 to discuss the best way to move forward with seeking funding and support from the WIFIA program. WIFIA likes to see funded projects completed within 5 to 7 years.
» The program will fund up to 49 percent of the project costs. Santa Maria could receive up to $261M in low-interest loan funding for this project if approved by the WIFIA program. » The City should begin the application process when the project's preliminary design is at 30 percent.
» Fees for applying for a WIFIA loan could be up to $250,000. » The City should budget to spend about $110,000 for the loan application process. California CWSRF:
» In early 2026, a general application (the first step in the application process) was submitted to the CWSRF program for the Percolation Ponds Project. The estimated score will be 13 if at least 50 percent of the design has been completed by December 2026 (see Appendix A for the estimated score).
» The California CWSRF is focused on funding wastewater and stormwater projects and is the next best option for additional loan funding for this project. » To be competitive, the project should score at least a 13 on the priority scoring system found within the Policy for Implementing the Clean Water State Revolving Fund. » The program caps all loans at $50M, regardless of the project costs. » The City should budget to spend about $110,000 for the loan application process.
If approved for the maximum loan amounts, the City of Santa Maria could obtain up to $311M in low-interest loan funding to complete the necessary upgrades for the Phase 1 Project.
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX A CALIFORNIA CWSRF PRIORITY SCORING
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN A-1
Priority Scoring Estimation
The California Clean Water State Revolving Fund (CWSRF) is a promising funding opportunity for the project. However, the project must score high enough on the CWSRF priority scoring worksheet to present a competitive application for this program. The estimated priority score for the percolation pond project is discussed below. Carollo assisted the City in submitting the general application package in the spring of 2026; the following estimated score information reflects what was submitted.
Table A.1 Project Score
Resource or Impact Purpose
Corrective Preventive Improvement
Drinking Water Source 10 9 6
Nutrient Removal 8 6
Water Recycling - - 8
Water Quality Control Plan or Permit, or Impaired Water Body 8 7 4 The estimated score for Santa Maria's percolation ponds project is an 8 because the project will prevent future violations of the plant’s permit related to the capacity of the ponds.
Table A.2 Secondary Score (Maximum Score of 3)
Secondary Score Score
Applicant volunteers this project to meet SRF's equivalency requirements, meaning all federal crosscutting requirements will apply. (Projects may be selected to meet necessary equivalency requirements associated with the funding source, regardless of whether the applicant volunteers.) 3 Project eliminates a discharge of waste regulated by a Regional Water Board or the State Water Board (e.g., regionalization, consolidation, or septic-to-sewer projects). 2 Project is cited in a multi-agency regional environmental management plan or has multi-media environmental benefits.
2 The applicant agrees to provide funds to match federal capitalization grants by agreeing to the match financing option.
2 The estimated score for Table A.2 is a 3, as the City of Santa Maria (City) will need to meet the State Revolving Fund's (SRF's) equivalency requirements (meaning all federal crosscutting requirements, such as Build America, Buy America (BABA), will apply to the project).
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN A-2
Table A.3 Affordability Score (Maximum Score of 5)
Secondary Characteristics
<80% of State MHI ≥80% and <100% of State MHI ≥100% and ≤150% of State MHI Small (≤20,000) Not subject to scoring 2 2
Medium (>20,000 and
≤100,000)
2 1 0
Large (>100,000) 1 0 0
Sewer Rates as a Percentage of MHI:
<1% of MHI
≥1% and <1.5% of MHI
≥1.5% of MHI
0
1
2
Offers Rate Assistance 1
Notes:
MHI - median household income
According to the U.S. Census Bureau, the state of California's MHI is $100,149. Based on this data, 80 percent of the state MHI is $80,119. The median household income in the City is $74,986 with a 2020 census population of 109,707 people (according to the U.S. Census Bureau). This places the City in the chart above as a large community with an MHI of less than 80 percent of the state MHI and awards a score of one for this item.
Based on the "Notice of Proposed Rate Increases to Water and Sewer Rates for 2024-2027," the current monthly sewer rate for a single-family residential household is $36.40 per month, or $436.80 annually.
This annual rate represents approximately 0.5 percent of the local MHI, which awards the City a score of zero for this item. Lastly, as the City does not offer rate assistance, the score for this item is also zero.
Overall, the City scores an affordability score of one.
Table A.4 Readiness Score (Maximum Score of 2)
Application or Design Status Score
Plans and Specifications:
≥90% as verified by Division staff
≥50% as verified by Division staff
2 1
Consent to use of a funding agreement template as posted on the Division's website
(Requires a satisfactory certification form submitted with application documents) Remaining Capacity Process-eligible
VOLUME 12 / CHAPTER 1: FUNDING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN A-3
The current project schedule shows that design of the percolation pond will be at least 50 percent by December 2026, therefore, the City would receive 1 point for their readiness score. The priority score estimated worksheet that was submitted noted this score as zero. This can be resubmitted later in the process to note this change to the project schedule.
Table A.5 Total Estimated Priority Score
Scoring Element Estimated Score for the Project
Project Score 8
Secondary Score 3
Affordability Score 1
Readiness Score 1
Total Estimated Priority Score 13
While the priority score needed to get on the fundable list varies from year to year, the score needed on the most recent intended use plan for 2026-2027 is 13. This project scores an estimated 13 points and could be a competitive project for CWSRF funding.
CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 13: Support Facilities
FINAL / October 2026
CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Volume 13: Support Facilities
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.
Date: 2026.10.24 11:27:44-07'00'
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/Master Plan/Volume 13/_Cover_TOC_Abbrevs_AppxCovers.docx Contents
CHAPTER 1 PLANT WATER SYSTEMS
1.1 Purpose/Background 1-1
1.2 City Water System 1-1
1.2.1 Fire Suppression 1-4
1.3 Softened Water System 1-6
1.4 Utility Water System 1-8
1.4.1 Utility Water Quality 1-8
1.4.2 Projected Utility Water Demand 1-10
1.4.3 Tertiary Filtration System Capacity 1-11
1.4.4 Layout Considerations 1-12
1.4.5 Comparison of Alternatives 1-22
1.4.6 Other Tertiary Filtration Considerations 1-23
CHAPTER 2 PLANT DRAINAGE AND STORMWATER
2.1 Introduction 2-1
2.2 Plant Drainage System 2-1
2.2.1 Phase 1 Plant Drainage Considerations 2-2
2.3 Stormwater System 2-3
2.3.1 Phase 1 Plant Stormwater Considerations 2-5
CHAPTER 3 INSTRUMENT AIR AND PROPANE
3.1 Introduction 3-1
3.2 Instrument Air 3-1
3.2.1 Phase 1 Considerations 3-1
3.3 Propane System 3-3
3.3.1 Phase 1 Considerations 3-3
CHAPTER 4 UTILITY BUILDING, MAINTENANCE, AND LABORATORY
4.1 Introduction 4-1
4.2 Utility Building 4-2
4.2.1 Phase 1 Utility Building Considerations 4-2
4.3 Maintenance Building 4-4
4.3.1 Phase 1 Maintenance Building Considerations 4-4
4.4 Storage Building 4-4
4.4.1 Phase 1 Storage Building Considerations 4-4
4.5 Laboratory 4-5
4.5.1 Phase 1 Laboratory Considerations 4-5
4.6 City Yard 4-5
4.6.1 Phase 1 City Yard Considerations 4-5
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
CHAPTER 5 SEPTAGE HANDLING
5.1 Septage Overview 5-1
5.2 Septage Sampling Results 5-3
5.2.1 First Sampling Event - September 2024 5-3
5.2.2 Second Sampling Event - Major Haulers - March/April 2025 5-5
5.2.3 Third Sampling Event - June 2025 5-8
5.2.4 Fourth Sampling Event - July to August 2025 5-9
5.2.5 Comparison of Sampling Events 5-10
5.2.6 Impact of Current Septage Loads on Effluent Quality 5-12
5.3 Proposed Modifications to the Septage Receiving Area 5-12
5.3.1 Debris Removal 5-12
5.3.2 Septage Equalization Basin for Influent Metering 5-18
5.3.3 Return Activated Sludge Treatment of Septage 5-18
5.3.4 Conceptual Layouts 5-19
5.3.5 Planning Level Cost Estimates 5-22
5.4 Conclusion 5-27
Appendices
APPENDIX A TERTIARY FILTER PILOT STUDY REPORT
APPENDIX B HEADWORKS SAMPLING RESULTS - SEPTEMBER 2024
APPENDIX C PFAS SAMPLING RESULTS - SEPTEMBER 2024
APPENDIX D SUMMARY OF CONSTITUENTS IN MAJOR HAULER SAMPLING
APPENDIX E RESULTS FROM MAJOR HAULER SAMPLING
APPENDIX F HEADWORKS SAMPLING RESULTS - JUNE 2025
APPENDIX G COMPARISON OF LOADING EVENTS
Tables
Table 1.1 Treated Effluent Re-use Regulations 1-9
Table 1.2 Projected Utility Water Demands for Each Facility After Phase 1 Expansion 1-10 Table 1.3 Layout Alternative 1 Cost Estimate 1-17
Table 1.4 Layout Alternative 2 Cost Estimate 1-19
Table 1.5 Layout Alternative 3 Cost Estimate 1-20
Table 4.1 New Utility Building Features 4-3
Table 5.1 Summary of Septage as Percentage of Influent Flow for Various WWTPs 5-1 Table 5.2 Summary of September 2024 Sampling Event - Flows 5-3 Table 5.3 Summary of Results From First Sampling Event - September 2024 - BOD5, TKN, and NH3(1) 5-4
Table 5.4 Contribution of Septage to Influent BOD, NH3, and TKN Load - September 2024 (Adjusted for 24-Hour Period) 5-4
Table 5.5 List of the Eight Septage Haulers and Their Annual Flow Contribution 5-5 VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iii
Table 5.6 Average Concentrations for Constituents Sampled for Each Major Hauler 5-7 Table 5.7 June 2025 Sampling Event Results 5-8
Table 5.8 July/August 2025 Sampling Event Results 5-10
Table 5.9 Summary of Septage Loading Contributions and Planning Range 5-11 Table 5.10 Preliminary Sizing for Huber RotaShield Units 5-17 Table 5.11 Preliminary Design Criteria - Booster Pump Station 5-22 Table 5.12 Septage Station Improvements Cost Estimate - Level 1 - Improved Screening Only 5-23
Table 5.13 Equalization Basin and Metering Cost Estimate - Level 2 - Small Equalization and Return to Headworks 5-23
Table 5.14 Septage Treatment Cost Estimate - Level 3 - Full Treatment 5-24 Table 5.15 Preliminary O&M Costs for Septage Treatment - Based on Level 3 5-25 Table 5.16 Preliminary Unit Cost for Septage Treatment - Based on Full Treatment - Level 3 5-25
Figures
Figure 1.1 Existing Utility Water Tank Configuration 1-2 Figure 1.2 City Water Tie-In Connection Points As-Builts - Sourced Courtesy of City of Santa Maria 1-3
Figure 1.3 Existing Plant Water Distribution Schematic 1-5 Figure 1.4 Approximate Location of Existing Fire Hydrants 1-6 Figure 1.5 Existing Softened Water Distribution Schematic - Phased Out 1-7 Figure 1.6 Layout Alternative 1 - Chlorine Contact Tank With Tertiary Filters in the South 1-14 Figure 1.7 Example of Tertiary Filter Installation 1-15 Figure 1.8 Layout Alternative 2 - Intermediate Clarifier With Tertiary Filters Located Centrally 1-18
Figure 1.9 Layout Alternative 3 - Tertiary Filters South of Facility with Intermediate Clarifier Storage 1-21
Figure 2.1 High-Level Drainage Pattern for Plant Drain System 2-1 Figure 2.2 Plant Drainage Pump Station 2-2
Figure 2.3 High-Level Surface Water Stormwater Drainage Pattern 2-3 Figure 2.4 High-Level Stormwater Pumping Schematic 2-4
Figure 2.5 East Supernatant Pit Pump Station 2-5
Figure 3.1 High-Pressure Air (Instrument Air) Schematic 3-2 Figure 3.2 Propane Storage Cylinder 3-3
Figure 4.1 Plant Operations and Maintenance Support Buildings 4-1 Figure 4.2 Utility (Left Portion - 1961) and Maintenance (Right Portion - 1979) Buildings 4-2 Figure 4.3 Preliminary Location of New Utility Building and Other Facilities 4-4 Figure 5.1 Existing Septage Receiving Area at Entrance to WWTP 5-2 Figure 5.2 Existing Septage Receiving Area at Entrance to WWTP 5-2 Figure 5.3 Septage Contributions From Major Haulers - November 2023 to November 2024 5-6
Figure 5.4 Septage Loading From Major Haulers 5-7
Figure 5.5 Influent Area Piping Elevations 5-9
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iv
Figure 5.6 Septage Loading Comparison Between Sampling Events 3 and 4 - TSS and TDS 5-10
Figure 5.7 Septage Loading Comparison Between Sampling Events 3 and 4 - NH3 and Total Nitrogen 5-11
Figure 5.8 Examples of Septage Station Improvement Features Utilizing Manually Cleaned Screens 5-13
Figure 5.9 Huber RotaShield Septage Acceptance Units 5-15 Figure 5.10 Huber RotaShield Field Trial - November 2025 5-16 Figure 5.11 Existing Pipe Orientation at the Septage Receiving Station With the Canopy 5-18 Figure 5.12 Proposed Septage Improvements for Equalization and Return to Headworks 5-20 Figure 5.13 Proposed Septage Improvements for Full Treatment Showing Three Alternative Locations 5-21
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN v
Abbreviations
µg/L micrograms per liter
BOD biochemical oxygen demand
BOD5 5-day biochemical oxygen demand test
City City of Santa Maria
COD chemical oxygen demand
DI ductile iron
F Fahrenheit
gpcd gallons per capita day
gpd gallons per day
gpd/ac gallons per day per acre
gpm gallons per minute
hp horsepower
kWh kilowatt-hour
lb/day pounds per day
M million
MCL maximum contaminant level
MG million gallons
mg/L milligrams per liter
mgd million gallons per day
mg-min/L milligrams per minute per liter
mL milliliter
MPN most probable number
msl mean sea level
N/A not applicable
ND not detected
NH3 ammonia
NH3-N ammonia-nitrogen
NL notification level
NTU nephelometric turbidity unit
O&M operations and maintenance
OSHA Occupational Safety and Health Administration
PFAS per- and polyfluoroalkyl substances
PFBS perfluorobutanesulfonic acid
PFHxA perfluorohexanoic acid
PFHxS perfluorohexanesulfonic acid
PFOA perfluorooctanoic acid
PFOS perfluorooctanesulfonic acid
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN vi
PS primary sludge
psi pounds per square inch
PTF primary trickling filter
PVC polyvinyl chloride
RAS return activated sludge
RL response level
ROC reactive organic compound
RUL remaining useful life
RV recreational vehicle
RWQCP regional water quality control plant
RWRF regional water reclamation facility
SCADA supervisory control and data acquisition
scf standard cubic feet
scfm standard cubic feet per minute
STF Secondary Trickling Filter
TDS total dissolved solids
TKN total Kjeldahl nitrogen
TSS total suspended solids
UV ultraviolet
UW utility water
V volt
VFD variable frequency drive
VOC volatile organic compound
VSS volatile suspended solids
WAP Wash and Press
WAS waste activated sludge
WRF water reclamation facility
WTP water treatment plant
WWTP wastewater treatment plant
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-1
CHAPTER 1 PLANT WATER SYSTEMS
1.1 Purpose/Background
This chapter discusses the existing and proposed water systems at the City of Santa Maria's (City) Wastewater Treatment Plant (WWTP), including City-supplied water and a proposed utility water system.
The plant currently uses City-supplied water for washing down equipment, and other utility uses to support liquid and solid treatment processes. Historically, these functions were fulfilled by an on-site well prior to the City supply becoming available. The on-site well is still operable as a standby source. There was also a separate softened-water system, but it was decommissioned as of 2024.
The planned expansions and modifications to the existing WWTP as part of the Phase 1 improvements project, presented in the other Volumes of this Master Plan, will significantly alter the treatment process and require a much larger volume of utility water to support operation. Purchasing City water to meet these higher demands will substantially increase the cost and also add to the total volume of water requiring disposal in the percolation ponds. For these reasons, a new utility water system that uses treated effluent for plant water is being evaluated. The analysis of this system is presented in this chapter.
Other WWTP support systems are discussed in Volume 13, Chapters 2, 3, and 4. The septage receiving system is discussed in Chapter 5.
1.2 City Water System
As mentioned, the WWTP was previously served by water from a local well. The City water distribution system now connects to the well header, which incorporates a small hydropneumatic tank to provide a buffer volume and a pressure regulator that controls pressure at 72 pounds per square inch (psi).
A pressure blowoff, set at 75 psi, is provided as a safety measure. An air release valve is also included.
Figure 1.1 shows a schematic of the previous well system, which now serves as the backup to City water.
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-2
Figure 1.1 Existing Utility Water Tank Configuration
The City water connection point into the system was made in 2024. The new connection is made at the indicated pad in Figure 1.2. A 6-inch pipeline comes in from the 12-inch distribution pipe located on Black Road to connect to the valving and pump system on the pad. From that system, a 4-inch water distribution line sends flow to the site. An 8-inch fire line from the 12-inch distribution line on Black Road connects to the hydrant to provide fire suppression. The pipeline then connects with a series of valves and regulators that furnish the required pressure for the plant system.
Figure 1.2 illustrates the locations of the new connection point and highlights where the 6-inch City water line ties in with the plant distribution system. Figure 1.2 also indicates the water connection point to the fire hydrant located adjacent to the plant water distribution system.
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-3
Figure 1.2 City Water Tie-In Connection Points As-Builts - Sourced Courtesy of City of Santa Maria VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-4
Because the City water is currently the only high-pressure water source at the treatment plant, it must be used for the pump seal water systems (although the plant has moved away from using flushed seals for pumps in recent years), supply for the boiler makeup water, and for all hose bibbs.
There are two City water connections to the plant: one 4-inch line that provides water to the Operations Building and a separate 4-inch line that provides water to the various plant areas for uses such as washdown, boiler water makeup, etc. A schematic showing the distribution lines servicing the plant facilities, taken from the Operation and Maintenance Manual, is shown in Figure 1.3. Note that Figure 1.3 does not reflect the updated connection points highlighted in Figure 1.2 but indicates the existing distribution lines from that point to the remainder of the plant.
As shown in Figure 1.3, the distribution system for water is extensive. This will need to be modified when the plant moves to a separate utility water system, discussed later.
1.2.1 Fire Suppression
Currently, the WWTP has four fire hydrants that are connected to the City water distribution system. The approximate locations are shown by the yellow placemarks in Figure 1.4. The fire hydrants are currently rated to deliver 85 psi of static pressure. In addition, there are approximately 13 hand-held fire extinguishers located around the plant. As part of the Phase 1 project, the fire suppression system will remain on City water.
Additional fire hydrants, probably two, may need to be added in the area of the plant that will house the new activated sludge system and blower building, and serve the solids thickening and dewatering areas.
The location of these hydrants will be confirmed during preliminary design.
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-5
Figure 1.3 Existing Plant Water Distribution Schematic
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-6
Figure 1.4 Approximate Location of Existing Fire Hydrants
1.3 Softened Water System
In the past, potable water supplied to the Laboratory and Operations Building was treated for hardness by passing it through a water softener. The soft water system was eliminated when City water was connected to the plant in 2024, and the old soft water supply header line was used to supply "potable" water to the offices. The soft water distribution system within the WWTP yard is still underground (see Figure 1.5) but not in use and has been disconnected near the office buildings to avoid any cross-connections with water used in the WWTP processes.
This system is used to distribute softened water from the water softeners located in the Storage Building to the Laboratory, the Utility Building, the Primary Sludge Pump Station, the Secondary Sludge Pump Station, and the Digester No. 1 Control Building.
For the Phase 1 project, it is not anticipated that softened water will be needed. This will be confirmed during the Preliminary Design phase, at which time a decision can be made on whether to keep or remove the existing distribution system piping.
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-7
Figure 1.5 Existing Softened Water Distribution Schematic - Phased Out VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-8
1.4 Utility Water System
This section presents an evaluation of a new utility water system to support the anticipated plant water demands associated with the operation of the future Phase 1 liquids and solids treatment processes. It summarizes existing treated effluent regulations and provides regulatory justification for the choice of utility water quality. The evaluation also considers alternative locations for the chosen treatment system, preliminary layouts for the major utility water pipework, and the estimated cost.
1.4.1 Utility Water Quality
Utility water systems at municipal WWTPs in California typically utilize treated wastewater effluent as the plant process water. Some systems combine the fire water system as part of the utility water system or have a separate potable water system that provides potable water uses and fire suppression. As discussed, it has been assumed that, for the Phase 1 expansion, the existing and any new fire hydrants would remain on potable City water.
Because of the volume of water required for the Phase 1 Utility Water System, using City water would be both cost-prohibitive and add significant water to the system, increasing loading for the percolation ponds. Accordingly, the City is evaluating the use of treated effluent for the washdown and maintenance operations required under the Phase 1 improvements.
1.4.1.1 Worker Health and Title 22 Requirements
Recycled water is typically subject to strict treatment requirements, as specified in Title 22 of the California Code of Regulations. Title 22 provides guidelines for the quality of recycled water that is to be used for processes, which are presented in Table 1.1. Three qualities of treated wastewater effluent are permitted for reuse under Title 22, namely: Disinfected Secondary - 23, Disinfected Secondary - 2.2, and Disinfected Tertiary. These are listed in order of increasing quality, with Disinfected Tertiary being the highest quality.
The first two only differ in the level of disinfection that is required.
However, pursuant to an exception noted in Section 60303 of Title 22 of the California Code of Regulations, the regulations do not apply to recycled water used on-site at a water recycling plant or wastewater treatment plant if public access is restricted. The City restricts public access to the wastewater facility and, therefore, will not be required to hold a Title 22 permit for the re-use of treated effluent within the plant.
The treatment regulations under Title 22 are noted in Table 1.1. However, these are informative only, as the City will not be subject to the allowable uses and monitoring requirements indicated therein.
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-9
Table 1.1 Treated Effluent Re-use Regulations
Title 22 Regulatory Standard Treatment Requirements Allowable Uses Disinfected Secondary - 23 Disinfection that reaches:
7-day median total coliform < 23 MPN/100 mL.
One sample per 30 days > 240 MPN/100 mL.
Industrial cooling without mist
generation.
Boiler feedwater.
Industrial process water that
does not contact humans.
Disinfected Secondary - 2.2 Disinfection that reaches:
7-day median total coliform < 2.2 MPN/100 mL.
One sample per 30 days > 23 MPN/100 mL.
Industrial cooling without mist
generation.
Boiler feedwater.
Industrial process water that
does not contact humans.
Disinfected Tertiary(1) Disinfection that reaches:
7-day median total coliform < 2.2 MPN/100 mL.
One sample per 30 days > 23 MPN/100 mL.
> 450 mg-min/L Contact Time with > 90-minute
overall contact time.
Media filtration that reaches:
24-hour average Turbidity < 2 NTU.
Max Turbidity no more than 5% of time: < 5 NTU.
Landscape irrigation in public
access areas.
Food crop irrigation.
Recreational impoundments.
Dual-plumbed systems (e.g.,
building reuse).
Industrial processes where
worker contact may occur.
Notes:
mg-min/L - milligrams per minute per liter; mL - milliliter; MPN - most probable number; NTU - nephelometric turbidity unit (1) A Title 22 permit will not be required unless the tertiary effluent is used for off-site recycled water purposes, which is not the intention.
Although the City is not required to comply with the regulations, worker health should be considered. The future utility water system will include hose bibbs for general washdown, spray systems in the aeration basins, and the solids thickening and dewatering areas, which can create mist, among other uses.
Accordingly, there is a high likelihood that there will be human contact with the water. Only Disinfected Tertiary effluent meets the quality requirements for these uses. Accordingly, Disinfected Tertiary effluent is recommended as the water supply for the proposed future utility water system to protect worker health.
The related requirements and monitoring noted in Table 1.1 will not apply, allowing the City to preserve worker health without the stringent monitoring that would be required under typical Title 22 permits.
1.4.1.2 Suspended Solids Considerations
An additional key consideration in evaluating the water quality for the utility water system is ensuring a system that reliably conveys flow without causing obstructions or blockages. Disinfected Secondary - 23 and 2.2 will contain more suspended solids than Disinfected Tertiary, and may lead to regrowth within the distribution network and sloughing of solids, which could block small orifices, including valves, seals, and sprays.
Operators at a plant with both tertiary- and secondary-treated utility water systems report that disinfected secondary effluent has led to higher biomass growth and operational issues in the plant's water system.
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-10
1.4.1.3 Disinfection Efficacy Considerations
A third consideration related to the plant water quality is the ability of a new disinfection system to achieve worker safety protection and regulatory standards. The three primary disinfection systems utilized in municipal WWTPs are chlorination, ultraviolet (UV) irradiation, and ozonation. Design manuals and observational evidence indicate that the disinfection efficiency for each disinfection approach improves with increasing water quality, which is lower turbidity and lower organic content. Accordingly, tertiary filtered water will be easier to disinfect compared to the other qualities.
1.4.1.4 Water Quality Recommendation
Considering the three key factors governing the utility water system, it is recommended that a tertiary filtration and disinfection system be provided for the plant water supply. Disinfected tertiary effluent will allow the WWTP to preserve worker health, reduce the likelihood of biomass growth in the plant water distribution system, and allow the disinfectant residual to last longer. This filtration standard and recycled water use will not require a Title 22 permit.
1.4.2 Projected Utility Water Demand
Preliminary estimates of the projected utility water demand for the new Phase 1 Improvements are shown in Table 1.2. These values will need to be updated/revised during the preliminary design phase. The average utility and peak utility water demands are depicted in gallons per minute (gpm). Note that safety shower and emergency eye-wash facilities will all be provided with potable water.
Table 1.2 Projected Utility Water Demands for Each Facility After Phase 1 Expansion Facility Reclaimed Water Utilities Included
Average Daily
Demand (gpm)
Peak Hourly
Demand (gpm)
Septage Station 9 50 1 Hose Bibb in service 10 hours/day Screening/ Headworks 5 20 Hose Bibb
Grit Chambers 5 60 Hose Bibb and Grit Flushing
Primary Clarifiers 10 40 Hose Bibb and Scum Spray
Primary Effluent Pump Station 5 20 Hose Bibb
Bardenpho - Aeration Basins 225 1,500 Spray Water and Hose Bibbs Secondary Clarifiers 20 40 Hose Bibb and Scum Spray
Tertiary Filter Feed Pumps 5 20 Hose Bibb
Tertiary Filter Backwashing System 5 20 Polymer, Hose Bibb Effluent Pump Station 5 40 Hose Bibb
PS Thickening 25 120 Polymer, Hose Bibb, Spray Water
WAS Thickening 60 120 Polymer, Hose Bibb, Spray Water
Anaerobic Digesters 15 40 Hose Bibb
Sludge Storage 5 40 Hose Bibb
Dewatering (screw press) 80 1,150 Polymer, Hose Bibb, Spray Water Cake Storage Area 5 20 Hose Bibb
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-11
Facility Reclaimed Water Utilities Included
Average Daily
Demand (gpm)
Peak Hourly
Demand (gpm)
Blower Building 5 40 Hose Bibb
Boilers 5 30 Make Up Water and Hose Bibb
Irrigation 25 100 General Irrigation
Ponds 5 20 Hose Bibb
Electrical Building 2 20 Hose Bibb
Admin Building 0 0 Potable Water Only
Maintenance Building 0 0 Potable Water Only
Sum 526 3,500
Safety Factor 1.2 -
Design Flow (gpm) 632 3,500
Design Flow (mgd) 0.91 5.0
Notes:
mgd - million gallons per day; PS - primary sludge; WAS - waste activated sludge Table 1.2 indicates that the most significant contributors to the utility water system will be the aeration basins and the solids thickening and dewatering processes. The large peaks reflect the washdown periods and scum spraying that are typically required for these processes based on existing flows. As indicated, the anticipated daily average flow is expected to be close to 1.0 mgd, including a 20 percent safety factor.
This would equate to about 10 percent of the Phase 1 treatment plant design flow, which is a reasonable estimate for planning purposes. The actual utility water uses should be confirmed during the preliminary design phase of the project once equipment selections have been made.
1.4.3 Tertiary Filtration System Capacity
In order to size the tertiary filtration system, the average daily demand flow shown in Table 1.2, together with the 20 percent safety factor, was used as the basis, which is approximately 1 mgd.
The peak-hour flow could be as high as 3,500 gpm (5.0 mgd) and would be provided from a suitable storage tank. Historical influent flow data indicates that effluent flow, even during low diurnal periods, does not decrease below about 2 mgd. Therefore, it is anticipated that there will be sufficient effluent flow to allow the average daily utility water demand to be met at all times.
1.4.3.1 Peak Storage
Utility water systems require peak storage to meet demand instantaneously. The peak storage will be sized to accommodate one hour of demand flow as indicated in Table 1.2, that is, 3,500 gpm, 5.0 mgd, or 210,000 gallons.
There are two potential options for peak storage. The first is the construction of a new aboveground or belowground tank. This will address any fluctuations in flow and serve demand when it is required. It will also provide contact time for disinfection with chlorine.
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-12
The second is the utilization of the existing intermediate clarifier. According to Volume 4 of this Master Plan, the condition assessment of the intermediate clarifier assessed a remaining useful life of up to 20 years. The assessment noted that some spalling and wear in the concrete had been observed.
However, this can be repaired, and the reclaimed tertiary effluent is less corrosive than the wastewater the clarifier currently receives, allowing for potential reuse of this structure. This would reduce the cost of providing storage volume.
According to the 2008 Expansion Record Drawings, the intermediate clarifier is sized for 1.92 hours of detention time at a flow of 3.6 mgd. This corresponds to a volume of 288,000 gallons, which is sufficient to provide up to 4,800 gpm of flow for one hour of peak utility demand, more than is needed. The tank would need to be recoated, and a new covering would likely need to be installed to maintain chlorine residuals and reduce algal growth.
1.4.4 Layout Considerations
Three layout alternatives were evaluated for a tertiary filtration and peak storage facility that will initially serve the plant's disinfected utility water demands while preserving the ability to expand to full tertiary treatment of the plant effluent in the future, should the City elect to do so. Each alternative below illustrates the site area required to accommodate a total of four filters. However, the planning-level cost estimates within this chapter assume that only two filters will be installed initially (one duty and one standby) during Phase 1 to meet the immediate utility water demand. The allocated space can accommodate individual filters up to 2.5 mgd average flow in size, but equipment costs assume use of two 1 mgd filters to match the utility water needs. This phased approach minimizes initial capital costs while providing infrastructure capable of expanding to approximately 10 mgd of filtration capacity within the initial structure before additional structural expansion is required. For each alternative, the layout, tertiary filtration and peak storage facilities, major piping requirements, and planning-level cost estimate are presented. Final layout and costs for the tertiary filtration and utility water system are presented in Volume 6, Chapter 5 with the final project selection.
Alternative 1 locates the filters south of the Percolation Pond pump station and incorporates the construction of a new peak storage demand tank and chlorine contact facility to attenuate peak demand.
Alternative 2 places the filters closer to the intermediate clarifier, to the north of the Percolation Pond pump station. Alternative 3 locates the filters in the same place as Alternative 1, but also uses the intermediate clarifier for storage.
It has been assumed that the disinfection approach will be to use sodium hypochlorite solution, which will be dosed in two locations: directly downstream of the filter(s) to provide a residual entering the storage tank, and then downstream of the utility water pumps using an inline injector and static mixer to provide a residual in the plant distribution system.
Each alternative considers the size of the required piping and pumping for the facilities. Each layout alternative is considered in more detail below.
1.4.4.1 Alternative 1 - Tertiary Filters and Construction of Contact Tank This alternative includes the construction of a chlorine contact tank that will serve as a peak storage buffer to supply the utility water system during peak demand. Secondary effluent from the Percolation Ponds Pump Station influent box will be pumped to the tertiary filters, located south of the Percolation Ponds VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-13
Pump Station. This location keeps the filter system away from other areas of the plant where Phase 1 construction activities are anticipated. Filtered effluent will gravitate to a below-grade storage tank. From the tank, the average demand for the utility water system will be provided by a new utility water pump station that would discharge into the utility water distribution system.
Any excess filtered water will overflow from the storage tank to the Percolation Pond Pump Station for discharge to the percolation ponds. Tertiary filter backwash will be pumped to either the headworks or directly to the primary clarifier influent splitter box. The layout for this alternative is shown in Figure 1.6, which shows the preliminary layout of the Phase 1 facilities and location of the tertiary filters, and includes a preliminary layout of the utility water distribution system, shown in red. As indicated, there would be two loops within the plant: one incorporating the septage receiving area in the north, and a second incorporating the activated sludge process and the solids treatment area to the west.
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-14
Figure 1.6 Layout Alternative 1 - Chlorine Contact Tank With Tertiary Filters in the South VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-15
Tertiary Filter Footprint
It is anticipated that the tertiary filtration facility will include a chemical containment facility for chlorine solution storage and addition located adjacent to the tertiary filters. Chlorine will be dosed immediately downstream of the filter and also in the discharge of the utility water pumps. It is anticipated that the system will be constructed with a metal canopy, similar to that shown in Figure 1.7, which the City may wish to enclose.
Figure 1.7 Example of Tertiary Filter Installation
The tertiary filter system is expected to have a footprint of 72 feet by 25 feet, corresponding to a space footprint of 1,800 square feet, and will include duty and standby filters, each sized for a production rate of
1.0 mgd.
The peak volume storage tank will be sized with the following parameters:
0.3 million gallons (MG; one hour of peak flow).
70 feet long by 38 feet wide by 17 feet high.
» 2,660 square feet of space required.
The anticipated sodium hypochlorite dosing rate will be between 2 and 5 milligrams per liter (mg/L).
Piping and Pumping
The primary utility water pipeline will be a 14-inch C900 polyvinyl chloride (PVC) line that is sized for the peak flow of 5.0 mgd at a maximum velocity of not more than 6 feet per second. A 14-inch pipe will be able to accommodate the peak flows while also reaching minimum velocities for average flows. A 12-inch C900 pipe with a parallel bypass from the chlorine tank may be necessary to handle peak flows from the VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-16
utility water pumps. In this Alternative 1 layout, the pipe will be connected to a wet well at the edge of the storage tank. The pumps required to service this flow will be sized with the following parameters:
15 percent minor losses.
Approximately 4,400 feet of pipeline (14-inch C900 pipe). 10 feet of static head.
5.5 mgd of peak flow.
Delivering 72 psi to match the existing potable water system. The pumps will be sized to accommodate both average flow and peak flows while maintaining high pump efficiency.
» Two 700-gpm pumps in a duty-standby configuration will be installed to accommodate the average flows during regular operation, with a control panel to allow switching of the duty pump to reduce wear on individual pumps.
» When demand cannot be met from the smaller pumps, larger 1,400-gpm pumps in a 2-duty-1-standby configuration will progressively be brought into service to meet the peak flow.
The pumps will be able to handle 166 feet of head.
» Pumps will be fitted with variable frequency drives (VFDs) to adjust flow to meet demand. At average flow, the VFD can ramp down to around 30 to 50 percent of standard flow to accommodate average demands.
The power demand for the pumps is anticipated to be 42 horsepower (hp) and 84 hp for the 700 and 1,400 gpm pumps, respectively. The pumps could be vertical turbine or submersible types and will be connected to the storage tank outlet and the utility water system. Details would be established during preliminary design.
Flow from the tertiary filters will gravitate to the peak storage basin. When the storage tank is full, there will be an overflow weir that will convey excess filtered effluent by gravity to the Percolation Pond Pump Station.
The elevations and heads for this alternative are:
Grade elevation at tertiary filters: 158 feet (18-inch slab on grade). Outlet elevation tertiary filters: 163.8 feet.
Inlet elevation for contact tank: 162.0 feet.
Utility Water Pump Station Inlet: ranges from 144.8 to 160.2 feet.
There is sufficient head to gravitate from the tertiary filters to the storage tank and from the storage tank to the Percolation Pond pump station.
Cost Estimate (Alternative 1)
The anticipated cost for this alternative (Class 5 estimate) is shown in Table 1.3 and includes the costs of the tertiary filters, the shade structure, disinfection, piping, the peak flow storage tank, and the utility water pumps. The total project cost is estimated at $10.9 million.
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-17
Table 1.3 Layout Alternative 1 Cost Estimate
Item Description Amount
1 Tertiary Cloth Filters and Storage Basin
Site Construction. $565,000
Structural Work. $911,400
Cloth Filters, Pumps, Backwash Chemicals, Equipment, etc. (1+1 Duty/Standby, 1.0 mgd each).
$1,150,000
2 Utility Water System Piping $1,410,000
3 Electrical (15%) $610,000
4 Instrumentation and Controls (10%) $350,000
Subtotal - Direct Costs $4,990,000
5 Contingency (30%) $1,496,000
6 Contractor Mark-ups (General Conditions, Overhead and Profit) (30%) $2,182,000 7 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $284,000 Estimated Construction Cost $8,950,000
8 Engineering and Construction Management (17%) $1,520,000 9 Legal Admin and Regulatory Costs (5%) $450,000
Total Project Cost $10,915,000
1.4.4.2 Alternative 2 - Tertiary Filters and Re-use of Intermediate Clarifier Alternative 2 will utilize the existing intermediate clarifier as the storage tank to supply peak demand. As noted above, the structure for the intermediate clarifier could be rehabilitated and reused for the storage of disinfected filtered effluent. In this case, the tertiary filters will be located north of the Percolation Pond pump station. This location was selected to allow tertiary filters' effluent to easily flow by gravity to the intermediate clarifier.
This location is more central within the existing plant and is more likely to impact construction sequencing and construction of new anaerobic digesters for the Phase 1 project, but would reduce the overall cost of the proposed system by reusing the existing structure.
Tertiary Filter Footprint
The footprint requirements and arrangement of equipment would be similar to Alternative 1.
Secondary effluent would be sent to the filters from the Percolation Pond Pump Station Influent Box. The filter backwash would be returned to the headworks or directly to the primary clarifiers, similar to Alternative 1. The layout for Alternative 2 is shown in Figure 1.8.
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-18
Figure 1.8 Layout Alternative 2 - Intermediate Clarifier With Tertiary Filters Located Centrally VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-19
Piping and Pumping
The piping and pumping system configuration would be similar to Alternative 1.
There would be about 60 feet between the tertiary filter and the intermediate clarifier. Based on anticipated levels, there would be sufficient head to gravitate to the intermediate clarifier from the indicated location.
Cost Estimate (Alternative 2)
The cost for this alternative (Class 5 estimate) includes the costs of the tertiary filters, an overhang, pumping, disinfection, piping, and the rehabilitation of the intermediate clarifier. Table 1.4 highlights the cost estimate for this alternative.
Table 1.4 Layout Alternative 2 Cost Estimate
Item Description Amount
1 Tertiary Cloth Filters and Intermediate Clarifier
Site Construction. $276,000
Structural Work and Intermediate Clarifier Rehab. $615,000 Cloth Filters, Pumps, Backwash Chemicals, Equipment, etc. (1+1 Duty/Standby, 1.0 mgd each).
$1,177,000
2 Utility Water System Piping $1,306,000
3 Electrical (15%) $506,000
4 Instrumentation and Controls (10%) $310,000
Subtotal - Direct Costs $4,190,000
5 Contingency (30%) $1,260,000
6 Contractor Mark-ups (General Conditions, Overhead and Profit, 30%) $1,833,000 7 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $266,000 Estimated Construction Cost $7,516,000
8 Engineering (17%) $1,280,000
9 Legal Admin and Regulatory Costs (5%) $380,000
Total Project Cost $9,170,000
1.4.4.3 Layout 3 - Tertiary Filters and Re-use of Intermediate Clarifiers at South Location
The next alternative utilizes the same location for the filters as Alternative 1, south of the Percolation Pond pump station, but in this case, the existing intermediate clarifier would be used as the storage tank to supply peak demand, similar to Alternative 2. As noted, the structure for the intermediate clarifier could be rehabilitated and reused for the storage of disinfected filtered effluent. It is anticipated that this location will still allow the filtered effluent to flow by gravity to the intermediate clarifier; however, the filter slab will need to be raised to accomplish this.
Similar to Alternative 1, this location for the filters would keep the bulk of the activities away from where the Phase 1 contractor would be doing most of the work. Reusing the intermediate clarifier would take up VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-20
space originally allocated to new anaerobic digesters, but a preliminary analysis has shown that there would still be adequate space to locate both new digesters in the remaining area.
Tertiary Filter Footprint
The layout of the equipment and the required footprint for Alternative 3 would be the same as the previous alternatives, and backwash water would be directed to the headworks or the primary clarifiers.
Figure 1.9 shows the preliminary layout.
Piping and Pumping
The piping and pumping requirements for this alternative would be the same as for Alternative 2, with a new utility water pump station located adjacent to the existing intermediate clarifier.
There would be about 500 feet between the tertiary filter and the intermediate clarifier. To allow for flow by gravity from the filters to the intermediate clarifier, the filters would need to be raised about 42 inches.
Cost Estimate (Alternative 3)
The cost for this alternative (Class 5 estimate) includes the costs of the tertiary filters, an overhang, pumping, disinfection, piping, and the rehabilitation of the intermediate clarifier. Table 1.5 provides the details of the items included in the cost estimate for Alternative 3.
Table 1.5 Layout Alternative 3 Cost Estimate
Item Description Amount
1 Tertiary Cloth Filters and Intermediate Clarifier
Site Construction. $283,000
Structural Work and Intermediate Clarifier Rehab. $750,000 Cloth Filters, Pumps, Backwash Chemicals, Equipment, etc. (1+1 Duty/Standby, 1.0 mgd each).
$1,177,000
2 Utility Water System Piping $1,378,000
3 Electrical (15%) $540,000
4 Instrumentation and Controls (10%) $331,000
Subtotal - Direct Costs $4,450,000
5 Contingency (30%) $1,340,000
6 Contractor Mark-ups (General Conditions, Overhead and Profit, 30%) $1,950,000 7 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $255,000 Estimated Construction Cost $7,992,0000
8 Engineering (17%) $1,360,000
9 Legal Admin and Regulatory Costs (5%) $400,000
Total Project Cost $9,750,000
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-21
Figure 1.9 Layout Alternative 3 - Tertiary Filters South of Facility with Intermediate Clarifier Storage VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-22
1.4.5 Comparison of Alternatives
Three potential layout options for implementing tertiary filters and supplying utility water as part of the Phase 1 upgrades were evaluated. The first alternative (Alternative 1), while more expensive (at $10.9 million) due to the construction of an additional peak volume storage tank, offers significant advantages in terms of construction sequencing and spatial availability. The filter system location south of the Percolation Pond pump station facilitates easier access, allows for future expandability, and keeps the filters out of the area where a majority of the Phase 1 construction work is anticipated.
Alternative 2 proposes reusing the existing intermediate clarifier, saves about $1.7 million, and results in the lowest project cost estimate ($9.2 million). This approach, however, introduces the potential for spatial congestion near the solids dewatering area and anaerobic digesters, which could complicate future construction during the Phase 1 upgrades as well as daily operations.
Alternative 3, which places the tertiary filters in the same location as Alternative 1, is about $0.5 million more than Alternative 2 (at $9.75 million). It remains a lower-cost alternative with the re-use and rehabilitation of the intermediate clarifier for storage while reducing the spatial congestion and removing some construction sequencing constraints. This alternative will require the filters to be installed above grade for gravitational hydraulics from the filters to the intermediate clarifier, but that is a minor cost addition. Further, if the intermediate clarifier must be decommissioned for some reason in the future, the layout provides adequate space in the adjacent area to construct a new peak storage tank, similar to Alternative 1.
Reusing the intermediate clarifier to provide peak flow storage and disinfection volume presents a cost-effective and functionally viable solution for achieving Phase 1 goals. Accordingly, the preferred option is to proceed with using tertiary filtration and disinfection, and the use of the intermediate clarifier for storage as part of the planned initial phase of upgrades. Due to Phase 1 construction and sequencing activities, it would seem that Alternative 3 would be the preferred approach, but a closer look at the construction sequencing and potential conflicts associated with Alternatives 2 and 3 might show that Alternative 1 is the better choice. This can be done as part of the preliminary design.
Conclusion
A separate new utility water system utilizing an average of 1.0 mgd of tertiary filtered secondary effluent from the new Phase 1 activated sludge treatment process was evaluated as an approach to replace potable water for plant process water needs. Three alternatives were considered to provide an average flow of 1.0 mgd and a peak hour flow of 5.0 mgd. The cost of the new system is expected to range between $9.2 million on the low end if the filters are located closer to Digester 4 and the existing intermediate clarifier is utilized for storage and disinfection volume (Alternative 2), and up to $10.9 million if the filters are located south of the existing Percolation Pond pump station and a new storage/disinfection tank is constructed (Alternative 1). Alternative 3, which locates the filters to the south (like Alternative 1) but also makes use of the intermediate clarifier for storage, has an estimated project cost of $9.75 million and seems to be the most favorable approach because it keeps the filters out of the way of future Phase 1 construction activities. The location associated with Alternative 2 could be investigated further during preliminary design.
VOLUME 13 / CHAPTER 1: PLANT WATER SYSTEMS
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1-23
1.4.6 Other Tertiary Filtration Considerations
1.4.6.1 Use of Tertiary Filters as Part of Phase 1 Treatment Geotechnical investigations of the soils in the existing percolation ponds in 2024 showed that the top layers of the existing soil contained a lot of fine organic material. These are presumably solids from the secondary effluent that have settled and built up over a long period of time, contributing to the gradual reduction in percolation rate observed by the City. This is reported in more detail in Volume 7, Chapter 2, together with strategies to periodically remove the fine organic solids layer from the bottom of the ponds.
Due to the observed effects on percolation pond capacities by the accumulation of organic material, the City recognized the benefits that percolation of tertiary filtered effluent, rather than secondary effluent, would have for long-term maintenance of the ponds. Because of this, the City would like to approach tertiary filtration with the near-term goal of providing equipment capacity to produce the necessary utility water to serve the WWTP, with the ability to expand the facility in the future to provide partial or full treatment of the plant effluent prior to discharge in the percolation ponds. Details are provided in Volume 6, Chapter 5, which shows a larger tertiary filtration facility located in the same location as shown for Alternative 3 above. The remainder of the Utility Water system, including the use of the intermediate clarifier, would be operated as discussed above.
1.4.6.2 Tertiary Filtration of Trickling Filter Secondary Effluent In 2024, the City began a pilot study to evaluate whether tertiary filtration of the existing trickling filter secondary effluent would be effective at reducing both 5-day biochemical oxygen demand test (BOD5) and total suspended solids (TSS) concentrations to below the interim effluent limits defined by the new General Permit. The study was a requirement stipulated by the Regional Water Board, the intention being that temporary treatment facilities be provided to meet the interim effluent limits until such time as the new Phase 1 facilities were constructed.
The pilot study demonstration that some reduction in the BOD5 and TSS concentrations was achievable, but ultimately implementation of temporary facilities would take considerable time to design and construct, therefore providing limited effluent quality benefits for the capital and operating cost, while introducing complications to the treatment plant and the plant expansion process. Therefore, the Regional Water Board agreed that the studies to be performed by the City for interim BOD5 and TSS compliance were complete, and a temporary filtration system would not be required. Appendix A includes the Tertiary Filter Pilot Study Report.
VOLUME 13 / CHAPTER 2: PLANT DRAINAGE AND STORMWATER
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-1
CHAPTER 2 PLANT DRAINAGE AND STORMWATER
2.1 Introduction
This chapter describes the existing plant drainage and stormwater systems. Both systems will need to be modified and upgraded as part of the Phase 1 Project, but their overall functionality is expected to remain similar to the existing systems.
2.2 Plant Drainage System
Figure 2.1 provides an aerial view of the wastewater treatment plant (WWTP) and indicates the approximate drainage pattern for the plant drains. Currently, there are two plant drainage pump stations in the WWTP. The majority of office bathrooms, digester emergency overflows, and plant drains within the WWTP gravitate to a submersible pump station located near the boiler area, a photograph of which is shown in Figure 2.2. This pump station is equipped with two 3.4-horsepower (hp) submersible pumps, which return flow to the grit basins.
Figure 2.1 High-Level Drainage Pattern for Plant Drain System VOLUME 13 / CHAPTER 2: PLANT DRAINAGE AND STORMWATER
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-2
Figure 2.2 Plant Drainage Pump Station
A second pump station collects drainage from the Digester No. 4 Building and Digester No. 4 overflow box and pumps it into the Plant Drainage discharge line that transfers flow to the first pump station. This pump station is equipped with two 1.5-hp submersible pumps.
In addition, a catch basin at the 1961 headworks north of the grit chamber conveys flow to the Primary Trickling Filter (PTF) Pump Station.
The Primary Building and the Grit Chambers have independent drainage systems that discharge flow into the grit chamber overflow box.
In addition, the Secondary Clarifier Sludge basement area has its own sump and pump. It discharges to the Secondary Clarifier No. 2 launder recirculation box.
2.2.1 Phase 1 Plant Drainage Considerations
The new Phase 1 facilities will require an expansion of the plant drainage system, details of which will be developed during the preliminary design. Overall, the concept will be to continue to use the existing plant drainage pump station located near the boiler area and return plant drainage water to the grit basins. The rehabilitation could either be a full rehabilitation of the existing plant drainage pump, with new pumps, guide rails, controls, and piping, or the construction of a new plant drainage pump station adjacent to the one shown. In addition, new plant drain pump station (s) will either pump to the existing pump station or transfer flow directly to the grit basins.
VOLUME 13 / CHAPTER 2: PLANT DRAINAGE AND STORMWATER
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-3
2.3 Stormwater System
The existing stormwater system at the WWTP is primarily based on surface water drainage. Most of the runoff is conveyed through concrete gutters or the existing slopes to the east supernatant pit or to the asphalt-lined sludge beds. The East Supernatant Pit occasionally drains to the West Supernatant Pit when there is excess flow from both surface runoff and sludge bed drainage. From the beds, the stormwater is decanted to the supernatant pump, which rejoins other drainage lines and sends collected runoff to the head of the plant. In addition, as much of the site is gravel, a large portion of the stormwater directly percolates into the soil.
There are three areas where the surface water slopes do not convey runoff to the sludge beds or supernatant pit: the Grit Chamber Ramp, the PTF Pump Station, and the Secondary Trickling Filter (STF) Area. At the Grit Chamber Ramp, runoff falls into a sump and is pumped into the Grit Chamber Effluent Box. At the PTF Pump Station, there is a gravity line that runs north, connects with the floor drain at the 1961 headworks, and drains to the PTF Pump Station. At the STF Area, water flows to a sump in the Secondary Sludge basement, then to the STF Pump Station, and is returned to the headworks.
Figures 2.3 and 2.4 illustrate the existing stormwater drainage patterns that constitute the stormwater system.
Figure 2.3 High-Level Surface Water Stormwater Drainage Pattern VOLUME 13 / CHAPTER 2: PLANT DRAINAGE AND STORMWATER
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-4
Figure 2.4 High-Level Stormwater Pumping Schematic
The East Supernatant Pit contains a 3-inch, 5-hp self-priming pump that connects to the 6-inch supernatant line that returns runoff and sludge bed supernatant to the Grit Chamber. The supernatant pit, shown in Figure 2.5, is in poor condition and will likely need to be rehabilitated ahead of the Phase 1 construction to continue receiving stormwater. Duty/standby pumps, new discharge/collection piping, and concrete rehabilitation will be included as part of that pit rehabilitation.
VOLUME 13 / CHAPTER 2: PLANT DRAINAGE AND STORMWATER
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2-5
Figure 2.5 East Supernatant Pit Pump Station
2.3.1 Phase 1 Plant Stormwater Considerations
For the Phase 1 project, most of the sludge drying beds are to be demolished and replaced with aeration basins and secondary clarifiers. Once Phase 1 processes are operational, the existing primary and secondary trickling filter systems will be demolished. Overall, once the Phase 1 project is complete, the impervious surface area will be similar to the current WWTP or somewhat less, depending on the final sizing and layout of new facilities. Nevertheless, it is anticipated that additional stormwater conveyance and pump stations will need to be constructed.
As mentioned, the concrete in the supernatant pit is in poor condition, but once that structure has been rehabilitated, it can continue to serve as a basin for future stormwater collection. Captured storm flow from future pump sumps that are installed for surface water drainage could be routed to this pit for transfer to the head of the plant for treatment. No stormwater will drain from the site; it will all be contained and treated through the WWTP.
VOLUME 13 / CHAPTER 3: INSTRUMENT AIR AND PROPANE
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 3-1
CHAPTER 3 INSTRUMENT AIR AND PROPANE
3.1 Introduction
This chapter describes the existing instrument air and propane gas systems at the City of Santa Maria's (City) wastewater treatment plant (WWTP). Both of these systems will remain in place for the Phase 1 Project, but both may need to be modified and potentially upgraded as part of the expansion.
3.2 Instrument Air
The purpose of the instrument air supply is to provide filtered, dry, high-pressure air to treatment plant instrumentation and to air tool connectors throughout the plant. The distribution of high-pressure air is shown in Figure 3.1. Individual compressors have been installed at the headworks, primary sludge pump station building, the digester building, and the 2009 Digester Control 4 Building to supply air to the local systems, which use it for control purposes. The plant's high-pressure air supply is still also available at those locations. The local compressors increase the reliability of the air supply to the equipment.
Two tank-mounted, two-stage reciprocating piston air compressors provide clean, filtered air at between 98 and 140-145 psi to each dedicated air receiver (tank). The compressors are equipped with pressure switches to automatically start and stop the units at set pressures.
There are isolation valves at the old digester control building, the primary sludge building, secondary sludge pump station, new Digester 4 Control Building, and headworks to allow isolation of the main air system and local connection of portable compressors to keep these systems in operation in case the main air system must be taken out of service. High-pressure air is necessary for operating the bubblers at the headworks in order to control the screen cleaning cycles and also for operating the heat control and digester control valves. Portable compressors can be connected to the quick-connect couplings near these locations.
The air compressors and receivers are located in the Maintenance Building. For details, refer to Figure 3.1.
3.2.1 Phase 1 Considerations
The City has decided to move away from air-operated actuators, so all actuators provided as part of the Phase 1 Project will be electric. However, the existing instrument air system will need to be retained to support existing instruments that still use air. In addition, the City may wish to have high-pressure air connections at other parts of the plant associated with the new Phase 1 facilities for powering air tools.
These requirements and the impacts on the high-pressure air compressor sizing and distribution system will be finalized during the preliminary design phase of the project.
VOLUME 13 / CHAPTER 3: INSTRUMENT AIR AND PROPANE
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 3-2
Figure 3.1 High-Pressure Air (Instrument Air) Schematic VOLUME 13 / CHAPTER 3: INSTRUMENT AIR AND PROPANE
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 3-3
3.3 Propane System
The WWTP does not have a supply of natural gas piped to the site; instead, it uses propane. Liquid propane gas is stored on the treatment plant grounds and provides a pilot flame for the sludge heating hot water boiler and for the waste digester gas burner. The potable water heater is fueled with propane.
Propane gas can also be piped to the boiler as a standby fuel source, or the propane-powered standby boiler in the digester building can be used. The City receives deliveries of 550 gallons of propane every 3 weeks if the propane standby boiler isn't running. If the standby boiler is running, a propane delivery is required every two to three days. A photograph showing the location of the propane storage cylinder is shown in Figure 3.2.
Figure 3.2 Propane Storage Cylinder
3.3.1 Phase 1 Considerations
The existing propane gas system will need to be maintained during and after the Phase 1 expansion project in order to support critical plant operations, including the sludge heating via the hot water boiler, waste gas digester gas burner, potable water heater, and the standby boiler. Careful planning during the project's preliminary design phase will be required to maintain an uninterrupted propane supply and ensure safe system operation while construction activities are underway. Key considerations include protecting the existing liquid propane storage tank and distribution piping from potential damage, ensuring adequate access for refueling, and coordinating tie-ins or modifications to avoid service disruptions. Any expansion of heating or standby fuel demands will also need to be evaluated against current storage and supply capacity to determine whether system upgrades or additional redundancy are warranted. Safety compliance, including adherence to fire code clearances, separation distances, and pressure regulation requirements, must be maintained throughout Phase 1 construction. These items will all be addressed as part of the preliminary design.
VOLUME 13 / CHAPTER 4: UTILITY BUILDING, MAINTENANCE, AND LABORATORY OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4-1
CHAPTER 4 UTILITY BUILDING, MAINTENANCE, AND
LABORATORY
4.1 Introduction
This chapter describes the existing utility, maintenance, and laboratory buildings at the plant and the proposed upgrades and modifications required as part of the Phase 1 Project. It is anticipated that this chapter will be updated as the design progresses and the need for modified and/or additional facilities to support the operation of the expanded treatment facility becomes clearer.
The locations of the major buildings on the site that provide support for plant operations and maintenance are shown in Figure 4.1. The City of Santa Maria (City) does not have a separate Corporate Yard, and the existing wastewater treatment plant (WWTP) serves that role too.
Figure 4.1 Plant Operations and Maintenance Support Buildings VOLUME 13 / CHAPTER 4: UTILITY BUILDING, MAINTENANCE, AND LABORATORY OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4-2
4.2 Utility Building
It is not clear exactly when the existing Utility Building was constructed, but the 1961 Plans show either an expansion or modification of an existing structure, which is still present today. In 1979, the building was expanded to the north to create a Maintenance portion, which also still exists. Figure 4.2 shows a photograph of the two buildings, with the 1961 Utility Building on the left portion of the photograph and the Maintenance Building on the right portion.
Figure 4.2 Utility (Left Portion - 1961) and Maintenance (Right Portion - 1979) Buildings
4.2.1 Phase 1 Utility Building Considerations
A new utility building will be constructed as part of Phase 1 of the project. It is currently envisioned that the new utility building will be approximately 3,000 square feet and will include a workspace area and a storage area. The utility building will include a restroom equipped with hot and cold water, windows, and skylights for natural light, and outdoor light fixtures. Hose bibs will be located both inside and outside of the utility building, and access to the building will be monitored using outdoor security cameras and an alarm system. Table 4.1 lists the features that will be included in the new utility building.
VOLUME 13 / CHAPTER 4: UTILITY BUILDING, MAINTENANCE, AND LABORATORY OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4-3
Table 4.1 New Utility Building Features
Proposed New Utility Building Features/Facilities
Workspace Area
Air conditioning to meet OSHA indoor requirements.
Industrial or shop-grade wash sink for hand washing.
Floor drains.
Workbench space along walls with tool storage drawers and shelves underneath.
Movable workbench island (4 feet by 8 feet) to work on larger items.
Welding bench/area.
Industrial-grade shelving on walls.
120V, 240V, and 480V available to supply power for hand tools, welders, and to accommodate bench testing of 480V equipment.
Compressed air.
Bench grinder.
Chop saw.
Vise.
Drill press.
Ventilation system to allow for indoor welding or painting.
Pipe storage on rack on wall.
Fire protection system.
Roll up door to access workshop area.
2-ton minimum shop/bridge crane.
Roll-up door access to adjacent parts/vehicle storage.
At least one man door to access the shop.
Storage Area
Vehicle storage area that is tall enough to house a vactor truck or loader.
At least one man door to access the vehicle storage area.
Notes:
OSHA - Occupational Safety and Health Administration; V - volt Figure 4.3 shows a preliminary location for the new Utility Building. The existing structure will need to be demolished, and the new building will be located to the south. This will create some space to the north of the existing building to allow the road to be widened to increase the turning radius to accommodate dewatered sludge hauling trucks. Existing Digesters 2 and 3, as well as the existing Gravity Thickener No. 1, would also be demolished. The area shown in Figure 4.3 would allow for about a 3,000-square-foot Utility Building with space for the new Anaerobic Digesters. The final location, size, and internal division of space within the building will be determined during the Preliminary Design phase.
VOLUME 13 / CHAPTER 4: UTILITY BUILDING, MAINTENANCE, AND LABORATORY OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4-4
Figure 4.3 Preliminary Location of New Utility Building and Other Facilities
4.3 Maintenance Building
The Maintenance Building is currently connected to the Utility Building, as described above.
4.3.1 Phase 1 Maintenance Building Considerations
A separate Maintenance Building is not planned as part of the Phase 1 project. Rather, the proposed new Utility Building will incorporate a portion dedicated to maintenance activities, similar to the current arrangement. The features/facilities to be incorporated in the new Utility Building are presented in Table 4.1.
4.4 Storage Building
The Storage Building was constructed in 1996, and its condition was evaluated during the plantwide condition assessment (see Volume 4 for details). The structure was assessed to have about 20 years of remaining useful life (RUL). The northern portion of the building houses general storage, and the southern portion houses office space, a large meeting room, and ablution facilities. The ablution facilities do not include separate male and female facilities.
4.4.1 Phase 1 Storage Building Considerations
Since the building has a RUL of about 20 years, it will remain in place for the Phase 1 project and may be considered for replacement during a future plant expansion. The building does require some ongoing maintenance, but these repairs will be taken care of as part of a separate project to the Phase 1 project.
VOLUME 13 / CHAPTER 4: UTILITY BUILDING, MAINTENANCE, AND LABORATORY OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4-5
4.5 Laboratory
The laboratory at the City's WWTP conducts water and solids analyses to keep the operators informed of plant efficiencies, and to help predict problems that are developing in the process, and to comply with the current permit requirements for the WWTP. Laboratory test results are a record of plant performance and are evaluated by governing, regulatory, and private consulting agencies.
The Laboratory was constructed as part of the Operations Building in 1982. It is well equipped and expected to have more than 20 years of RUL.
4.5.1 Phase 1 Laboratory Considerations
Because the Phase 1 treatment process will be significantly different to the current treatment plant and because the new permit now requires analysis for total nitrogen, in addition to a BOD5 and TSS, it is likely that some upgrading of the existing laboratory will be included in the Phase 1 project. The details of what upgrades will be required will be developed during the Phase 1 design process.
4.6 City Yard
As noted above, the City does not have a dedicated City Yard and currently makes use of the WWTP facilities for this purpose, for example, to hold all-hands meetings or staff training events.
4.6.1 Phase 1 City Yard Considerations
As the design of the Phase 1 facilities develops, and there is more definitive information on the sizing and location of new buildings and structures, the City will be in a better position to decide what additional modifications will be required to accommodate its needs for a City Yard. It is anticipated that these modifications could include additional vehicle parking spaces, additional maintenance facilities, and potentially larger meeting room space.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-1
CHAPTER 5 SEPTAGE HANDLING
5.1 Septage Overview
The City WWTP accepts septage from industrial, commercial, and domestic customers. It is one of the few locations in the region (Santa Barbara and San Luis Obispo Counties) where septage haulers may dump.
Most of the other WWTPs in the area do not have septage receiving facilities. As a result, the City receives significantly more septage flow compared to other WWTPs of similar size. The City's WWTP typically receives septage from 54 different septage haulers. The gate to the WWTP is open for septage receiving between 7:00 a.m. and 3:30 p.m. Monday-Thursday and from 7:00 a.m. to 1:30 p.m. on Fridays.
In the one-year period between November 2023 and November 2024, a total of 11.5 million gallons (MG) of septage was received at the WWTP. An informal survey of selected Southern California WWTPs that receive septage was conducted in 2024 and 2026. Table 5.1 shows a summary of the information obtained for the WWTPs and City, and presents the septage flow as a percentage of the average WWTP influent flow rate. As shown, the City's contribution from septage haulers is significantly greater than all the other WWTPs surveyed, at around 0.7 percent of the influent flow, which is between 1.7 to about five times greater than the others. In addition, all WWTPs listed in Table 5.1 operate activated sludge processes, except for Santa Maria, which operates a trickling filter process.
Table 5.1 Summary of Septage as Percentage of Influent Flow for Various WWTPs Treatment Plant Average Influent Flow
Rate to WWTP (mgd)
Total Daily Septage Flow
(gallons)
Percentage Contribution
of Septage to Average
Influent Flow
City of Riverside - RWQCP 26.9 33,000 0.12%
Eastern Municipal Water District -
San Jacinto Valley RWRF
8.0 12,000 0.15%
Eastern Municipal Water District -
Perris Valley RWRF
14.0 35,000 0.25%
Inland Empire Utilities Agency -
Regional Plant No. 1
26.0 30,000 - 35,000 0.14%
City of Fresno WWTP(1) 54.0 210,000 0.39%
City of Santa Maria WWTP 6.6(2) 44,000(3) 0.67%
Notes:
mgd - million gallons per day; RWQCP - regional water quality control plant; RWRF - regional water reclamation facility (1) Information obtained during a visit on April 21, 2026. Typically receive 50 - 60 trucks per day. The station is open 7-days per week (5 a.m. to 5 p.m.) but typically only receives 20 - 30 loads on Saturdays and <15 loads on Sundays. (2) Based on monthly average influent flow for 12 months starting November 2023 from self-monitoring reports. (3) Based on one year of data, November 2023 to November 2024; 11.4 MG and 260 days available for dumping.
In addition to the disproportionately high septage contribution at Santa Maria, observations from operational staff and from previously recorded data suggest that septage can produce slug loads on the plant and affect effluent biochemical oxygen demand (BOD) and total suspended solids (TSS) concentrations. As such, the City conducted sampling to determine the significance of the septage on the organic and nitrogen loads entering the plant.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-2
Figures 5.1 and 5.2 highlight one of two septage receiving areas at the WWTP. The other receiving area is designated for septage that may contain large debris and rags, and haulers are required to discharge the septage through an in-ground screen/grating, which is later manually raked to remove captured material.
Material removed from the screen/grating is manually placed into a dumpster. Both receiving areas connect directly to a 48-inch manhole, which then diverts flow to one of two incoming 48-inch influent pipes through a 60-inch diversion manhole.
Figure 5.1 Existing Septage Receiving Area at Entrance to WWTP Figure 5.2 Existing Septage Receiving Area at Entrance to WWTP VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-3
5.2 Septage Sampling Results
To obtain additional information on the quality of septage being received, the City conducted four separate sampling events between September 2024 and August 2025. Each sampling effort aimed to quantify the organic and nitrogen loading entering the plant from septage haulers.
5.2.1 First Sampling Event - September 2024
In September 2024, the City collected composite samples upstream and downstream of the septage receiving station in order to assess the impact of septage dumping on the concentrations and loads of BOD, ammonia (NH3), and total Kjeldahl nitrogen (TKN) entering the WWTP.
Three separate 8-hour composite samples, coinciding with the septage receiving period, were collected a week apart and analyzed for NH3, TKN, and BOD. Automatic samplers were set up to collect a sample every 15 minutes and sampling began at 8:00 a.m. prior to the first septage haulers entering the plant.
Two samples were collected upstream of the septage dumping locations, from the north and the south trunk mains at Junction Box A', and the third sample was collected downstream of the septage dumping locations at the headworks. The volume of septage dumped on each of the sampling days was recorded, as well as the influent flow.
Table 5.2 shows a summary of the influent and septage flows, and the flows in the North and South trunks during the sampling. The data indicates that an average of almost 30,000 gallons of septage was dumped for the three sampling dates. This contributed an average of 1.5 percent of the incoming flow for the 8-hour period on those days.
Table 5.2 Summary of September 2024 Sampling Event - Flows Sampling
Date(1)
Influent Flow to WWTP
During Sampling Period
(gallons)
Total Daily
Septage Flow
(gallons)
Flows (MG) Percent Contribution of
Septage to Average North Trunk South Trunk Influent Flow(1,2) 9/16/2024 2,258,333 34,099 1.35 0.91 1.5%
9/23/2024 2,295,833 20,349 1.37 0.92 0.9%
9/30/2024 2,312,500 35,443 1.38 0.93 1.5%
Average 2,288,889 29,964 1.37 0.92 1.5%
Notes:
(1) Sampling period lasted from 8:00 a.m. to 4:00 p.m.
(2) Percentage is based on eight hours of influent flow.
Table 5.3 summarizes the concentration of BOD, NH3, and TKN upstream and downstream of the septage station. The influent BOD sample was collected as a single combined sample. As indicated, the BOD concentration was significantly higher at the headworks compared with the combined sample collected upstream of the septage station. The average BOD concentration increase was almost 38 percent. The North trunk consistently showed higher concentrations of NH3 than the South trunk. TKN concentrations showed similar trends for the North and South trunks. Accounting for the average flow split between the North and South trunks during the sampling period yields an average upstream NH3 concentration of
71.6 milligrams per liter (mg/L), compared to 76 mg/L after septage addition, a 6 percent increase.
Similarly, for TKN, the combined stream had an average concentration of 99.4 mg/L compared to 111 mg/L after septage, an increase of almost 12 percent.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-4
Note that the percent changes indicated above were only for the 8-hour period during which septage was received at the WWTP. The actual percent contribution by septage over the entire day would be lower, but the higher values represent the concentration of the slug of influent flow that the treatment process would experience during weekdays when septage is accepted at the plant.
Table 5.3 Summary of Results From First Sampling Event - September 2024 - BOD5, TKN, and NH3 (1)
Sampling
Date
BOD5 (mg/L)(1) TKN (mg/L)(1) NH3-N (mg/L)(1)
Upstream of
Headworks
(Pre-Septage)
Headworks
(Post-Septage)
Upstream of
Headworks
(North
Trunk)
Upstream
of Septage
(South
Trunk)
Headworks
(Post-Septage)
Upstream of
Headworks
(North
Trunk)
Upstream
of Septage
(South
Trunk)
Headworks
(Post-Septage)
9/16/2024 340 388 110 84 93 97 66 65
9/23/2024 376 533 94 93 120 69 56 77
9/30/2024 424 650 110 95 120 74 56 86
Average 380 524 105 91 111 80 59 76
Notes:
NH3-N - nitrogen component of ammonia
(1) Samples were collected from 8:00 a.m. to 4:00 p.m. to coincide with septage dumping.
In addition to the three major constituents listed above (BOD, TKN, and NH3), the sample collected at the headworks was also analyzed for several metals, priority pollutants, and per- and polyfluoroalkyl substances (PFAS) compounds. Because there was no “before septage” sample to compare with, the measured concentrations cannot be attributed to septage only. Therefore, these results are not presented here, but have been included in Appendices A and B for information.
Using the flow information and the concentration data, the load of BOD, NH3, and TKN from the septage was calculated and compared to the incoming wastewater load. The loading was flow-adjusted to a 24-hour basis by utilizing the observed average daily flow from the sampling event. The results in Table 5.5 show that when adjusted for a 24-hour composite, the septage contributed about 6.9 percent of the NH3 load, 11.9 percent of the TKN load, and over 28 percent of the BOD load.
A BOD load of 2,873 pounds per day (lb/day) is equivalent to a concentration of 55 mg/L based on the average influent flow of 6.26 mgd for the three sample days, including septage flow.
Table 5.4 Contribution of Septage to Influent BOD, NH3, and TKN Load - September 2024 (Adjusted for 24-Hour Period)
Description NH3
(lb/day)(1)
TKN
(lb/day)(1)
BOD
(lb/day)(1)
Average Load Upstream of Septage(2) 1,369 1,891 7,254
Average Load at Headworks 1,470 2,147 10,127
Average Contribution of Septage(3) 101 256 2,873
Notes:
(1) Load measured over an 8-hour sampling period when septage received, equivalent to daily load for septage flows. (2) Upstream loads based on concentrations in influent wastewater collected over 8 hours and adjusted to a 24-hour value based on average monthly reported concentrations.
(3) Based on measured concentrations and flow for an eight-hour sampling period.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-5
5.2.2 Second Sampling Event - Major Haulers - March/April 2025 Due to the findings from the September 2024 sampling event that the septage appeared to be contributing significantly to the incoming plant load, a second sampling event was carried out in March and April 2025. This event focused on the major septage haulers. Information gathered by the City showed that of the 54 septage haulers, eight each contributed more than 380,000 gallons per year to the plant. Figure 5.3 shows graphically the volumetric contribution of each septage hauler for the period of November 2023 through November 2024. The goal of the second sampling event was to collect four separate samples from the eight identified haulers to determine whether one or more are significant contributors to the incoming plant loads.
Table 5.5 lists each of the eight haulers and the volume they contributed to the plant during the November 2023 to November 2024 period. The total contributed by the eight major haulers was a little over 6.5 MG, or about 57 percent of the total volume dumped. There were two additional haulers that fell into the “major hauler” category [Frank's Underground Utilities (415,500 gallons) and North County Septic (409,200)], which were not included in the sampling exercise. Frank's Underground Utilities is no longer in business.
Table 5.5 List of the Eight Septage Haulers and Their Annual Flow Contribution Septage Hauler
Volume Dumped
(November 2023-November 2024)
(gallons)
Average Volume per Day
(gpd)(1)
Al's Septic Service 1,391,400 5,352
Harvey's Honey Huts 572,500 2,202
I&G 681,300 2,620
Marborg Industries, Inc. 1,379,489 5,306
Pacific Petroleum Company 449,693 1,730
Portable Johns 387,500 1,490
United Site Services 1,051,200 4,043
Valley Septic Service 599,109 2,304
Total 6,512,242 25,047
Percentage of Total Septage Volume(2) 57.1%
Notes:
gpd - gallons per day; I&G - Ingram and Greene
(1) Septage dumping takes place 5 days per week; 260 days per year. (2) Based on total volume dumped of 11.4 MG (November 2023 to November 2024).
More than 20 parameters were analyzed for in the samples collected from the major septage hauler loads.
The list of parameters is included in Appendix D.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-6
Figure 5.3 Septage Contributions From Major Haulers - November 2023 to November 2024 VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-7
Table 5.6 shows the results for the major wastewater constituents. Each septage hauler was sampled between two and four times over the sampling period. Appendix E provides a summary of all laboratory data for all parameters over the sampling period from each hauler.
Table 5.6 Average Concentrations for Constituents Sampled for Each Major Hauler Septage Hauler COD
(mg/L)
BOD5
(mg/L)
TSS
(mg/L)
VSS
(mg/L)
TKN
(mg/L)
NH3
(mg/L)
I&G 8,750 1485 6,200 4,650 425 129.5
Al's Septic Service 16,850 1,463 16,725 12,128 588 138
Harvey's Honey Huts 9,800 3,775 3,220 2,820 778 898
Marborg Industries, Inc. 27,675 5,543 19,228 12,033 1032.5 1100 Portable Johns 11,175 4,100 4,450 3,900 723 1,120
Pacific Petroleum Company 5,767 1,970 1,343 1,128 617 708 Valley Septic Service 10,925 1,485 9,275 7,025 428 145
United Site Services 8,325 2,725 3,900 3,175 618 793
Notes:
COD - chemical oxygen demand; VSS - volatile suspended solids Note that the concentrations of each constituent from the major haulers are large. This produces a slug load effect on the plant as the concentrated flows enter the facility. As shown, the largest concentrations of all constituents tested were in septage from Marborg Industries, with the exception of VSS, which was slightly lower than the concentration from Harvey’s Honey Huts. The TSS, BOD, and TKN loading in lb/day from each major hauler is shown in Figure 5.4.
Figure 5.4 Septage Loading From Major Haulers
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-8
5.2.3 Third Sampling Event - June 2025
A third sampling event was conducted in June 2025. It included sampling upstream and downstream of the septage receiving station, similar to the first sampling event, except that there was one combined composite sample upstream and one downstream, and sampling was conducted over a full 24-hour period on each day for seven selected days in the month. The goal was to capture data for periods when septage dumping was taking place and also for when septage dumping was not taking place, i.e., over the weekend. It was not possible to sample for seven consecutive days, but all seven days of a week were captured over a four-week period.
In this sampling event, TSS, total dissolved solids (TDS), NH3-N, and total nitrogen were sampled.
Table 5.7 lists the average concentrations and load contributions for each constituent upstream and downstream of the septage receiving station, for the days on which septage was accepted at the plant, excluding the weekends. Appendix F presents the summarized concentrations observed during this sampling event.
Table 5.7 June 2025 Sampling Event Results
Description TSS TDS NH3-N Total
Nitrogen TKN(1)
Average Concentration Upstream of Septage (mg/L) 320 1084 48 67 66 Average Load Upstream of Septage (lb/day)(2) 16,900 57,100 2,600 3,600 3,500 Average Concentration Downstream of Septage (mg/L) 453 1,111 55 75 76 Average Load Downstream of Septage (lb/day) 24,100 59,100 2,900 4,100 4,050 Average Contribution of Septage (lb/day) 7,230 1,990 340 410 560 Average Septage Contribution (%)(2) 30% 3% 12% 10% 14%
Notes:
(1) TKN was only sampled on three out of seven days during this event. (2) Average septage contribution to the plant when excluding the days on which no septage was received.
Table 5.7 indicates that septage does contribute a significant load to the plant: 30 percent for TSS and between 10 and 14 percent for the nitrogen parameters. As the plant receives septage, the influent stream experiences an increase in both organic and nitrogen loading. The large contributions from the septage stream may affect the ability of downstream processes to treat wastewater.
There are some confounding variables. On the days that the City did not accept septage (Saturday and Sunday), the data showed that TSS loading increased by 2,430 lb/day downstream of the septage receiving station, representing 13 percent of the average loading observed during that time period. This suggests that influent TSS may still increase, regardless of additional contributions from septage.
The increase over the weekends may be partially explained by the piping orientation feeding the headworks, shown in Figure 5.5. The parallel 48-inch sewers (see Volume 5, Chapter 1) that connect to Box B are relatively flat. Therefore, solids can settle in these pipes during low-flow periods and may be resuspended during high-flow periods, regardless of additional contributions from septage.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-9
Figure 5.5 Influent Area Piping Elevations
5.2.4 Fourth Sampling Event - July to August 2025
A fourth and final sampling event was conducted from July to August 2025. Sampling was conducted upstream and downstream of the septage receiving station. This sampling event was carried out in order to specifically track BOD data and develop a more comprehensive understanding of septage loads. As in the previous sampling events, a composite sample was collected over 24 hours and once for every day of the week. In this sampling event, TSS, TDS, BOD5, NH3-N, and total nitrogen were collected. The daily flow of septage over the corresponding week was also provided during this sampling period.
The average concentrations and calculated loads for the five parameters from the fourth sampling event are shown in Table 5.8. In this case, the TSS again showed the highest contribution at 30 percent.
Ammonia and total nitrogen contributions from septage were in a similar range to the third sampling event (14 to 16 percent), and the contribution of BOD was measured at 17 percent.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-10
Table 5.8 July/August 2025 Sampling Event Results
Description TSS TDS BOD5 NH3-N Total
Nitrogen
Average Concentration Upstream of Septage (mg/L) 310 920 393 49 69 Average Load Upstream of Septage(1) (lb/day) 16,662 49,196 21,030 2,623 3,684 Average Concentration Downstream of Septage (mg/L) 442 922 457 55 76 Average Load Downstream of Septage (lb/day) 23,796 49,530 25,200 3,122 4,283 Average Contribution of Septage (lb/day) 7,134 334 4,170 499 599 Average Septage Contribution (%) 30% 0.7% 17% 16% 14%
Notes:
% - percent
(1) The days in which no septage was received are not included in the loading average.
5.2.5 Comparison of Sampling Events
This section compares the results from each septage event to establish if there are any correlations between septage constituents. The third and fourth sampling events provide a strong point of comparison because the sampling methodology was the same in both. The results from either event provide a reasonable estimate of the loading the plant receives from septage and provides a comparison of the accuracy of sampling. Figures 5.6 and 5.7 illustrate the comparison of the loading from both sampling periods. BOD was not analyzed during the third sampling event and is therefore not included in the comparison in the figures. However, in the first sampling event, the BOD load was measured at 2,873 lb/day, which is about 69 percent of the load measured in the fourth sampling event (4,170 lb/day).
Figure 5.6 Septage Loading Comparison Between Sampling Events 3 and 4 - TSS and TDS VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-11
Figure 5.7 Septage Loading Comparison Between Sampling Events 3 and 4 - NH3 and Total Nitrogen The results indicate that septage continues to contribute a significant amount of loading to the plant. As expected, the loading of the major constituents varies from day to day depending on the mix of septage haulers that visit the site. The results have shown that TSS loading can reach up to 7,000 lb/day of additional loading, and between 350 and 500 lb/day of ammonia, and between about 400 and 600 lb/day of total nitrogen. This information is reported in tabular form in Appendix G.
Table 5.9 summarizes the loading of major constituents for the four sampling events, where available, and then provides a range of loading that can be used for planning purposes.
Table 5.9 Summary of Septage Loading Contributions and Planning Range Average Contribution From Septage for
Each Sampling Event
BOD5
(lb/day)
TSS
(lb/day)
NH3-N
(lb/day)
TKN
(lb/day)
Event #1 2,873 Not Measured 101 256
Event #2(1) 612 2,176 128 142
Event #3 Not Measured 7,231 344 564
Event #4 4,179 7,134 499 Not Measured
Anticipated Loading Range (lb/day) 2,800 - 4,200 3,500 - 7,300 100 - 500 250 - 560 Notes:
(1) Eight major haulers only, data just for comparison.
Clearly, the results of the sampling events confirm that the septage received at the City's WWTP is contributing significantly to the loads that the plant is required to treat. Also, because septage is only accepted five days per week, it induces an additional diurnal load to the plant during the weekdays, meaning that the plant experiences more variation in BOD5 and nitrogen load than would be experienced by other WWTPs that either do not accept septage or ones that receive a more typical volume of septage.
Accordingly, managing septage and its associated load will be important in order to manage effluent quality and preserve the biological processes downstream of the headworks.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-12
5.2.6 Impact of Current Septage Loads on Effluent Quality Currently, the Secondary Trickling Filter process is not able to meet the Interim Discharge limit of 60 mg/L for BOD5 set by the new General Permit (see Volume 2, Chapter 4) for more information. The City has been evaluating approaches to reduce the effluent BOD5 concentration to meet the interim limit that include tertiary filtration and chemical addition (see Volume 13, Chapter 1 for more information).
The sampling events have provided valuable information about the contribution of septage to the incoming organic and nutrient load at the plant. Another way to reduce the effluent BOD5 concentration is to lower the incoming BOD5 load. From the values shown in Table 5.9, septage is estimated to add between 2,800 and 4,200 lb/day of BOD to the treatment plant load. At an average daily plant flow rate of
6.5 mgd, this is equivalent to increasing the influent wastewater BOD5 concentration by between 52 and 77 mg/L. Therefore, significantly reducing or potentially eliminating septage dumping at the City's WWTP would be expected to lower the effluent BOD5 concentration under the current treatment plant configuration.
5.3 Proposed Modifications to the Septage Receiving Area Based on the sampling results reported above, septage contributes a significant loading to the treatment plant. If the City continues to accept septage at the plant, then improvement should be considered to help with operations and reduce the impacts of the high-strength slugs entering the treatment process.
Improvements could include customer access to septage receiving, equalization basins for metering and pre-treatment prior to returning to the treatment process, and even standalone treatment. Some proposed improvements to the septage process are discussed in the following sections.
5.3.1 Debris Removal
The septage haulers coming to the WWTP are divided into two groups: those with high solids loads containing a lot of rags, and those with more conventional septic waste. The high-load group discharges in the northern area, near the grease receiving area, and the second group discharges under the canopy area (shown earlier in Figures 5.1 and 5.2).
In the northern area, the discharge point is equipped with a bar screen, but the spacing is fairly large, and some debris, rags, rocks, and other solids get through to the influent sewers. Accordingly, dischargers need to manually rake and remove larger debris from the area as they are dumping.
In the canopy area, the grade of the influent pipes that receive this septage is fairly flat, and therefore sand and rocks entering at the septage station (both locations) settle out in the large 48-inch lines downstream. These solids continue to build up in the influent pipes until they are flushed out during high-flow events, which is an operational issue for plant staff and may explain some of the TSS values measured at the headworks, even when septage was not being dumped.
Moving forward, the City would like to see a more robust system for the removal of rocks and rags. One example arrangement is where the septage hauler connects to a camlock fitting and discharges into a line (see the top image in Figure 5.8) that feeds a downstream box, where rocks and some grit become trapped. These are removed manually after each septage load by opening the wing nuts on the box's front plate. This approach would be very labor-intensive and probably not suitable for Santa Maria, given the high number of septage discharges each day.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-13
Figure 5.8 Examples of Septage Station Improvement Features Utilizing Manually Cleaned Screens VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-14
Another approach (lower image in Figure 5.8) shows a different arrangement in which the septage hauler discharges to an open steel container that has a V-shaped bar screen built into the base. The screen captures rocks and rags, which are then manually raked out by the septage hauler into an adjacent dumpster. Screened flow from the base of the tank can then be directed into the headworks or a holding tank. Both examples above are simple systems with minimal automated or moving parts. However, both require manual removal of the trapped screenings and rocks, which may be cumbersome given the large number of septage loads that the City receives.
A third alternative is a more automated approach, for example, using a Huber RotaShield unit, as shown in Figure 5.9. The RotaShield is a septage acceptance unit designed to screen and separate coarse material such as rags, plastics, stones, and other debris from septic or sludge deliveries before further treatment.
Incoming septage is fed into a rotating perforated drum, where large solids are retained while fine material passes through. As the drum rotates, solids are slowly moved out of the rotating drum and discharged into a washer compactor, where it is washed, dewatered, and discharged to a bin for disposal.
The unit features forced material guidance and spray water to prevent blockages in the drum perforations, enclosed operation with the ability to connect to an odor control system, and high solids-handling capacity. Each unit can be configured with two 4-inch male camlock inlet connections for simultaneous offloading of two trucks into the same RotaShield unit. Huber also offers a hauler access station that uses a card reader to record the date, time, and hauler information, as well as providing secure access and operation for approved haulers. Figure 5.9 shows a typical installation of two units.
The City would like to see the existing two septage dumping areas consolidated into one area. This consolidation can be achieved with the RotaShield Units by installing them underneath the existing canopy. Special consideration will be required for recreational vehicles (RVs) and other select users that are not equipped to discharge through the Huber RotaShield units. Typical RVs utilize a gravity drain connection with minimal available discharge head, making it impractical to route flow directly into the elevated Huber RotaShield inlet without a separate below-grade receiving tank and pump system. Such a system would add complexity and require periodic O&M activities by the City.
Because RV wastewater is not expected to contain the same quantity of rags, rocks, and other irregular debris often found in commercial septic loads, the City may instead provide a separate grade-level gravity connection for RVs and other select haulers, similar to those commonly found at RV parks. This connection could discharge directly to the influent sewer and headworks, while the remaining haulers will be required to discharge into the Huber RotaShield system. The final configuration, including whether RVs and other select haulers are provided with a separate discharge connection should be evaluated during preliminary design.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-15
Figure 5.9 Huber RotaShield Septage Acceptance Units
Huber RotaShield Field Test
Based on the proposed capabilities of the RotaShield system, the City decided to conduct a one-week field trial. A unit was brought to the treatment plant and installed on November 3, 2025, and operated for three days. Figure 5.10 shows some photographs taken during the operating period. The top left image shows the unit in position, treating the septage from a hauler. The unit was able to unload a 4,500-gallon truck in 6 or 7 minutes and was efficient at removing rags and larger rock material. Haulers were able to pressurize their tanks to lift the septage up to the screen inlet point.
A significant amount of small rock and grit is introduced with septage, as depicted in Figure 5.10 (top right-hand photograph). Because these solids pass through the unit's screen, an additional grit-removal process, such as a dedicated grit trap or chamber, would be necessary. The material discharged from the unit was thoroughly washed and dewatered, making it substantially less objectionable and more visually appealing compared to the material in the current septage scrapings dumpsters. An additional operational benefit observed by the plant operators was a significant improvement in the headworks bar screen run times after implementing septage pretreatment with the RotaShield unit.
The City found the unit's maintenance requirements reasonable, provided operators perform daily rounds and bi-weekly pressure washing to ensure optimal screen permeability. Periodic checks and replacement of wear parts are also necessary with a frequency dependent on grit accumulation.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-16
Figure 5.10 Huber RotaShield Field Trial - November 2025 Based on the successful field trial, the City would like to include Huber RotaShield units as part of the improvements to be made for the septage receiving system.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-17
Huber RotaShield Criteria
The proposed equipment for the screening of septage is the Huber Sludge RotaShield and Wash and Press (WAP). This unit is a screening drum that separates coarse solids (less than 10 millimeters) and liquid streams. The solids are washed, compacted, and discharged into a bin. Septage trucks may be connected to either unit using a 4-inch connection. In addition, these units may be configured with connections on both sides such that one unit can accommodate two haulers simultaneously.
As noted above, the characteristics of the septage indicate a significant amount of debris, rocks and rags.
This level of debris could impact the lifetime of the units and lead to more extensive wear and maintenance than anticipated. As a result, it is recommended that three units be installed (two duty, one standby) to allow for one unit to be out-of-service for maintenance. These units would be installed under the existing canopy to provide some protection from the elements (the existing canopy is shown in Figure 5.1).
The preliminary sizing criteria for the units are shown in Table 5.10.
Table 5.10 Preliminary Sizing for Huber RotaShield Units Item Units Value
RotaShield
Septage Acceptance Capacity gpd 44,000
Units duty x standby x maintenance 2 + 1
Maximum Flow Rate gpm 400
Sizing feet, length x width x height 12 x 8 x 8
Weight pounds 2,976
Wash Water Consumption (RotaShield) gpm 23
Washer Compactor (WAP)
Maximum Screening Capacity cubic feet/hour 140
Wash Water Consumption gpm 16
Weight pounds 750
Notes:
gpm - gallons per minute
Site Modifications
The City would prefer the two septage dumping areas described above consolidated into one area. The high-load dischargers and the more conventional septic waste dischargers would both be able to connect to the RotaShield units.
In addition, the RotaShield units will reduce the amount of solids that accumulate in the 48-inch influent pipes by removing solids from septage before it enters the incoming sewer to the headworks. Figure 5.11 indicates the existing pipe orientation at the septage receiving station under the canopy. In the new configuration, the RotaShield units will still connect to the existing underground pipes and to the diversion manhole.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-18
Additional grit screens may be added at the inlets and in the pipe connections as needed. A slight expansion of the existing slab will be necessary to accommodate the third unit and to permit haulers to attach on both sides of the overhang.
Figure 5.11 Existing Pipe Orientation at the Septage Receiving Station With the Canopy
5.3.2 Septage Equalization Basin for Influent Metering
As discussed previously, the BOD, TSS, and NH3 loadings from the septage station are significant and can result in adverse impacts to the proposed activated sludge secondary treatment facilities. To address this concern, the City is also considering a holding tank to accept screened septage. The idea would be to meter the flow from the tank into the plant over a period of hours to even out the septage load and avoid high load variations. The need for a tank will be assessed further during preliminary design based on the expected loads from septage haulers.
This option would include a storage facility sized for no more than 2 days of septage, roughly 0.12 MG.
This will be achieved with two 25-square-foot basins with 14 feet of depth each. Each basin will be about 60,000 gallons and will accommodate one full day of septage flow for metering into the WWTP. The basin will be located near the existing septage overhang and connect to the existing 60-inch diversion manhole.
The septage flow may be able to gravitate to Box B. The ground elevation at the septage station is 173.5 feet, and the current water elevation at Box B is 170.63 feet at peak wet weather flow. However, it will be equipped with recessed impeller standby pumps with variable speed controllers in case of overflow.
5.3.3 Return Activated Sludge Treatment of Septage
Due to the high-strength nature of septage and the daily volume received at the treatment plant, it may be beneficial to treat it in a separate biological process, similar to the approach used for treating dewatering liquor. And, because the Phase 1 treatment system will include new mechanical dewatering equipment, there may be an opportunity to combine treatment of dewatering liquor with septage.
In order to develop a preliminary cost estimate for a standalone septage treatment system, a recent dewatering liquor side-stream treatment project in Moreno Valley, California was used as a basis for sizing and costing. The project included the construction of equalization basins and return activated sludge (RAS) treatment of dewatering liquor containing high concentrations of NH3, orthophosphate, and COD.
The Moreno Valley facility treats up to 192,600 gpd of flow with a total NH3 load of about 1,700 lb/day.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-19
The size of the facility was adjusted based on projected septage flows and loads appropriate for Santa Maria. It was assumed that future septage flows will average around 44,000 gpd with a future buildout at 60,000 gpd. NH3 and BOD5 loads were assumed to be in the range of 100 to 500 lb/day and 2,800 to 4,200 lb/day, respectively (Table 5.9).
In addition, the equalization basin would be sized to hold a total of 0.18 MG of flow, configured in three separate basins of 0.06 MG each. The basins would be operated in a duty standby mode, with one basin offline for cleaning/maintenance. The equalization basins would be directly connected to aeration basins sized to treat the daily septage load. The sizing of the aeration basins would be suited to accommodate projected septage loads as well as any potential centrate or dewatering flows. The unique feature of this aeration basin system is that, in addition to the septage flow, it would receive a portion of the RAS from the Phase 1 activated sludge secondary clarifiers. Aeration air would be provided to assist with the breakdown of BOD and nitrification of ammonia. The high-nitrate, low BOD stream from the septage aeration basins would be blended with the remaining RAS flow and be recycled to the Phase 1 anoxic zones as normal. The lower ammonia load and higher nitrate load from the septage treatment system would provide additional nitrate for denitrification and reduce the overall ammonia load on the Phase 1 activated sludge system.
It is anticipated that the new septage treatment system will be located at the southern edge of the site property, near the future Phase 1 secondary clarifiers and aeration basins. Coupling the equalization and aeration basins will reduce the slug-loading effects of septage and improve the overall effluent quality of the treatment system.
5.3.4 Conceptual Layouts
There are two possible layouts depending on the level of septage treatment that is provided.
Figure 5.12 illustrates the conceptual layout for potential smaller-scale improvements for the septage receiving area and the construction of an equalization tank for holding and metering flow back to the headworks. The RotaShield units would be installed beneath the existing overhang. As mentioned, the three units will be installed such that pumper trucks may connect to each unit on either side of the unit.
For dumpers that do not have the ability to pressurize their septage tanks for discharge, such as recreational vehicles and the like, an alternative arrangement will be needed. Initial thoughts include providing a relatively small self-cleaning sump into which “non-pumping” haulers would dump.
A self-priming pump would transfer the contents of the sump to the RotaShield unit for processing. At the end of each day, the sump will be flushed to clean out any remaining debris. This concept or alternatives will need to be developed further during the preliminary design phase.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-20
Figure 5.12 Proposed Septage Improvements for Equalization and Return to Headworks Figure 5.13 illustrates the conceptual layout and possible locations for the full septage treatment option, which includes septage upgrades, a septage pump station, and the equalization and aeration basins.
Three different locations for the treatment tanks (equalization and aeration basins) are shown. The southernmost location may not be preferred because it is close to the property line, and odor from the septage may become a future concern. Also, if the dewatering liquor is combined with the septage for treatment, then this location is relatively far from the dewatering building. The location to the northeast of the tertiary filters will be open after demolition of the existing facilities, and may be a good location.
However, this area would only be available after demolition of the existing facilities, which may be a disadvantage. It is also relatively far from the dewatering building if dewatering liquor is to be combined with septage for treatment. The third location is to the north of the new secondary clarifiers, adjacent to the proposed cake storage area. This location is far from the property line, so odor is not expected to be a concern and is close to the dewatering building if septage and dewatering liquor treatment is to be combined. Its disadvantage is that it would be furthest from the septage receiving area and, therefore, require the longest pipe run. The most suitable location for the septage treatment facility can be evaluated further during the preliminary design. The RotaShield units would be located underneath the existing overhang near the plant entrance, as before.
Note that for each layout and alternative, the septage overhang and slab will need to be expanded slightly in order to accommodate trucks and haulers.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-21
Figure 5.13 Proposed Septage Improvements for Full Treatment Showing Three Alternative Locations VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-22
Septage Transfer Pump Station
In each case, a septage transfer pump station would be required to transfer flow from the septage receiving station to the equalization tanks, and then either metering it to the headworks or transferring it to the aeration basins, in the case of the full treatment approach. The station will connect to the existing 60-inch fiberglass-reinforced plastic diversion manhole installed as part of the 2019 improvements to the Septage Receiving Station. Pumps would be housed in a sump. The pumps will be able to convey flow to the other side of the site or to meter back into the existing influent lines.
The preliminary design criteria for the septage transfer pump station are shown in Table 5.11.
Table 5.11 Preliminary Design Criteria - Booster Pump Station Item Units Value
Sump Diameter feet, length x width x height 6 x 9 x 6
Operating Depth feet 5
Sump Liner - PVC
Pump Type - Recessed Impeller
Number of Pumps Duty + Standby 1 + 1
Rated Capacity gpm 350
Head feet 35
Motor Size hp 10
Speed Control - Variable Speed
5.3.5 Planning Level Cost Estimates
Three separate cost estimates were developed for potential upgrades of the septage system:
1. Septage station modifications only - which would only include the addition of Huber screening units and consolidation of the two existing septage areas.
2. Septage station modifications and equalization basins for metering - which would include the addition of Huber screening units, consolidation of the two existing septage areas, and the provision of holding tanks for daily metering of septage flow to the headworks.
3. Full septage treatment and septage station modifications - which would include the addition of Huber screening units, consolidation of the two existing septage areas, provision of a new transfer pump station, and RAS aeration basin treatment of the septage.
Level 1 Modifications
Table 5.12 lists the preliminary planning level construction cost estimate for adding Huber RotaShield units and consolidation of the two septage receiving areas. There would be no major piping or equalization in this alternative.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-23
Table 5.12 Septage Station Improvements Cost Estimate - Level 1 - Improved Screening Only Item Description Amount
1 Septage Station Modifications
Site and Piping Modifications. $324,000
Construct Three (3x) Huber RotaShield Units. $1,950,000 Subtotal - Direct Costs $2,274,000
2 Contingency (30%) $684,000
3 Contractor Markups (General Conditions, Overhead and Profit) (28%) $871,000 4 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $131,000 Estimated Construction Cost $3,960,000
Level 2 Modifications
Table 5.13 lists the preliminary planning-level construction cost estimate for improving the septage station with Huber units, along with the construction of an equalization basin that holds up to two days of septage flow, separated into two compartments, to be metered slowly into the plant each day.
Table 5.13 Equalization Basin and Metering Cost Estimate - Level 2 - Small Equalization and Return to Headworks Item Description Amount
1 Septage Station Modifications
Site and Piping Modifications $324,000
Construct Three (3x) Huber RotaShield Units $1,950,000 2 Metering Pump Station and Small Equalization Basins (2 x 60,000 gal) $$474,000 Subtotal - Direct Costs $2,751,000
3 Contingency (30%) $829,000
4 Contractor Markups (General Conditions, Overhead and Profit) (28%) $1,052,000 5 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $$158,000 Estimated Construction Cost $4,790,000
Level 3 Modifications
For the full treatment alternative, the costs were primarily based on the cost estimates developed for a side-stream dewatering liquor treatment system recently constructed in Moreno Valley, California. The direct costs listed for that project were escalated for inflation and subsequently factored down for sizing.
Typical civil and electrical direct cost factors were added.
It is anticipated that the Santa Maria system would be roughly a third of the size of the Moreno Valley installation, but due to the embedded costs of construction, a 55 percent direct cost factor was utilized. In addition, the direct costs for the transfer pump station were estimated as half the direct cost of the larger-scale pump station for the full septage treatment as a result of the reduced flows required.
Table 5.14 lists the preliminary planning-level construction cost estimate for full septage treatment, including construction of aeration and equalization basins for septage treatment only (excluding the addition of dewatering liquor), and the expansion/modification of the existing septage receiving area to include the removal of rags and debris.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-24
Table 5.14 Septage Treatment Cost Estimate - Level 3 - Full Treatment Item Description Amount
1 Septage Station Modifications
Site and Piping Modifications $324,000
Construct Three (3x) Huber RotaShield Units $1,950,000 2 Septage Transfer Pump Station and Piping $827,600
3 Septage Equalization and Aeration Basins $5,190,000
Subtotal - Direct Costs $8,295,000
4 Contingency (30%) $2,490,000
5 Contractor Markups (General Conditions, Overhead and Profit) (28%) $3,170,000 6 Sales Tax (Based on 50% of the Direct Costs at 8.75%) $475,000 Estimated Construction Cost $14,430,000
If the City decides to continue to accept septage moving forward, then partial or full septage treatment can be implemented as part of the final project completed under Phase 1.
Operating Cost Estimate
In addition to the planning level capital cost estimates, projected annual operations and maintenance (O&M) costs were developed for the Level 3 - full treatment scenario, which includes all the upgrades outlined above. O&M would include power, labor, and an allowance for equipment replacement. The following assumptions were used to develop the annual O&M cost estimate:
$0.25 per kilowatt-hour (kWh) power cost.
550 annual labor hours, $80 per hour.
» Labor hours were included for the additional O&M hours dedicated to the RotaShield units. It was assumed that labor costs for the septage treatment aeration basins would be included in the operating costs of the Phase 1 activated sludge system. Annual equipment replacement costs are 2 percent of the direct capital cost.
The electrical power cost was based on estimates for the power required to operate one RotaShield unit for eight hours per day and one unit for four hours per day, five days per week, plus pumping energy to transfer septage to the equalization and tanks and then to the aeration basins, and blower power to provide aeration air. The total power demand was estimated to be a continuous draw of 20 kWh.
Estimates of the annual O&M costs for the full septage treatment approach (Level 3) are summarized in Table 5.15.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-25
Table 5.15 Preliminary O&M Costs for Septage Treatment - Based on Level 3 Item Annual Cost
Power(1) $45,200
Labor(2) $44,000
Replacement/ Maintenance(3) $64,000
Total $152,200
Notes:
(1) Power estimates for operating Huber RotaShield units, pumping, and aeration basins totaling 20 kWh per hour. (2) Labor hours include the additional labor required for the Huber RotaShield units. Total labor costs for the operation of the full Level 3 facility will be encompassed in Phase 1 expansion operating budgets. (3) Replacement and maintenance costs based on 2 percent of the capital costs of the operating equipment.
Unit Cost Estimate for Septage Treatment
The estimated capital cost for the full treatment approach (Level 3) and the annual O&M cost from Table 5.15 were used to estimate the unit cost of septage treatment. The capital cost estimate from Table 5.14 was amortized over 20 years using an interest rate of 6 percent to obtain the annual payment amount. This value, together with the annual O&M cost, provides an estimate of the annual cost of treatment. The unit cost for treatment was based on a total volume of 11.4 MG of septage, the amount received during the 12-month period of November 2023 to November 2024. This resulted in a unit cost of $0.12 per gallon, as shown in Table 5.16. It should be noted that this cost excludes any further costs associated with septage treatment and handling, such as the cost for final treatment in the activated sludge process for nitrogen removal and a portion of the solids treatment and disposal cost. These costs still need to be developed.
Currently, the City is charging a septage tipping fee of $0.134 per gallon, which is close to the preliminary estimate developed above, and suggests that the City would have to increase the tipping fee to be able to recover sufficient funds from septage receiving to offset the cost of full septage treatment, as long as the annual volume of septage remains about the same as it is currently. In addition, it should be noted that a flat rate of $0.02 per gallon of the septage tipping fee is paid directly to the General Fund, reducing the amount that goes to the Wastewater Fund to cover the cost of treatment. A more detailed analysis of the costs for complete septage treatment will be needed before arriving at a realistic septage tipping fee to cover future treatment costs.
Table 5.16 Preliminary Unit Cost for Septage Treatment - Based on Full Treatment - Level 3 Item Annual Cost
Annual Cost of Capital(1) $1,258,073
Annual O&M Cost(2) $152,200
Total Annual Cost for Septage Treatment $1,410,273
Total Volume of Septage Received per year, MG(3) 11.4
Cost per Gallon to Treat Septage, $/gallon 0.12
Notes:
(1) $14.4 million capital cost estimate for full septage treatment, amortized over 20 years at a fixed interest rate of 6 percent. (2) Includes estimates for power, labor, and maintenance. (3) Based on the annual volume received for November 2023 to November 2024.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-26
No Septage Option
As noted above, the City is considering its options for septage receiving. One option is the “no septage” approach, in which the City would no longer accept septage at the WWTP. Some impacts associated with the “no septage” approach are briefly discussed below.
1. Impacts to the General Fund – The General Fund currently receives $0.02 per gallon for all septage received by the City. If septage dumping ceases, then the General Fund would lose about $228,000 per year based on the current volume of septage received at the WWTP.
2. Impacts to Phase 1 Capital Cost – If septage is no longer received at the WWTP, then there would be no need for the planned improvements in the septage receiving area or the proposed separate treatment system discussed as part of the Level 3 treatment approach. This would reduce the Phase 1 construction cost estimate by about $14.4 million for this single item. In addition, there could be reductions in other areas impacted by the septage load.
3. Impacts to Plant O&M Cost – There would be a reduction in the overall plant O&M cost if septage is no longer received at the plant. The full extent of this has not yet been quantified, but if septage contributes up to 17 percent of BOD5 load, up to 30 percent of the TSS load, and up to 14 percent of the TKN load, as indicated by the septage sampling events discussed earlier, there will be noticeable reductions in O&M costs, specifically in the primary and secondary treatment and solids handling processes.
4. Impacts to Septage Haulers – the City held discussions with some of the major haulers regarding where they might go if the City were to stop accepting septage at the plant. None of the haulers contacted are currently permitted to discharge elsewhere, and the closest alternative would be Bakersfield. Some haulers mentioned they have been unsuccessful in obtaining permission to discharge to WWTPs in the areas where the waste is generated, and if the City closed its gates to septage receiving they would have to either close their operation or raise their rates significantly to deal with longer haulage distances. Overall, the sentiment from the sample of haulers contacted was that if the City did not accept their waste, they would not have a feasible alternative without causing service interruption, significant rate increases for their customers, extreme hardship, or ending operations.
5. Impact on City’s Pretreatment Program – The City spends staff time administering the current septage receiving program associated with reviewing wastewater discharge permit applications and issuing and renewing individual liquid waste hauler discharge permits, assigning and issuing access cards for each permitted vehicle, tracking and managing each discharge event, performing the monthly commercial invoicing, and other administrative and regulatory tasks associated with the program. User Fees are collected for the regulatory administrative tasks associated with the Septage Receiving Program, so revenue would not be collected for those tasks if septage is no longer received at the WWTP. However, this would lessen the burden on the pretreatment program staff by reducing administrative time, allowing them to focus on other pretreatment activities for the City.
Overall, no longer accepting septage at the WWTP is likely to have a positive impact on the performance and stability of the current and future Phase 1 wastewater treatment processes and will reduce the operating costs. However, there would be a negative impact to the haulers themselves, as they might be forced out of business, and there would be a loss of revenue to the General Fund.
VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-27
5.4 Conclusion
This chapter provided an overview and analysis of the sources, quality, and type of septage received by the City at the WWTP. The City is the largest acceptor of septage in Santa Barbara and San Luis Obispo Counties and receives septage from both industrial and domestic haulers.
Four separate sampling events were conducted from September 2024 to August 2025. The results from the sampling events suggest multiple conclusions, including:
Septage constitutes a small portion of total influent flow (around 1.5 percent), but this is a significantly higher percentage than for other typical treatment plants that accept septage. Septage appears to contribute up to 17 percent of influent BOD, up to 30 percent of influent TSS, and up to 14 percent of influent TKN.
The sampling indicates that the anticipated loading from each constituent can be up to 4,200 lb/day of BOD5, up to 7,300 lb/day of TSS, up to 500 lb/day of NH3, and up to 650 lb/day of TKN. Eight major haulers contribute a significant portion of the septage flow and loading into the facility (about 57 percent).
If it is decided to continue accepting septage, then modifications to the existing facilities should be made.
As a part of this process, the City conducted a successful trial of a Huber RotaShield septage screening unit. After this successful trial, an evaluation of alternatives was performed based on this equipment, and cost estimates were developed for three levels of improvement:
Level 1 would improve septage receiving through installation of the Huber RotaShield units, consolidation of the existing receiving areas, and improved removal of rags and coarse debris. Level 2 would incorporate the Alternative 1 improvements and add equalization storage and controlled metering of septage back to the headworks, reducing the magnitude of the short-duration slug loads currently experienced by the treatment process. Level 3 would incorporate the receiving and equalization improvements and provide a dedicated biological treatment process for the high-strength septage prior to returning the treated flow to the Phase 1 activated sludge process.
Based on the historical septage sampling results, the relatively high concentrations of BOD, suspended solids, and nitrogen in the septage stream, and the significant variability associated with individual loads, the City should plan to implement at least Alternative 2. Improved screening under Alternative 1 would provide substantial operational benefits and reduce the amount of coarse material entering the plant, but screening alone would not address the high-strength organic, solids, and nutrient loads associated with the septage. Equalization and controlled metering under Alternative 2 would provide an important minimum level of protection by reducing peak loading and allowing the downstream treatment process to receive the septage load more gradually.
For long-term septage handling and for the planning purposes of this Master Plan, Alternative 3 is recommended. Providing dedicated equalization and biological treatment would give the City greater control over the high-strength septage load, reduce its direct impact on the Phase 1 activated sludge process, and provide greater flexibility to accommodate the variability in septage quantity and quality observed during the sampling program. The proposed system could also be configured to treat other high-strength sidestreams, including centrate or liquor from the solids dewatering process, providing VOLUME 13 / CHAPTER 5: SEPTAGE HANDLING
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5-28
additional long-term operational flexibility. Although Alternative 3 has the highest capital cost, it provides the most complete approach for continued septage acceptance and is considered the alternative that best meets the City's long-term goals for reliable septage handling, protection of the downstream treatment processes, and improved control of influent loading.
The planning-level capital cost estimates range from about $4 million to $14.4 million for the three levels of treatment.
Based on preliminary planning-level capital and O&M cost estimates for the full treatment approach (Alternative 3), the unit cost of septage treatment was estimated to be $0.12 per gallon. This cost is similar to the $0.134 per gallon tipping fee the City currently charges for septage, but excludes any further costs associated with final treatment in the Phase 1 activated sludge process for nitrogen removal, as well as a portion of the solids treatment and disposal costs. These costs still need to be developed and accounted for, but the indications are that the City would need to increase the septage tipping fee to cover the cost of treatment in the Phase 1 process, and cover the $0.02 per gallon, which goes directly to the General Fund.
Should the City decide not to accept septage in the future, this is likely to have a positive impact on the performance and stability of the current and future Phase 1 wastewater treatment processes, and will reduce the operating costs. However, based on preliminary discussions with some of the septage haulers there would be a negative impact on their businesses, as the closest alternative would be Bakerfield which might force them to shut down. An additional negative impact will be the loss of revenue to the General Fund, currently around $228,000 per year.
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX A TERTIARY FILTER PILOT STUDY REPORT
CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Tertiary Filter Pilot Study
FINAL / October 2026
CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
Tertiary Filter Pilot Study
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.
Date: 2026.10.23 07:55:26-07'00'
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/WWTP Tertiary Filter Pilot/Report/Tertiary Filter Pilot Report.docx Contents
SECTION 1 INTRODUCTION 1
SECTION 2 INITIAL STUDIES 1
SECTION 3 PILOT PLANT SETUP AND EQUIPMENT 2
SECTION 4 PILOT TESTING APPROACH 3
SECTION 5 RESULTS 4
5.1 Historical Effluent Quality 4
5.2 Pilot Results 4
5.2.1 Filter Flow and Loading Rate 4
5.2.2 Solids Removal Performance 5
5.2.3 Biochemical Oxygen Demand Removal Performance 7
5.2.4 Backwash Interval and Recovery 7
5.2.5 Impact of Polymer Addition 8
5.2.6 Evaluation of Backwash Water 10
SECTION 6 FILTER SIZING AND COST ESTIMATE 12
6.1 Cost Estimate 13
6.1.1 Planning Level Capital Cost 13
6.1.2 Planning Level O&M Cost 15
SECTION 7 DISCUSSION 15
7.1 Meeting with the Regional Water Board 16
7.1.1 Reduced Solids Loading on the Percolation Ponds 16
7.1.2 A source of Water for In-Plant Use 17
SECTION 8 CONCLUSIONS 18
Attachments
ATTACHMENT A TERTIARY FILTER PILOT TEST PLAN
ATTACHMENT B SANTA MARIA TEMP TERTIARY FILTRATION COST ESTIMATE Tables
Table 1 City of Santa Maria General Order Interim Wastewater Treatment Plant (WWTP) Effluent Limits 1
Table 2 Nexom Pilot Filter Design Criteria 3
Table 3 Full-Scale Tertiary Filter Design Criteria 12
Table 4 Planning Level Cost Estimate for Tertiary Filters 14 Table 5 Planning Level Annual O&M Cost Estimate for Tertiary Filters 15
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Figures
Figure 1 Proposed Site Layout and Backwash Flow Paths for Nexom Filter 2 Figure 2 Nexom Cloth Media Tertiary Pilot Filter 3
Figure 3 Historical Secondary Effluent BOD5 Concentration 4 Figure 4 Variation in Filter Feed Flow Rate 5
Figure 5 Variation in Filter Hydraulic Loading Rate 5
Figure 6 Filtered Effluent TSS and Filter Loading Rate 6 Figure 7 Filter Feed and Effluent Turbidity Variation 6 Figure 8 Feed and Effluent Turbidity Variation 7
Figure 9 Variation in Backwash Interval 8
Figure 10 Variation in Overall Recovery 8
Figure 11 Variation of TSS Removal Before, During, and After ACH Addition 9 Figure 12 Variation of COD Removal by Cloth Filter During Addition of ACH 10 Figure 13 Impact of ACH on Percent Solids Remaining in Backwash Water 11 Figure 14 Visual Impact of High Doses of ACH to Backwash Water After 2 Minutes (Top) and 90 Minutes (Bottom) Settling 11
Figure 15 Impact of Filter Capacity on Effluent BOD5 Concentration 12 Figure 16 Simplified Process Flow Diagram and Preliminary Layout for Tertiary Filters 13 Figure 17 Example Tertiary Filter Installation With Shade Cover 14 Figure 18 Impact of TSS (Cs) on Total Infiltration (S) - from Rice 1974 17
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN iii
Abbreviations
ACH aluminum chlorohydrate
amps amperes
BOD5 biochemical oxygen demand (5-day test)
Carollo Carollo Engineers
City City of Santa Maria
COD chemical oxygen demand
ft feet
ft2 square feet
gpm gallons per minute
gpm/ft2 gallons per minute per square foot
hp horsepower
kWh kilowatt-hour
lb/ft2 pounds per square foot
mg/L milligrams per liter
O&M operations and maintenance
TN total nitrogen
TSS total suspended solids
WWTP wastewater treatment plant
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1
SECTION 1 INTRODUCTION
The City of Santa Maria (City) has been investigating ways to reduce the biochemical oxygen demand (BOD5) and total suspended solids (TSS) of the secondary trickling filter effluent to achieve the interim discharge limits established by its new 2023 General Order. These limits are shown in Table 1, and both BOD5 and TSS are required to meet a 30-day average of 60 milligrams per liter (mg/L) or less. In response to the requirements of the General Order, the City prepared a Time Schedule Compliance Plan (see Volume 2, which includes a copy of the Plan) in June 2024 and requested that the interim limits be extended until June 2033. By this time, it was anticipated that the upgraded treatment facilities would be in operation. If not extended, the new effluent limits of 30 mg/L for both BOD5 and TSS would come into effect after June 16, 2025.
Table 1 City of Santa Maria General Order Interim Wastewater Treatment Plant (WWTP) Effluent Limits Constituent Units Interim Limit per General Order Proposed Interim Dates per Time Schedule Compliance Plan
BOD₅ mg/L 100 (daily maximum)
60 (30-day average)
Until June 2033
TSS mg/L 100 (daily maximum)
60 (30-day average)
Until June 2033
At the time this work was undertaken, the City was investigating methods to achieve or get close to achieving the proposed interim effluent limits, based on direction from the Regional Water Board.
SECTION 2 INITIAL STUDIES
In 2023 and 2024, Carollo Engineers (Carollo) conducted some bench-scale testing on the primary influent stream to assess the effectiveness of various coagulants to reduce the BOD5 concentration in the primary effluent. This testing showed that ferric chloride would be most effective, but the dosage and associated cost would be significant.
Following this work, in March 2024, Carollo investigated adding a coagulant to the secondary trickling filter effluent to determine whether a coagulant could increase the settleability of the solids and improve TSS and BOD5 removal efficiency. Only one coagulant provided some improvement in settleability. To confirm its efficiency, a full-scale trial would be needed, which would be costly, challenging to implement, and could have unintended consequences resulting from the recycling of excess coagulant.
Earlier sampling in December 2023 had shown that a significant portion of the BOD5 in the secondary effluent was associated with solids and that there was quite a lot of soluble BOD5 present. 24-hour composite samples showed an average effluent BOD5 value of 66 mg/L, with an average soluble BOD5 concentration of 18 mg/L, indicating about 73 percent of the BOD5 was associated with the solids fraction.
Laboratory filtration of secondary effluent samples suggested that tertiary filtration may be a suitable approach to further reduce the TSS concentration and, consequently, the BOD₅ concentration. The testing indicated that tertiary filtration of the secondary effluent might be sufficient to reduce the BOD5 to less than 60 mg/L. A detailed evaluation of the performance of the existing plant showed that the trickling
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2
filters are performing as well as can be expected, and although the secondary effluent has an average TSS concentration of 38.6 mg/L (2018 to 2023), the BOD₅ concentration has been above 60 mg/L.
These initial investigations were included in the City's Time Schedule Compliance Plan, which established a milestone (Milestone 1) for the City to meet with the Regional Water Board to discuss the results of tertiary effluent pilot testing to establish whether the BOD5 limit of 60 mg/L could be achieved. This report presents the findings of the pilot testing.
SECTION 3 PILOT PLANT SETUP AND EQUIPMENT
In July 2024, Carollo developed a Tertiary Filter Pilot Test Plan that outlined an approach to testing to assist the City in conducting the pilot. The Test Plan is included in Attachment A.
Figure 1 presents an overview of the site arrangement for the pilot testing. The City contracted with Nexom US (Nexom) to provide the tertiary filter pilot unit.
Figure 1 Proposed Site Layout and Backwash Flow Paths for Nexom Filter
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 3
Table 2 presents the performance design criteria for the cloth filter unit.
Table 2 Nexom Pilot Filter Design Criteria
Description Value Units
Influent Flow 600-800 gpm at 20 ft of head
Filter Head Loss 24 inches
Maximum Filter Area 108 ft2
Cloth Media Pore Size 10 micron
Backwash Flow 80 gpm
Backwash Cycle 5-15 minutes
Max Hydraulic Loading 3.5 - 4.5 gpm/ft2
Max Solids Loading 3 lb/ft2.d
Notes:
amps - amperes; ft - feet; ft2 - square feet; gpm - gallons per minute; gpm/ft2 - gallons per minute per square foot; lb/ft2.d- pounds per square foot per day
SECTION 4 PILOT TESTING APPROACH
Nexom delivered the pilot filter to the site and provided the mechanical and electrical hook-up required.
Once the pilot unit was operational, the City took over the day-to-day operation. The pilot filter operated from December 2024 through April 2025. Figure 2 shows a photograph of the trailer-mounted unit.
Figure 2 Nexom Cloth Media Tertiary Pilot Filter
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4
SECTION 5 RESULTS
5.1 Historical Effluent Quality
Figure 3 shows the WWTP effluent BOD5 concentration variation from October 2023 through December 2024, indicated as individual data points sampled weekly, as well as the running average. The figure also shows the 30-day average limit (60 mg/L) and the maximum daily limit (100 mg/L), per the Interim Discharge Limits presented in Table 1. As shown, historically, the effluent BOD5 has remained in the range of 60 to 100 mg/L. A few samples have been recorded below 60 mg/L, and three individual samples have been above 100 mg/L.
Figure 3 Historical Secondary Effluent BOD5 Concentration
5.2 Pilot Results
5.2.1 Filter Flow and Loading Rate
Figure 4 presents the variation in filter flow rate for the pilot testing period. As shown, the feed flow ranged from 370 gpm to 470 gpm. This corresponded to filter hydraulic loading rates of between 3.5 and
4.5 gpm/square foot, as shown in Figure 5.
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5
Figure 4 Variation in Filter Feed Flow Rate
Figure 5 Variation in Filter Hydraulic Loading Rate
5.2.2 Solids Removal Performance
The 10-micron cloth filter achieved an average of 38 percent removal of TSS and produced a filtered effluent with an average TSS concentration of around 17 mg/L, well below the interim limit. Figure 6 presents the TSS data plotted together with the filter solids loading rate. The influent stream to the filter had average TSS concentrations of 30.9 mg/L with minimum and maximum values of 8.4 and 57.2 mg/L, respectively. As shown in Figure 6, the TSS removal efficiency did not seem to be significantly impacted by the filter loading rate. The TSS removal efficiency was 38 percent, and effluent TSS ranged between 14 and 28 mg/L for the composite samples.
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 6
Figure 6 Filtered Effluent TSS and Filter Loading Rate
Turbidity measurements of the influent and effluent were made regularly throughout the pilot period.
These are plotted in Figure 7 and show that generally the filter was able to reduce the turbidity to about half of the feed value. The trend lines indicated a general increasing trend in the filter feed effluent, and a corresponding increase in the effluent turbidity. Again, there does not appear to be a relationship between effluent turbidity and filter loading rate.
Figure 7 Filter Feed and Effluent Turbidity Variation
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 7
5.2.3 Biochemical Oxygen Demand Removal Performance
A filtered effluent BOD5 of less than 60 mg/L was generally achieved. Figure 8 shows both grab samples (on the left) and 24-hour composite samples (on the right). Grab samples were collected during the daytime and generally resulted in lower concentrations, particularly for the feed stream. Since the composite samples are more representative of what the filter effluent would be, these values were used in the analysis. The composite samples indicate that the filter feed BOD5 varied between a minimum of 51.5 and a maximum of 90 mg/L, while the filter effluent BOD5 was in the range of 31.1 to 71 mg/L, but the majority of samples showed BOD5 of less than 60 mg/L. The average filter feed BOD5 for the composite samples was 74 mg/L, and the effluent was 48 mg/L. The average BOD5 removal efficiency was around 35 percent, but there was wide variability, ranging between 4 and 63 percent.
Figure 8 Feed and Effluent Turbidity Variation
5.2.4 Backwash Interval and Recovery
The backwash frequency impacts the overall recovery of the filter. The backwash interval was typically in the 5 to 15-minute range, but it varied throughout the testing period, as shown in Figure 9. However, even when the unit was backwashing every 5 minutes, the overall recovery was still high, well above 90 percent, as shown in Figure 10.
Grab Samples Composite Samples
Average
Average
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 8
Figure 9 Variation in Backwash Interval
Figure 10 Variation in Overall Recovery
5.2.5 Impact of Polymer Addition
To assess the impact of polymer addition on TSS and BOD5 removal, aluminum chlorohydrate (ACH) was dosed at concentrations of 1, 5, and 10 mg/L to the filter feed stream. This polymer was tested during the bench-scale work that was mentioned earlier and was found to be the only one that appeared to have the ability to coagulate the trickling filter effluent solids. Figure 11 shows the variation of the percentage TSS removal before, during, and after the addition of the coagulant. The figure also illustrates the variation in
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 9
filter loading rate. Each dose of the ACH was continued for one week. As shown in the figure, the TSS removal varied between about 20 and 70 percent in the period before polymer addition, and this variation continued during the polymer addition at all three dosages tested. Overall, there was no noticeable improvement in TSS removal with the addition of ACH.
Figure 11 Variation of TSS Removal Before, During, and After ACH Addition To assess the change in BOD5 before, during, and after ACH addition, chemical oxygen demand (COD) measurements were used. The results are shown in Figure 12, and as indicated, the addition of ACH at the three dosages had no noticeable impact on COD removal either, which stayed constant at around 10 percent for the entire period.
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 10
Figure 12 Variation of COD Removal by Cloth Filter During Addition of ACH
5.2.6 Evaluation of Backwash Water
An important consideration for the pilot testing was the quality and quantity of backwash water that would be produced by the filter, and where in the WWTP such a stream would be directed if a full-scale project were implemented.
As mentioned above (Figure 10), the recovery level for the pilot filter was high, typically between 92 and 97 percent. Thus, the flow rate of backwash water would not be expected to be significant. However, if the solids in the backwash water cannot be removed from the system, they will circulate back to the trickling filters and gradually build up over time, potentially creating operational issues and leading to higher effluent TSS concentrations. To evaluate the settleability of the solids in the backwash, the City conducted some further bench tests using ACH.
The testing determined that without the addition of ACH, only about 60 to 65 percent of the solids settled, leaving a large portion that does not settle and could potentially recirculate. When ACH was dosed at up to 50 mg/L to the backwash water, there was little to no improvement in the percentage of solids that settled. However, at a dose of 100 mg/L, more than 85 percent of the solids settled. This increased to more than 95 percent, settling at a very high dose of 300 mg/L. The results are summarized in Figure 13.
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 11
Figure 13 Impact of ACH on Percent Solids Remaining in Backwash Water Figure 14 shows a photograph of the settling tests in the laboratory for the high ACH doses, indicating the improvement after 2 minutes (top) and 90 minutes (bottom) of settling. Clearly, these results indicate that ACH addition can help with settling the solids in the backwash water, although the dosages are high.
Figure 14 Visual Impact of High Doses of ACH to Backwash Water After 2 Minutes (Top) and 90 Minutes (Bottom) Settling
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 12
SECTION 6 FILTER SIZING AND COST ESTIMATE
The pilot testing has determined that removal of around 30 percent of the BOD5 in trickling filter effluent can be achieved with a nominal 10-micron tertiary cloth filter. To establish the capacity of a full-scale installation that would be needed to reduce the effluent BOD5 to less than 60 mg/L, some design criteria were established from the pilot testing. These are shown in Table 3.
Table 3 Full-Scale Tertiary Filter Design Criteria
Description Value
WWTP Effluent Flow, mgd 6 - 7
Filter Influent BOD5, mg/L 74
Filter Effluent BOD5, mg/L 48
ACH Addition to Filter Influent No
ACH Addition to Backwash Water Yes - 100 - 150 mg/L
Backwash Cycle, min 5
Max Hydraulic Loading, gpm/ft2 3.5
Max Solids Loading, lb/ft2.d 3
The pilot results show that if all the flow leaving the trickling filters is filtered, the resulting BOD5 concentration would be below 50 mg/L. However, if a partial-treatment approach were used, where most of the flow is filtered and the unfiltered portion of the flow is blended with the filtered portion, then it should still be possible to achieve the desired 60 mg/L for BOD5. Figure 15 illustrates the partial treatment approach for a scenario in which the plant effluent flow rate is 6.5 mgd. If, for example, the filter capacity is 3.5 mgd, and 3.0 mgd bypasses the filter, the effluent BOD5 of 60 mg/L should be met, but there would be no safety factor.
Figure 15 Impact of Filter Capacity on Effluent BOD5 Concentration
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 13
On the other hand, treating 5.0 mgd through the filter should produce a combined effluent BOD5 concentration of around 54 mg/L, which provides a 10 percent safety factor to account for variations in flow and concentration. The combined effluent would be expected to have a TSS value of around 20 mg/L.
6.1 Cost Estimate
Based on the above, a capital and operations and maintenance (O&M) cost estimate was developed for the construction and operation of a partial-filtration system with a nominal capacity of 5.0 mgd. Figure 16 presents a simplified process flow diagram and a preliminary layout showing the proposed location of the tertiary filters and arrangement of the major piping runs.
Figure 16 Simplified Process Flow Diagram and Preliminary Layout for Tertiary Filters
6.1.1 Planning Level Capital Cost
The new filters would be located just south of the existing Percolation Pond Pump Station structure and would receive flow from the distribution box just upstream. New transfer pumps would be provided to lift the effluent to the filters, which would be located on a concrete slab under a shade canopy. An example installation is shown in Figure 17. Filtrate from the filters would be returned to the Percolation Pond Pump Station, from where it would be distributed to the existing and proposed new percolation ponds. The backwash water from the filter, up to 280 gpm, would be directed to just downstream of the existing grit chamber, where the flow distribution to the primary clarifiers occurs. This stream would receive a dose of ACH in a mixing tank located near the filters before being pumped to the grit chamber area. Settled solids would be captured in the primary clarifiers and pumped to the anaerobic digesters.
Quotations were obtained from two cloth filter manufacturers, Nexom and Aqua-Aerobics, for the equipment that would be needed. The cost includes installing two filters, each 2.5 mgd capacity, on a concrete slab under a shade canopy (Figure 17). Although the tertiary filters would be a "temporary" facility and not needed once the Phase 1 project is completed, the installation would need to operate until
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 14
the end of 2033, approximately 8 years from now. For the cost estimate it was therefore assumed that this would be a fully functional tertiary filter installation.
Figure 17 Example Tertiary Filter Installation With Shade Cover A summary of the planning level cost estimate (Class 5) is shown in Table 4. A more detailed table showing the breakdown of the Direct Costs is included in Attachment B. As indicated in Table 4, the construction cost is estimated to be a little over $7 million, with a total project cost, including engineering design and construction support etc., of almost $9 million.
Table 4 Planning Level Cost Estimate for Tertiary Filters Item Description Amount
1 Tertiary Cloth Filters
- Site Construction $264,000
- Concrete Work $196,000
- Steel Canopy Structure $281,000
- Cloth Filters, Pumps, Backwash Chemicals, etc. $2,031,000 - Mechanical $361,000
Subtotal $3,133,000
2 Electrical (20%) $627,000
3 Instrumentation and Controls (10%) $313,00
Subtotal - Direct Costs $4,073,000
4 Contingency (30%) $1,222,000
5 Contractor Mark-ups (General Conditions, Overhead and Profit) $1,556,000 6 Sales Tax $232,000
Estimated Construction Cost $7,083,000
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 15
Item Description Amount
7 Engineering (Design and Construction Support) (17%) $1,204,000 8 Legal, Admin, and Regulatory Costs $637,000
Total Project Cost Estimate $8,924,000
6.1.2 Planning Level O&M Cost
To estimate the anticipated O&M costs for a new tertiary filtration facility, estimates were made for electrical power use and chemical use. For electrical power, the major areas would be for the new filter feed pumps, which were assumed to require 15 feet of lift, and the backwash water return pumps, which would require about 10 feet of lift. Electrical power costs were assumed to be $0.25/kilowatt-hour (kWh).
The major chemical cost would be for ACH to be added to the backwash water to help with coagulation and settling. There will also be added O&M associated with the additional solids that will settle in the primary clarifiers and be processed in the anaerobic digesters. These solids will add to the load on the sludge drying beds and the mass of solids hauled from the site. Solids disposal costs were based on the values presented in Volume 8 and assume 70 percent solids and a 75:25 percent split between disposal to Engle and Grey and the City's landfill. Table 5 presents a summary of the O&M cost.
Table 5 Planning Level Annual O&M Cost Estimate for Tertiary Filters Item Description Amount
Annual Cost
Comments
1 Electrical Cost(1)
- Filter Feed Pumps $33,800 3,500 gpm @ 15 ft
- Backwash Transfer Pumps $1,800 280 gpm @ 10 ft
- Tertiary Filters (drive and backwash pump) $9,800 About 5 hp combined 2 Chemicals
- ACH in Backwash(2) $137,000 100 mg/L dosage
3 Solids
Estimate for additional Solids Disposal (11 wet tons/month)(3) $4,200 Assumes 15,600 lb/month DS Total O&M Cost Estimate $186,600
Notes:
hp - horsepower
(1) Assuming $0.25/kWh.
(2) 100 mg/L and 150 mg/L almost provide the same performance, and lower dose saves $60,000. (3) Based on 75:25 split at $33.61 and $26.63 per wet ton (=>$31.9).
SECTION 7 DISCUSSION
Construction of a new $9 million tertiary filtration facility that does not have a need once the Phase 1 construction is completed in 2033 seems like an additional unnecessary burden that the City will need to carry should the Regional Water Board request that the tertiary facilities be constructed.
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 16
7.1 Meeting with the Regional Water Board
At a meeting held with the Regional Water Board on November 19, 2025, the results from the pilot testing were presented and discussed. It was noted that based on the results, the City would need to filter about 80 percent of the secondary trickling filter effluent (~ 5 mgd) and blend it with the remaining flow to produce a combined effluent BOD5 less than 60 mg/L.
The City had looked into long-term rental of tertiary filter equipment and it was determined that this approach would probably not be feasible since the City would pay for the equipment several times over.
The planning level cost estimate to purchase and install a 5-mgd tertiary filtration system was noted as being $9 million (2025). And the annual electrical, chemical, and solids disposal costs were expected to total around $190,000.
In addition, it was noted that the City was concerned about potential unintended consequences associated with adding a new process (partial tertiary filtration) to the treatment train. For example, it was not clear what the long-term impact of adding polymer to the backwash water might be, given the high recirculation rates associated with the current trickling filter treatment process. Also, allowing time for design and construction and the supply chain issues with electrical equipment it was estimated that a new tertiary filtration system would only be expected to be in operation in 2029, which means there would be limited effluent quality benefits prior to the upgraded plant coming into operation. Furthermore, the $9 million (2025) cost was an unplanned capital expenditure for the City, which is already having to find funds to pay for the approximately $500 M main project.
The Regional Water Board acknowledged that the $9 M cost estimate was significant.
It was also pointed out that during the course of the pilot work and development of materials for the master plan, the City had recognized the long-term benefit of incorporating tertiary filtration for the main project, for two main purposes:
As a means to protect/enhance the performance of the percolation ponds, by minimizing the amount of solids discharged to the ponds. The City will be undertaking maintenance work on all of the ponds to remove fine material that has built up over many years of operation, and this is a costly exercise. To provide a source of recycled water that can be used for in-plant use, thereby avoiding the additional of an external water source that would need to be percolated.
Each of the above is discussed in more detail in the following sections.
Despite the above long-term benefits, the City was of the opinion that a temporary filtration solution to address BOD5 introduces complications within the plant with parallel projects and sequencing of work and hinders progress and dilutes the focus on the main larger project. The Regional Water Board acknowledged the work that had been done and agreed that the task set out in the Time Schedule Compliance Plan that included studies by the City for interim BOD5 and TSS compliance was complete.
7.1.1 Reduced Solids Loading on the Percolation Ponds
During the pilot testing, the secondary treated trickling filter effluent had an average TSS concentration of around 30 to 35 mg/L. At an effluent flow rate of 6.5 mgd, this represents a load of about 52,000 lb/month of solids to the ponds, or almost 310 tons per year. Cleaning the ponds by removing, washing, and replacing the sand is a costly operation. Volume 7, Chapter 2 of the Master Plan
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 17
recommended that the City budget to spend $23 million over a 5-year period to rehabilitate the ponds and that this be repeated every 10 to 15 years as percolation rates decline.
Yeh and Associates noted the impact of suspended solids on infiltration in their geotechnical analysis of the ponds. Figure 18 is taken from their report that shows a curve developed by Rice in 1974, and indicates the low infiltration rate, indicated by the pink arrow, at a TSS value of 41 mg/L, which was the average effluent TSS reported by the City in 2023. The figure also includes a black arrow at 20 mg/L (point "A"), which would be the anticipated TSS blend downstream of the filters, and the arrow at point "B" is the anticipated TSS in the effluent from the secondary clarifiers after Phase 1 is complete, between 5 and 10 mg/L. Based on the curve in Figure 18, a change in TSS from 41 to 20 mg/L would more than double the infiltration value. And the water quality from the Phase 1 facility would more than triple the infiltration value compared to point "A".
Figure 18 Impact of TSS (Cs) on Total Infiltration (S) - from Rice 1974 In terms of mass of solids, the tertiary filters, with a TSS concentration of about 20 mg/L, would reduce the solids load by about 30 percent, to 200 tons per year. And when the Phase 1 project comes online, the solids load on the ponds would be halved to less than 100 tons per year.
The City is planning to construct new percolation ponds, which are expected to be operational in about 3 years. These ponds will receive effluent from the existing WWTP for about 6 years before the Phase 1 process is fully operational. Providing tertiary-treated effluent to the new ponds would be expected to provide a benefit in terms of the reduced solids load and any impacts on percolation caused by fine organic solids. The financial benefit has not been determined.
7.1.2 A source of Water for In-Plant Use
Recently, the City completed a project to bring City water to the WWTP, which is now used as in-plant utility water. Prior to that, the WWTP used a local on-site groundwater well to provide utility water.
B
A
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 18
Approximately 800,000 gallons per month are currently being used; 18.5 gpm on average. When the Phase 1 project comes online, the plant's water use is expected to be significantly greater. Major usage will occur in the new aeration basins for foam/scum control, and in the solids thickening and dewatering steps for removing solids from the drums or belts, together with other minor use around the plant. This is discussed in more detail in Volume 13, Chapter 1.
The tertiary filters can be used to provide flow for a new utility water system. This would consist of a disinfection step, likely using chlorine, some storage capacity, a pump station, and a utility water distribution system. Based on the initial estimates, not all of the anticipated 5 mgd filtration capacity would be needed.
SECTION 8 CONCLUSIONS
The City completed a five-month tertiary filter pilot test, and based on the analysis of the data, the following conclusions can be made:
1. Tertiary cloth filters with a 10-micron nominal pore size can effectively treat the secondary trickling filter effluent and reduce the BOD5 and TSS concentrations.
2. The pilot filter, operating at a flowrate of between 370 and 470 gpm was able to achieve an overall recovery of between 92 and 97 percent.
3. The filter operated at hydraulic loading rates of between 3.5 and 4.5 gpm/sf, and the loading rate did not seem to impact either BOD5 or TSS removal efficiency.
4. Thirteen 24-hour composite samples of the filtered effluent collected between February and April 2025 showed that the BOD5 concentration could be reduced to less than 60 mg/L.
5. An aluminum-based polymer (ACH) added to the filter feed stream at dosages of 1, 5, and 10 mg/L did not improve either BOD5 or TSS removal efficiency.
6. Dosages of ACH of up to 50 mg/L could not increase the solids settleability in the filter backwash water. However, above 100 mg/L, good improvement in settleability was observed.
7. An analysis showed that filtering 5 mgd of the secondary trickling filter effluent and blending the remaining untreated flow (1.5 mgd) would produce an effluent with a BOD5 concentration of approximately 54 mg/L, providing about a 10-percent safety factor below the 60 mg/L interim limit to allow for flow and water quality variations.
8. The planning level total project cost estimate (Class 5) for a 5 mgd tertiary filtration system is $8.9 million (2025).
9. Operationally, the 5 mgd tertiary filtration system is expected to cost about $187,000 per year to operate. This cost includes the expected electricity use, additional solids disposal, and more than 70 percent of the cost would be for polymer addition to the backwash water. The polymer dose could potentially be lowered during actual operation given the long detention time in the primary clarifiers, which would reduce the anticipated O&M costs. The O&M costs do not include typical wear and tear costs for the filtration system.
10. In addition to providing the filtration system to meet the interim BOD5 effluent limit, the filters would offer additional benefits. First, they would reduce the organic solids load on the new and existing
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 19
ponds, thereby preserving the percolation rate (particularly for the new ponds). Second, once Phase 1 is in operation, a portion of the filter capacity could be retained for providing flow for a new utility water system for the WWTP.
11. The City sees the value in long-term use of tertiary filtration for the main project, but installing a temporary filtration system introduces complications and only provides limited effluent quality benefits for the cost. Therefore, the best use of resources would be to build filtration into the main Phase 1 project rather than provide an interim solution.
12. The Regional Water Board agreed that the studies to be performed by the City for interim BOD5 and TSS compliance (Task 1) were complete. Therefore, a temporary filtration system to reduce BOD5 and TSS would not be needed.
TERTIARY FILTER PILOT STUDY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
ATTACHMENT A TERTIARY FILTER PILOT TEST PLAN
CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
TECHNICAL MEMORANDUM
Tertiary Filter Pilot Test Plan
FINAL / October 2026
CITY OF SANTA MARIA
Wastewater Treatment Plant Master Plan
TECHNICAL MEMORANDUM
Tertiary Filter Pilot Test Plan
FINAL / October 2026
Digitally signed by Graham J.G. Juby
Contact Info: Carollo Engineers, Inc.
Date: 2026.10.21 18:23:23-07'00'
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN i
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/WWTP Tertiary Filter Pilot Sampling Plan/TM_TertiaryFilterPilotTestPlan.docx Contents
SECTION 1 PURPOSE AND OBJECTIVES 1
1.1 Project Team 1
1.2 Project Goals 1
SECTION 2 BACKGROUND 2
SECTION 3 DESCRIPTION OF WORK TASKS 2
3.1 Coordination of Rental Unit and Set Up 2
3.1.1 Electrical Requirements 3
3.1.2 Grading/Site Requirements 3
3.1.3 Pumping/Piping Requirements 3
3.2 Pilot Plant Operation 5
3.2.1 Commissioning and Start-up 5
3.2.2 Phase 1 Operation – Initial Filter Loading Tests 5
3.2.3 Phase 2 Operation – Continuous Operation (No Chemicals) 6
3.2.4 Phase 3 Operation – Filtration Optimization (With Chemicals) 7
3.3 Sampling Plan 8
SECTION 4 MONITORING AND SAMPLING PLAN 9
Appendices
APPENDIX 1 NEXOM UNIT DRAWINGS
APPENDIX 2 DAILY LOG SHEET
APPENDIX 3 NEXOM EXAMPLE BROCHURE FOR TRAILER PILOT UNIT Tables
Table 1 Nexom Package Filter Specifications 4
Table 2 Filter Loading Rate Evaluation 6
Table 3 Preliminary Approach for Backwash Water Jar Testing 7 Table 4 Monitoring and Sampling Plan 9
Figures
Figure 1 Proposed Site Layout and Backwash Flow Paths for Nexom Filter 4
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN ii
Abbreviations
ACH aluminum chloralhydrate
amps amperes
BOD5 5-day biochemical oxygen demand test
Carollo Carollo Engineers
City City of Santa Maria
COD chemical oxygen demand
ft feet
ft2 square feet
gpm gallons per minute
gpm/ft2 gallons per minute per square foot
lb/ft2 pounds per square foot
mg/L milligrams per liter
N/A not applicable
NTU nephelometric turbidity unit
PLC programmable logic controller
Title 22 California Code of Regulations Title 22
TOC total organic carbon
TSCP Time Schedule Compliance Plan
TSS total suspended solids
Water Board Central Coast Regional Water Quality Control Board WWTP wastewater treatment plant
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 1
SECTION 1 PURPOSE AND OBJECTIVES
This technical memorandum outlines the recommended tertiary filter pilot test plan for the City of Santa Maria (City) Wastewater Treatment Plant (WWTP). The pilot test plan sets out the proposed testing phases to gather data to assess the performance of the cloth filter on the secondary trickling filter effluent. The City is working towards reducing the 5-day biochemical oxygen demand test (BOD₅) concentration in the WWTP effluent to below 60 milligrams per liter (mg/L) which is the current interim discharge limit.
Currently the trickling filter effluent is not able to meet the 60 mg/L limit. Data collected during the pilot study will be used to assess the feasibility of using a tertiary filtration step as a tool for the City to reach its permitted discharge requirements.
The pilot testing will be conducted over three months, beginning around August 1, 2024.
1.1 Project Team
The team of engineers and companies for this pilot project is as follows:
Project manager - Carollo Engineers (Carollo).
Host agency – City of Santa Maria.
Vendor equipment providers:
» Nexom – cloth filter and required accessories.
1.2 Project Goals
The project aims to operate a package cloth filter furnished by Nexom Inc, downstream of the existing secondary trickling filter system to achieve the following goals: The overarching objective is to reduce total suspended solids (TSS) and BOD₅ concentrations to the new discharge limits provided by the Central Coast Regional Water Quality Control Board (Water Board) as part of the ongoing Time Schedule Compliance Plan (TSCP). Other objectives for this project include:
1. Establish appropriate operating criteria for the tertiary filter:
a. Filter loading rate.
b. Backwash frequency.
c. Overall recovery.
2. Establish the TSS and BOD₅ removal efficiency achieved by the tertiary filter. Understand how the TSS and BOD₅ removal efficiency is impacted by the filter loading rate.
3. Establish the most appropriate method to deal with backwash water from the filter:
a. Return to the grit basins.
b. Return to the secondary trickling filter system.
c. Return to the intermediate clarifier for settling.
4. Establish whether coagulants are needed to assist with the filtration process.
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 2
SECTION 2 BACKGROUND
The City is currently undergoing a master planning effort to upgrade its existing WWTP in order to comply with updated permit requirements. Currently, the treatment plant utilizes trickling filters as the secondary treatment process. A detailed evaluation of the performance of the existing plant has shown that the trickling filters are performing as well as can be expected, and although the secondary effluent has an average TSS concentration of 38.6 mg/L (2018 to 2023), the BOD₅ concentration has been above 60 mg/L.
The Water Board has encouraged the City to explore alternatives to improve the secondary effluent quality and reduce the BOD₅ to below the interim limit of 60 mg/L.
Laboratory filtration of secondary effluent samples indicated that tertiary filtration may be a suitable approach to reduce the TSS concentration further and thereby reduce the BOD₅ concentration.
In June, 2024, per the requirements of the City’s new General Order, the City submitted a TSCP to the Water Board. The TSCP sets out a phased approach to reducing the BOD₅ concentration to below the interim limit of 60 mg/L. Conducting a tertiary filter pilot test and assessing the suitability of tertiary filtration to achieve the BOD₅ limit is the first step. Per the TSCP, the City is required to meet with the Water Board in December 2024 to discuss the results of the tertiary filter pilot study. If the results are found to be satisfactory then the City could implement a larger scale tertiary filtration process.
The implementation of a tertiary cloth filter downstream of existing secondary treatment processes is anticipated to improve TSS and BOD₅ effluent quality. Cloth filters utilized as a tertiary polishing step have been a reliable technology for removal of BOD₅ and TSS wastewater treatment plants around the world.
Nexom Inc, is the selected manufacturer for the pilot filter; they provide rental units that can be installed on a temporary basis to assess the treatment outcomes on City effluent.
The rental filter unit, in conjunction with this sampling and testing plan, may result in improved outcomes, and allow for compliance with the new interim effluent discharge limits.
SECTION 3 DESCRIPTION OF WORK TASKS
There are four major tasks in this project, each of which are described in this section.
3.1 Coordination of Rental Unit and Set Up
The goal of this task is to set up the pilot equipment at the City's WWTP. The City, Carollo, and Nexom Inc, are currently coordinating electrical, grading, power, and piping requirements for the package cloth filter pilot. The City has received a proposal and price quotation from Nexom for a fully integrated pilot skid that can treat up to about 800 gallons per minute (gpm). The City will contract with Nexom for the pilot equipment and the sampling work to FGL laboratories. Wastewater operators onsite will assist in collection and distribution of samples to the laboratory.
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 3
3.1.1 Electrical Requirements
The City has identified existing conduits that can be used to provide the required power to the area that the pilot filter will be located; close to one of the existing secondary clarifiers. The City will take care of providing any additional breakers in the motor control center and the cable for the power supply.
3.1.2 Grading/Site Requirements
Some slight grading will be needed to level that area where the 40-foot package pilot unit will be located.
There is sufficient space near one of the secondary clarifiers to locate the unit.
3.1.3 Pumping/Piping Requirements
Feed pumps (three) for the secondary effluent will be located in the secondary clarifier effluent launder.
Nexom will provide the pumps and the piping needed to convey the feed water to the tertiary filter.
Filtered effluent from the pilot will be directed to the percolation ponds with the rest of the secondary effluent. Backwash from the pilot filter will be initially directed to the secondary trickling filter pump station. The best location for the backwash water will be investigated as part of the study. The other locations to be investigated are:
1. Sludge drying bed, from where the flow can be returned to the grit chamber.
2. Primary trickling filter pump station.
3. Intermediate clarifier.
Appendices 1 and 3 show the pilot unit drawings and the associated brochure.
The cloth filter itself is fitted with on-line turbidimeters that continuously record the nephelometric turbidity unit (NTU) of the feed and filtrate. Data from the on-line analyzers will be stored in the pilot programmable logic controller (PLC). The effluent/filtrate line is fitted with a low range turbidimeter that is a self-cleaning unit. On the feed water side where the turbidity is higher, there will be a higher range probe type analyzer that has a range of 4 NTU to 100 NTU.
The pilot rental package includes submersible pumps, backwash pumps, and chemical pumps for the addition of coagulants. Coagulant testing may be tested, depending on the Baseline filter performance, discussed further below. The existing chemical day tanks in the pilot filter will be filled with sufficient chemical for testing, as needed.
It is anticipated that the pilot unit will be set up and commissioned by Nexom in late July 2024.
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 4
Figure 1 Proposed Site Layout and Backwash Flow Paths for Nexom Filter The Nexom filter has the following performance criteria:
Table 1 Nexom Package Filter Specifications
Description Value Units
Influent Flow 600-800 gpm at 20 ft of head
Filter Head loss 24 inches
Maximum Filter Area 108 ft2
Cloth media pore size 5 or 10 micron
Backwash Flow 80 gpm
Backwash Cycle 5-15 minutes
Max hydraulic loading up to 10 gpm/ft2
Max Solids Loading 3 lb/ft2.d
Electrical Requirements 40-50 amps
Notes:
amps - amperes; ft - feet; ft2 - square feet; gpm/ft2 - gallons per minute per square foot; lb/ft2 - pounds per square foot
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 5
3.2 Pilot Plant Operation
The pilot testing is anticipated to last for three months: August, September and October 2024.
The operational sequencing of the pilot filter will be critical to ensure applicable results. Float switches in the filter unit will determine when the filter is backwashed and the feed pumping rate based on filterability.
The WWTP’s regular working hours are from 7:30 a.m. to 4:30 p.m. Monday through Friday. During the initial set up the pilot filter will be operated during regular working hours, but once the City has confidence in the equipment it will be set to run continuously. An integrated control system and human machine interface panel will be used to set the operating parameters. Operators will record the daily set points for feed flow and backwash rate on a Daily Log Sheet – see Appendix 2. The Daily Log Sheet will also record values for feed and effluent turbidity, flow rates, head loss, and backwash intervals. This information will be tracked and consolidated in a reporting matrix.
Sample collection and analysis of the liquid streams will occur regularly throughout the pilot testing period, as outlined below and in Section 4.
The following phased operation of the pilot filter is planned.
3.2.1 Commissioning and Start-up
Nexom will be on-site for the commissioning and start-up of the pilot unit once it has been mechanically plumbed and the power supply provided.
It is anticipated that this period will last approximately including time for troubleshooting, if needed.
3.2.2 Phase 1 Operation – Initial Filter Loading Tests
The Phase 1 Initial Filter Loading tests are anticipated to last for 1 week. The purpose of this phase of the study is to determine what a reasonable feed flowrate and backwash frequency is for the secondary trickling filter effluent. Trickling filter secondary effluent tends to perform differently, in terms of filterability, compared with typical activated sludge secondary effluent. The California Code of Regulations Title 22 (Title 22) requirements for the Nexom tertiary cloth filters show a maximum loading rate of
10.0 gpm/ft2. The Santa Maria plant is not aiming to produce Title 22 quality effluent for reuse, but the Title 22 loading rate provides an indication of a rate that the State of California feels is sustainable. The purpose of this phase of testing is to determine an initial loading rate for the filter.
The pilot filter will be operated at a series of “conditions” outlined in Table 2, to determine which set of conditions works most favorably. For each “condition” a filter loading rate has been selected. Each loading rate corresponds to a specific feed flow rate. It is anticipated that as the filter loading rate increases (from Condition 1 to Condition 3), so the backwash frequency may increase. Condition 1 is set with a low loading rate (4.0 gpm/ft2) as an initial check to confirm that such a rate is achievable with the plant effluent quality. The most favorable conditions will be those at which the filtration rate can be as high as possible and the backwash frequency can be as low as possible; that is the maximum time of 15 minutes which is the current limit set by Nexom. This will minimize the backwash volume that the plant has to deal with.
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 6
For this testing the filter will be operated on a daytime basis only. For each “condition” the filter will begin operation at the start of the day (say around 8:00 a.m.) and the objective will be to keep the filter operating at the selected operating condition for the remainder of the day (until around 4:00p.m.). Once the pilot is operating the PLC will record the feed and filtrate flowrate and turbidity and the filter head loss. One grab sample of the feed and filtrate stream will be collected each day for analysis in the plant laboratory for TSS and chemical oxygen demand (COD) or total organic carbon (TOC), if possible.
Table 2 Filter Loading Rate Evaluation
Description
Filter Hydraulic
Loading Rate
(gpm/ft2)
Feed Flow
(gpm)
Backwash
Frequency
(minutes)
Comments
Condition 1 4.0 432 Can 15 min be
achieved?
Record Filter Headloss with time; record feed and
filtrate flow and NTU continuously; take one sample
for COD and TSS.
Condition 2 5.0 540 Can 15 min be
achieved?
Record Filter Headloss with time; record feed and
filtrate flow and NTU continuously; take one sample
for COD and TSS.
Condition 3 7.0 756 Can 15 min be
achieved?
Record Filter Headloss with time; record feed and
filtrate flow and NTU continuously; take one sample
for COD and TSS.
Condition 4 TBD TBD TBD Record Filter Headloss with time; record feed and filtrate flow and NTU continuously; take one sample
for COD and TSS.
Notes:
TBD - to be determined
After completion of Condition 3, the performance results for all three Conditions will be assessed. Based on the results a filter loading rate and a target backwash frequency will be selected for Condition 4. The filter will be operated at Condition 4 to confirm that performance can be met.
3.2.3 Phase 2 Operation – Continuous Operation (No Chemicals) Phase 2 is anticipated to last for a minimum of 2 weeks and will build on the results/performance of Phase 1. If the filter met the performance criteria during the Condition 4 from Phase 1 testing and performed well, the pilot filter filtration system will be set up to operate at similar conditions during Phase 2 testing. During Phase 2 the filter will be switched to 24-hour operation. The objective will be to keep the filter operating and confirm that the chosen loading rate and backwash frequency is sustainable.
Samples of feed and filtrate will be collected daily for BOD₅ and TSS analysis. Turbidity will continue to be recorded automatically. The feed and filtrate flows and the backwash frequency will be recorded by the PLC.
At the end of Phase 2 the performance data will be evaluated to confirm whether or not the filter loading used during Phase 2 was suitable for long term operation. If it is decided to adjust the filter loading conditions, then the filter will be operated for an additional week at the new loading conditions, until the team is comfortable with the filter performance.
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 7
3.2.3.1 Backwash Water
One concern is whether the backwash solids will settle readily so that they can be thickened and then pumped to the anaerobic digesters and removed from the system. During this period the backwash water will be directed to the secondary trickling filter pump station and will be returned to the secondary trickling filters. Samples of backwash water can be collected for conducting some initial settling tests in the laboratory at the WWTP. The purpose of the jar testing will be to understand the settleability of the backwash water to gauge how it might impact the downstream processes.
Carollo’s jar testing equipment can be used for this purpose. Table 3 presents a preliminary approach to conducting initial screening of coagulants to identify whether any show improved settling of the solids in the backwash. All six coagulants shown in Table 4 have been used in previous jar testing. The idea would be to run a series of initial screening jar tests using one coagulant at a time and using constant mixing and settling times to determine which chemicals work best. The determining factor will be a visual assessment of which dose provides the most solids accumulation and the best visual clarity. Turbidity measurements of the supernatant can be performed in the laboratory to assist with the assessment. Based on the findings from the initial screening it is anticipated that several of the chemicals and dosages will be eliminated. Depending on the results additional testing of the “best performing” chemical(s) may be carried out to refine the analysis further to determine whether chemical addition should be applied to the backwash stream as part of the pilot testing.
Table 3 Preliminary Approach for Backwash Water Jar Testing Test Number and Description
Jar Number and Dose (1)
Comment
1 2 3 4
Test 1-Ferrous chloride Control 2 5 10
Test 2-Ferric chloride Control 2 5 10
Test 3-ACH Control 2 5 10
Test 4-Brennfloc RE 5000 Control 5 10 20
Test 5-Alum Control 2 5 10
Test 6-Clarifloc Control 2 4 6
Notes:
ACH - aluminum chloralhydrate
(1) Number = dose in mg/L of metal salt (iron or aluminum) or polymer.
3.2.4 Phase 3 Operation – Filtration Optimization (With Chemicals) The purpose of Phase 3 will be to try to improve the performance of the filter (under the conditions tested in Phase 2) by the addition of a coagulant to the filter feed stream. The filter loading conditions established during Phase 2 will be maintained for Phase 3. The following chemicals will be tested sequentially during Phase 3:
Ferrous chloride – this chemical is already available on site and will be tested first. Ferric chloride.
ACH.
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 8
For the initial testing, ferrous chloride will be added to one of the day tanks in the pilot filter skid. Before setting the initial dose a set of jar tests will be performed to establish a starting point. The jar testing will be run with doses of 2, 4 and 6 mg/L as iron. Based on the results of the jar testing the initial dosing rate will be set and the filter will be operated continuously. The performance of the filter will be assessed over a one or two day period to determine whether there is any improvement in performance. Since the feed rate will be fixed, to provide a given filter hydraulic loading rate, the performance will be assessed based on the clarity (turbidity) of the filtrate, the TSS of the filtrate and the required backwash rate. If no improvement is seen, the chemical dose will be increased to based on the initial jar testing and the exercise repeated. At the end of the one or two day operating period the chemical will be switched to ferric chloride and the process will be repeated. Again, initial jar testing will be performed to establish the starting point for chemical addition.
Similarly, the exercise will be repeated using ACH as the coagulant.
This phase is expected to take about 3 weeks to complete; one week per chemical.
The test protocol is flexible and will be adjusted depending on the results that are obtained. If good performance is obtained with ferrous chloride then there may not be a need for further testing.
3.2.4.1 Longer-term Performance
After assessing the benefits of adding a coagulant to the feed stream, the pilot unit will be operated under the conditions determined to provide the best filter performance. Sample collection for laboratory analysis will be conducted during this period (see next section), which is expected to last a minimum of 2 weeks.
3.3 Sampling Plan
The proposed sampling plan/matrix for the pilot study is included in Table 4. As shown, it is anticipated that some samples will be analyzed on-site, either through instruments installed in the various pilot units, or by handheld meters used by the pilot plant operator. Other samples will be collected on a daily basis from Monday to Friday during working hours and analyzed at FGL laboratories. FGL can coordinate pickup of the cooled samples. It is recommended that TSS grab samples are taken once a week concurrently with the automatic readings.
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN 9
SECTION 4 MONITORING AND SAMPLING PLAN
Daily samples of the cloth filter influent, effluent and backwash flows shall be taken and refrigerated. It is expected that about 4 L of sample shall be collected at each stream for BOD₅ and TSS analysis. The following table indicates at what location each constituent should be sampled from.
Table 4 Monitoring and Sampling Plan
Parameter
Analytical
Method
Sampling Locations Phase 1 Phase 2 Phase 3
Cloth Filter
Feed
Cloth Filter
Effluent
Backwash Daytime Only 24 Hours/Day 24 Hours/Day
Flow, gpm N/A FIT-101 FIT-103 FIT-102 Continuous Continuous Continuous Turbidity, NTU On-line
Analyzer
AT-101 AT-??? - Continuous Continuous Continuous
Laboratory Samples
pH Twice daily(1) Twice daily(1)
TOC Twice daily(1) Twice daily(1)
COD Two per run(1) Twice daily(1) Twice daily(1)
BOD5 SM 5210 B Twice daily(1) Twice daily(1)
TSS SM 2540 D Two per run(1) Twice daily(1) Twice daily(1) Notes:
N/A - not applicable
(1) Correlate with daily high and low NTU diurnal pattern.
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX 1 NEXOM UNIT DRAWINGS
A
B
8 0.1
0.2 0.3
0.4 0.7
0.6 0.5
0.8 0.9
±
2 9
16 3
4 8
13 5
7 12
12 15
10 1
0.1 0.2
0.3 0.4
0.7 0.6
0.5 0.8
0.9 0.1
0.2 0.3
0.4 0.7
0.6 0.5
0.8 0.9
Free space
for discs
maintenance
VIEW FROM "A" SECT. "C-C" VIEW FROM "B"
01020304
nome file:
05 ClienteCustomer
Subject
Oggetto
Description
Descrizione
Revision
Revisione
Date
Data Modificato da
Revised by Checked by Approved by
Controllato da Approvato da
Customer approvalApprovazione da cliente
DateData
Disegnato
Drawn by Approved
Approvato
Drawing N°
ScalaScale
N° Disegno
Dim.
Dim.
SheetFoglio
NEXOM, INC.
888-426-8180
www.nexom.com
E-mail: [email protected]
CLOTH DISC FILTER IN METALLIC TANK
MSF 6/30 PEC VVM
STANDARD ASSEMBLY
VERTICAL FILTER
MDA-MSF630PECVVM-12070R06
VAGHI
26-03-12 1di1 1:25 A2
MDAMSF630PECVVM12070R06 Assieme commerciale 6-30 23-06-2020 CHANGED POSITION OF BOTTOM SLUDGE PUMP REINA 14 6
14 300 2
300 2
300 2
Free space
for discs
maintenance
01020304
nome file:
05 ClienteCustomer
Subject
Oggetto
Description
Descrizione
Revision
Revisione
Date
Data Modificato da
Revised by Checked by Approved by
Controllato da Approvato da
Customer approvalApprovazione da cliente
DateData
Disegnato
Drawn by Approved
Approvato
Drawing N°
ScalaScale
N° Disegno
Dim.Dim.
SheetFoglio
NEXOM, INC.
888-426-8180
www.nexom.com
E-mail: [email protected]
CLOTH DISC FILTER IN METALLIC TANK
MSF 6/30 PEC VVM
PROPOSAL LAYOUT
Layout proposal
Donati
07-02-2024 1di1 1:25 A2
Layout proposal Fort Saint John 6-30 PECV VM
11 1
6 7
8 B
A
Free space
for discs
maintenance
11 1
6 7
B
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX 2 DAILY LOG SHEET
Record Current Setpoints Programmed in PLC
Record the following values from PLC:
Feed (from Secondary Clarifiers) Filtrate (to Percolation Ponds) Backwash Feed
Flow
(gpm)
NTU Filter Headloss Time Recorded 4L Sample Taken? Filtrate flow (gpm) NTU Filter Headloss Time Recorded 4L Sample Taken? Backwash Flow (gpm) Backwash Frequenc y (minutes) Time Recorded 4L Sample Taken? Morning
YES
NO
YES
NO
YES
NO
Afternoon
YES
NO
YES
NO
YES
NO
Evening
YES
NO
YES
NO
YES
NO
Record the Amount of Chemical Dosing (if no chemical dosed, leave blank) General Observations (include information on clarity of effluent/influent/backwash) Coagulant Dosed Time of Initial Dose Dose amount (mg/L) Filter Loading Rate: gpm/ft2
Feed Flow: gpm
Backwash Flow: gpm
Backwash Interval: minutes
Daily Log Sheet City of Santa Maria Tertiary Filter Pilot Date: Operating Condition (circle one): Operator Initials:
1 2 3 4
TERTIARY FILTER PILOT TEST PLAN
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX 3 NEXOM EXAMPLE BROCHURE FOR
TRAILER PILOT UNIT
Pilot Project Study
Nexom’s Pile Cloth Filter
March 15th , 2024
KAUFMAN, TX
PILOT PROJECT
Example Only
CD25771.01 KAUFMAN TX 2
Project Overview
The Nexom Mita pile cloth filter (PCF) will be piloted for Kaufman in Texas. The pilot will be conducted to:
• Treat secondary effluent wastewater, measuring efficiencies for turbidity and TSS reduction.
• Validate hydraulic and surface solids loading limits of the cloth media technology • Provide engineers the opportunities to observe standard O&M for Mita pile cloth disk filter equipment
• Provide the owner with the opportunity to interface with the Mita pile cloth disk filter, experience and provide feedback on system controls, and validate its performance The Mita pilot filter system is a turnkey system designed for continuous discharge. 1000+ Mita filters worldwide minimize the owners expense and effort in maintaining wastewater treatment standards. The Mita filter consumes the smallest footprint in the lowest available hydraulic profile. Nexom delivers with factory-installed backwash systems and access platforms, leading the industry in quality and safety features.
Example Only
CD25771.01 KAUFMAN TX 3
System Design Parameters
Preliminary design loads and effluent objectives are presented in the following table:
Units Filter
Influent
Filter
Effluent
Pilot Flow Range gpm
TSS mg/L ≤ 5
Turbidity NTU
0-700
≤ 30 ≤
10 ≤ 2
Filtration design parameters are presented in the following table:
Configuration Units Design Parameter
Filter model MSF 2/10 PECV VM
Filter headloss in 24
Maximum filtration area ft2 108
Duty filtration area for testing ft2 17.9
Tertiary Max hydraulic loading gpm/ft2 up to 10
Tertiary Max surface solids loading rate (SSLR) lb/ft2d up to 3 Example Only
CD25771.01 KAUFMAN TX 4
Treatment Processes
Operating Narrative
The Nexom Mita filter continues to produce filtration during all aspects of the filtration cycle.
Filter inlet wastewater floods the filter tank. Nexom’s PCF utilizes an outside-in flow pattern with a completely submerged cloth media disk.
Filtrate from each disk collects in a central tube, passes into the effluent chamber and flows over the effluent weir. The filter basin includes an overflow weir, which partially bypasses excess flow in cases where the prevailing conditions exceed the filter design capacity. During the normal filtration process, all filter disks are stationary.
As the water passes through the filter media, solids accumulate on the disk's surface. As TSS is captured, headloss through the media rises. Tank level gradually increases to a set point elevation for backwash initiation. wastewater continues to be filtered during the backwash cleaning cycle, allowing for continuous, uninterrupted filtrate. The cleaning cycle can also run on a countdown timer.
The backwash cleaning cycle is controlled by a PLC-based operation system furnished with the filter equipment. The backwash cleaning system reverses the flow of filtrate, so no external backwash sources are required. Motors are energized in a set sequence for cleaning operations. Automatically controlled backwash pumps suction from dedicated clusters of disks, minimizing Example Only
CD25771.01 KAUFMAN TX 5
the peak backwash flow and required power consumption. Disks rotate while the backwash pumps vacuum the surface of the disks. Each backwash pump can clean up to four disks at a time by drawing water through molded backwash shoes engineered to minimize
backwash usage and extend media life. These shoes enable the Mita filter to deliver unparalleled performance in the smallest footprint.
A desludging system is provided with each filter to remove any settled solids accumulating in the filter cell. Each system includes an internal recycle for periodic chemical maintenance cleaning of the filter media with chlorine or citric acid.
Nexom delivers with factory-installed backwash systems and access platforms, leading the industry in quality and safety features. All components of the system are constructed from corrosion-resistant 304 stainless or composite materials that have been designed for continuous operation.
Reuse Filter Media
Nexom will test two types of next generation filter media in this validation study. Nexom’s polyester microfiber filter cloth is removable and replaceable in the field. Pile cloth filter media is preferable in applications to fixed-pore media of a similar sieve because it is less prone to fouling. During the vacuum backwash process the pile cloth fibers that are normally compressed under hydrostatic pressure are extended outward to release trapped solids. This motion and flexibility of the cloth fibers allows trapped solids to be released more efficiently compared to fixed pore media. Particles are less likely to become lodged in the PCF media or require manual disk maintenance and other interventions.
CA Title 22 approval for reuse was granted to cloth media filters using Nexom Generation 3 (SMPE-10-23, 10-micron) and Generation 4 (SMPE-10-25, 5-micron) pile cloth media at the Adelanto Wastewater Treatment Facility (AWWTF) in meeting the California Code of Regulations (CCR)Title 22 §60301.230 "Disinfected Tertiary Recycled Water “requirements in 2021. The protocol was conducted by PACE Water.
Example Only
CD25771.01 KAUFMAN TX 6
Scope of Work
By Nexom
• Lead project planning meeting
• Supply a trailer mounted turnkey Nexom Mita pilot system • Onsite commissioning of equipment
• Operations and data logging of equipment settings
• Decommissioning, cleaning, and repackaging of Nexom pilot equipment.
By Owner
• Confirm dimensions of access points and layout for unit placement • Utility hookups for equipment
o Power supply and connection of electrical service: 480 VAC, 3-phase, 50 amps o Process water – owner to provide water sump for Nexom submersible pumps and safety float switch.
• The pilot should be located as close as possible (maximum of 50’) to the influent, effluent discharge and backwash discharge locations, and gravity flow should be available, if possible, to these discharge receiving points. • All analytical expenses (TSS or nutrients).
Pilot Protocol
Provided to the owner by Nexom.
Example Only
CD25771.01 KAUFMAN TX 7
Analytical Overview
Nexom maintains operations logs that include:
• Inlet and outlet turbidity
• Pilot flow rates (inlet, effluent, backwash)
• Headloss
• Backwash intervals / duration
• Other operator adjustable setpoints.
Owner will coordinate all analysis for TSS per the pilot protocol.
Scheduling
TBD based on the timing of the P.O. Schedule to be confirmed by the pilot project group in kickoff meetings with stakeholders.
Pricing as negotiated by sales representative:
Price for Mobilization
Description Unit Price Quantity Total
Shipping and logistics to site $2,200 1 $2,200
Shipping and logistics from site $2,200 1 $2,200
Total Mobilization Price $4,400
Site Services
Description Unit Price Quantity Total
Commissioning week $7,500 1 waived
Decommissioning week $7,500 1 waived
Weekly Rental $3,000 3-4 waived
Project Management $1,500 1 waived
Total Services Price $0
All pricing is before any applicable taxes. Pricing is valid for 60 days. Payments due on receipt of invoice.
Example Only
CD25771.01 KAUFMAN TX 8
Any questions or comments can be directed to:
Patrick Ely
Regional Sales Manager
[email protected]
573-356-0316
Nexom
[email protected]
888-710-2583
323 N. Spokane St. Suite 200, Post Falls ID 83854
www.nexom.com
Questions or
Comments?
Example Only
CD25771.01 KAUFMAN TX 9
Documentation
• PCF P&ID
• PCF GA Drawing
Example Only
M
E
T T
TANK
S G
M P
SYSTEM EXTENTS
PRIMARY PROCESS
FLOW PATH
REJECT
EFFLUENT
INFLUENT
INSULATED PIPELINE
HEAT TRACE
SECONDARY FLOW PATH
PIPING SYMBOLS
TEMPERATURE
REGULATOR
FILLED SYSTEM
PRESSURE
VACUUM
RELIEF
VACUUM RELIEF
STRAIGHT
WITH WELL
VACUUM
RELIEF ANGLE
PRESSURE
RELIEF
STRAIGHT
RUPTURE DISC
OR SAFETY HEAD
VACUUM RELIEF
RUPTURE DISC OR
SAFETY HEAD
PRESSURE RELIEF
BACK
PRESSURE
REGULATOR
EXTERNAL TAP
BACK PRESSURE
REGULATOR
SELF CONTAINED
PRESSURE
REDUCING
REGULATOR
SELF CONTAINED
SYMBOLS FOR
SELF-ACTUATED REGULATORS
TRAP WITH
EQUALIZING
CONNECTION
TRAP
CONTINUOUS
DRAINER BALL
FLOAD TYPE
LEVEL REGULATOR
FLOAT OPERATED
MECHANICAL
LINKAGE
PRESSURE
RELIEF ANGLE
DIFFERENTIAL PRESSURE
REDUCING REGULATOR -
SHOWN WITH INTERNAL AND
EXTERNAL PRESSURE TAPS.
(1 OR 2 DIGITS)
BRANCH
SIZE
MATERIAL
LINE TYPE
PRESSURE RATING
LINE NUMBER
PIPE LINE DESIGNATION
BALL
VALVE SYMBOLS
V-PORT
BALL VALVE AIR RELEASE
KNIFE GATE
VALVE
(UNDEFINED TYPE)
ANGLE WEIGHTED RELIEF
NEEDLE 3 WAY 4 WAY
CHECK DIAPHRAGM PINCH
PLUG 3 WAY PLUG BUTTERFLY
GATE GLOBE
COUPLING
(HALF OR FULL)
TANK AND ACCESSORIES
MANHOLE/ACCESS
RECEIVER TANK INSULATION
FLANGED NOZZLE
ECCENTRIC
REDUCER FLAT
ON BOTTOM
RESTRICTION
ORFICE
DUPLEX BASKET
STRAINER
FO
S
PIPING ACCESSORIES & DETAILS
QUICK
DISCONNECT
ASSEMBLY
VARIABLE AREA
FLOW INDICATOR
WITH INTEGRAL
NEEDLE VALVE
CALIBRATION
COLUMN
AIR DRYER
FILTER SCOPE LIMITS THERMOWELL
CONCENTRIC
REDUCER
ECCENTRIC
REDUCER
FLAT ON TOP
ORIFICE FLANGE
AIR FILTER
SIMPLEX BASKET
STRAINER
BACKFLOW
PREVENTER
SUMP/DRAIN
STRAIGHTENING
VANES FLEX HOSE
EXPANSION JOINT
DU
INSULATED FLANGE
OR
SIGHT GLASS DIELECTRIC UNION
PULSATI0N
MIST ELIMINATOR DAMPER
CHEMICAL SEAL
SPRAY NOZZLE
OR SPARGER
MIXING SECTION EJECTOR
SCREEN STRAINER
Y STRAINER CONE STRAINER OR STATIC MIXER
GENERAL
HEAT EXCHANGER
HEAT EXCHANGER SYMBOLS
AIR COOLED
HEAT EXCHANGER
ELECTRICAL
HEATING SHELL & TUBE HEAT EXCHANGER ELEMENT
VERTICAL
CENTRIFUGAL PUMP
ROTARY BLOWER
OR COMPRESSOR
MOTOR DRIVEN EQUIPMENT
VENT FAN
AIR COMPRESSOR DUPLEX AIR COMPRESSOR
LIQUID RING
VACUUM PUMP
CHEMICAL
SUBMERSIBLE PUMP FEED PUMP
PERISTALTIC PUMP
AGITATOR OR MIXER
DIAPHRAGM PUMP
(PNEUMATIC OPER.)
PROGRESSIVE
CAVITY PUMP
DIAPHRAGM
CHEMICAL FEED
PUMP W/ INTERNAL
RELIEF VALVE
VERTICAL TURBINE
FAN / BLOWER
CENTRIFUGAL
PUMP
PNEUMATIC
ELECTRIC MOTOR ROTARY MOTOR
PRIME MOVERS FOR
MOTOR DRIVEN EQUIPMENT
SYMBOLS FOR VALVE
ACTION IN THE EVENT OF
ACTUATOR POWER FAILURE
FO = FAIL OPEN
FC = FAIL CLOSED
FL = FAIL LOCKED
FI = FAIL INDETERMINATE ( LAST POSITION )
F = USED WITH 3 WAY & 4 WAY VALVE-
ARROWS SHOW PATHS OPEN TO FLOW
ON POWER FAILURE.
FO
SYMBOL LOCATED BY VALVE-USED ONLY WHERE NECESSARY
TO INCREASE UNDERSTANDING
OF THE SYSTEM.
CONTROL LOGIC
CAPILLARY TUBE
SOFTWARE OR DATA
INTERNAL SYSTEM LINK
PNEUMATIC SIGNAL
UNDEFINED SIGNAL
ELECTRIC SIGNAL
INSTRUMENT LINE SYMBOLS
CYLINDER &
SPRING
TO CLOSE
CYLINDER &
SPRING
TO OPEN
DOUBLE-ACTING
CYLINDER
(WITH)=POSITIONER
DOUBLE-ACTING
CYLINDER
(WITHOUT)
DIAPHRAGM &
SPRING TO CLOSE
(WITH)=POSITIONER
DIAPHRAGM &
SPRING TO OPEN
(WITHOUT)
DIAPHRAGM
AIR TO AIR (WITH)=POSITIONER
DIAPHRAGM
AIR TO AIR
(WITHOUT)
SOLENOID
(WITH)
=MANUAL
OVERRIDE
S
ELECTRIC
HANDWHEEL
(MANUAL
OVERRIDE)
MANUAL FOR
ON/OFF SERVICE
(NO SYMBOL) =
VALVE ACTUATOR SYMBOLS
SOLENOID
(WITHOUT)
S
BRZ - BRASS/BRONZE
CIR - CAST IRON
CST - CARBON STEEL
CPR - COPPER
FRP - FIBERGLASS
GCS - GALVANIZED CARBON STEEL
LCS - LINED CARBON STEEL
TEF - TEFLON
PU - POLYURETHANE
PET - POLYETHYLENE
POP - POLYPROPYLENE
PVC - POLYVINYL CHLORIDE
RUB - RUBBER
S04 - 304 STAINLESS STEEL
S4L - 304L STAINLESS STEEL
S16 - 316 STAINLESS STEEL
S6L - 316L STAINLESS STEEL
VIT - VITON
CVC - CHLORINATED POLYVINYL CHLORIDE
MATERIAL DESIGNATION
D = DUCT
H = HOSE
P = PIPE
T = TUBE
TYPE
GENERAL NOTES:
1. FOR INSTRUMENTATION SYMBOLS AND LIST OF
RELAY FUNCTIONS SEE NEXOM DRAWING NO.
PID-B.
THIS DRAWING IS PROVIDED FOR
INFORMATION ONLY.
DIRECT CONTACT
JET MIXER
6"-S04P1-101A
PRESSURE
REDUCING
REGULATOR
EXTERNAL TAP
TEMPLATE LAST MODIFIED: 08.05.19
PAGE 1/3
SCALE NTS
REV. 02
LOCATION: MITA Pilot
NUMBER: 210P-PID
DESCRIPTION:
Piping & Instrumentation Diagram,
Pile Cloth Filter 2-10
A
B
C
D
1 2 3 4 5 6 7 8
1 2 3 4 5 6 7 8
A
B
C
D
UNLESS OTHERWISE SPECIFIED
TOLERANCES:
00.0 OR X/X ± .125"
00.00 ± .05"
00.0° ± 2.0°
Example Only
I
P P
E
SYMBOLS FOR LOGIC CONTROL
INSTRUMENT FOR MULTIPLE SERVICE OR
MULTIPLE FUNCTIONS SHALLL BE INDICATED
BY TWO OR MORE TANGENT CIRCLES.
SYMBOL FOR PANEL MOUNTED INSTRUMENTS
MAY HAVE PANEL DESIGNATION. IF
PROJECT HAS A NUMBER OF PANELS.
(1) (2) (MAIN) (AUX.)
TYPICAL SYMBOLS FOR BEHIND-THE-PANEL
INSTRUMENT OR NORMALLY INACCESSIBLE
FUNCTION.
GENERAL NOTES:
INSTRUMENT IDENTIFICATION LETTERS
INSTRUMENT SYMBOLS
PROGRAMMABLE
LOGIC
CONTROLLER
FUNCTION
COMPUTER
FUNCTION
INCLUDING
DISTRIB.
CNTL. SYS.
SHARED DISPLAY
SHARED CONTROL
DISCRETE
INSTRUMENTS
AUXILIARY
PANEL OR RACK
NORMALLY
ACCESSIBLE TO
OPERATOR
FIELD
MOUNTED
PRIMARY
CONTROL PANEL
NORMALLY
ACCESSIBLE TO
OPERATOR
(TYPICAL EXAMPLE SHOWS SQUARE
ROOT EXTRACTOR IN FLOW LOOP)
REVERSE
PROPORTIONAL
Xn f(X)
f(t)
TIME FUNCTION
NON LINEAR
UNSPECIFIED OR
INTEGRAL EXPONENTIAL FUNCTION
n REV dtd
D
A
A
D
-K HOA REV
R
P
I AND OR
MISCELLANEOUS SYMBOLS
E = VOLTAGE
H = HYDRAULIC
I = CURRENT
O = ELECTROMAGNATIC OR SONIC
P = PNUMATIC
R = RESTANCE (ELECTRICAL)
CONVERT SIGNAL FORM
(TYPICAL EXAMPLES)
REVERSE DERIVATIVE
ANALOG DIGITAL
DIGITAL ANALOG
NOTE: THE SQUARE MAY BE USED AS A FLAG.
REVERSE ACTION
HIGH SELECTING LOW SELECTING
ROOT
EXTRACTION
PROPORTIONAL
BIAS
HAND-OFF-AUTO
K 1:1 2:1
GENERALIZED SPECIFIC
INTERLOCKING FUNCTIONS
RESET FOR LATCH
TYPE ACTUATOR
PURGE OR
FLUSHING DEVICE
FE
FT SONIC
M
FI FQIS
FT
FT FT
FI FI
FT FT
WEIR
FLUME VENTURI TUBE
FLOW TUBE
FLOW NOZZLE
OTHER
FLOW SENSORS VORTEX
TARGET
MAGNETIC FLOW METER
(SHOWN CONNECTED TO
TRANSMITTER)
POSITIVE DISPLACEMENT
FLOW TOTALIZING METER
(SHOWN WITH SWITCH)
TURBINE OR
PROPELLER TYPE
PRIMARY ELEMENT
VARIABLE AREA
FLOW INDICATOR
FLOW
INDICATOR
(TYPICAL)
ORIFICE PLATE
IN QUICK-CHANGE
FITTING
AVERAGING
PILOT TUBE
ORIFICE PLATE
WITH FLANGE
OR CORNER TAPS
1. FOR MECHANICAL SYMBOLS AND ADDITONAL
NOTES, SEE NEXOM DRAWING NO. PID-A.
THIS DRAWING IS PROVIDED FOR INFORMATION ONLY.
FLOW
TRANSMITTER
(TYPICAL)
NOTES:
1. ANY FIRST LETTER COMBINED WITH MODIFIER REPRESENTS A NEW AND SEPARATE MEASURED VARIABLE.
EXAMPLES: PD = DIFFERENTIAL PRESSURE FQ = TOTALIZED OR INTEGRATED FLOW.
EXCEPTION IS THE MODIFIER "J" FOR MULTIPOINT SCANNING.
2. FOR ANALYSIS NOT IDENTIFIED BY A SPECIFIC LETTER IN THE TABLE, USE THE LETTER "A" NEAR THE INSTRUMENT SYMBLOL, SPECIFY THE NATURE OF THE ANALYSIS.
EXAMPLE: PH
3. MEANING OF A "USER CHOICE" LETTER SHALL BE CONSISTENT THROUGHOUT A PROJECT AND SHALL BE SPECIFIED IN THE DRAWING LEGEND.
4. UNCLASSIFED LETTERS MAY HAVE A FEW DIFFERENT MEANINGS ON A PROJECT, THE MEANING SHALL BE SPCIFIED NEAR EACH INSTRUMENT SYMBOL USING THE UNCLASSIFIED LETTER.
5. THE MODIFIER "SCAN" APPLIES TO MULTIPOINT PRINTING INSTRUMENTS, SUCH AS CJRS (MULTIPOINT CONDUCTIVITY RECORDER WITH ALARM SWITHCES).
FLOW
TRANSMITTER
(TYPICAL)
ORIFICE PLATE
WITH VENA CONTRACTA
RADIUS, OR PIPE TAPS
+ -
-
FY.
16 SYMBOLS FOR FLOW MEASUREMENT
FIRST LETTER
MEASURE OR INIATING VARIABLE MODIFIER
A = ANALYSIS
B = BURNER, COMBUSTION
C = USER'S CHOICE
D = USER'S CHOICE DIFFERENTIAL
E = VOLTAGE
F = FLOW RATE RATIO (FRACTION)
G = USER'S CHOICE
H = HAND
I = CURRENT (ELECTRICAL)
J = POWER SCAN
K = TIME, TIME SCHEDULE TIME RATE OF CHANGE
L = LEVEL
M = USER'S CHOICE MOMENTARY
N = USER'S CHOICE
O = USER'S CHOICE
P = PRESSURE, VACUUM
Q = QUANTITY INTERGRATE, TOTALIZE
R = RADIATION
S = SPEED, FREQUENCY SAFETY
T = TEMPERATURE
U = MULTIVARIABLE
V = VIBRATION, MECH. ANALYSIS
W = WEIGHT, FORCE
X = UNCLASSIFIED X AXIS
Y = EVENT, STATE OR PRESENCE Y AXIS
Z = POSITION, DIMENSION Z AXIS
SUCCEEDING LETTERS
LETTER READOUT OR PASSIVE
FUNCTION OUTPUT FUNCTION MODIFIER
A ALARM
B USER'S CHOICE USER'S CHOICE USER'S CHOICE
C CONTROL
D
E SENSOR (PRIMARY ELEMENT)
F
G GLASS, VIEWING DEVICE
H HIGH
I INDICATE
J
K CONTROL STATION
L LIGHT
M MIDDLE, INTERMEDIATE
N USER'S CHOICE USER'S CHOICE USER'S CHOICE
O ORIFICE, RESTRICTION
P POINT (TEST) CONNECTION
Q
R RECORD
S SWITCH
T TRANSMIT
U MULTIFUNCTION MULTIFUNCTION MULTIFUNCTION
V VALVE, DAMPER, LOUVER
W WELL
X UNCLASSIFIED UNCLASSIFIED UNCLASSIFIED
Y RELAY, COMPUTE, CONVERT
Z
DRIVE, ACTUATOR,
UNCLASSIFIED FINAL
CONTROL ELEMENT
TEMPLATE LAST MODIFIED: 08.05.19
PAGE 2/3
SCALE NTS
REV. 02
LOCATION: MITA Pilot
NUMBER: 210P-PID
DESCRIPTION:
Piping & Instrumentation Diagram,
Pile Cloth Filter 2-10
A
B
C
D
1 2 3 4 5 6 7 8
1 2 3 4 5 6 7 8
A
B
C
D
UNLESS OTHERWISE SPECIFIED
TOLERANCES:
00.0 OR X/X ± .125"
00.00 ± .05"
00.0° ± 2.0°
Example Only
3/&
3/&
$,7
$7
785%,',7<
0(7(5
&+(0,&$/6.,'
&+(0
3 3/&
$,7
3/&
/,
/7
/6/
3/&
/$/
/6+
3/&
/$+
$7
&+(0,&$/6833/<
&+(0,&$/6.,'
&+(0
3 3/&
9(17&+(06833/<
%$&.:$6+
)7
),7
3/&
)/2:0(7(5
3$
3/&
3,6
,1)/8(17
0 3/&
())/8(17
67$7,&0,;(5
)/2:0(7(5
),7
3/&
)7
3/&
0 6/8'*(
/6
3/&
/,=
9(17&+(06833/<
72)$8&(7
)/86+&+(06.,'
&+(0,&$/6833/<
%:'5$,1
&+(0,&$/6833/<
6,1.'5$,1
3/&
)7
3/&
),7
:$7(56833/<
3 0,;7$1.'5$,1
9(17&+(06833/<
3/&
3 &+(0,&$/6.,'
&+(0
/,=
3/&
/6
&+(0:$6%$7&+
)/(;+26(
%<1(;20
73 &+(0:$60,;,1*%$55(/
0;
73 73
3 785%,',7<
0(7(5
3 73
73 73
73 ,36,36
,36
)/2:0(7(5 0;
',6&),/7(5
')
0 73
73 )/(;+26(
%<1(;20
)/(;+26(
%<1(;20
73 )/(;+26(
%<1(;20
)/(;+26(
%<1(;20
%:
73 73
73 73
73 &217$,1(5
)/(;+26(
%<1(;20
)/(;+26(
%<1(;20
73 73
6,1.
73 )/(;+26(
%<1(;20
5(9,6,216
5(9 '(6&5,37,21 (1*,1((5 '$7(
,1,7,$/5(/($6( 06
0$-25&+$1*(6 06
7(50,1$/32,177$%/(
73 0&$073 0&$073 0&$073 )&$073 )&$073 )&$073 )&$073 )&$073 )&$073 )&$073 )&$073 *+70$/(73 &2035(66,21),773 &2035(66,21),773 &2035(66,21),773 &2035(66,21),773 &2035(66,21),773 &2035(66,21),7 dDW>d>^dDK/&/͗Ϭϴ͘Ϭϱ͘ϭϵ 3$*(
6&$/(176
5(9
/2&$7,210,7$3LORW
>>/E&KZDd/KEKEd/EKEd,/^KhDEd/^d,WZKWZdzK&EyKD͕
/E͘;EͬKZ/d^&&/>/d^Ϳ͘d,^/'EKEWd^E/E&KZDd/KE
KEd/E,Z/EZWZKWZ/dZzdKEyKDEZ^hD/ddd/E
KE&/E͘d,zZEKddZE^&Z>EDh^dh^KE>z&KZd,
WhZWK^&KZt,/,d,KhDEd/^yWZ^^>z^hD/dd͘d,zDh^dEKd
/^>K^͕ZWZKh͕>KE͕KZh^/EEzKd,ZDEEZ
t/d,Khdd,yWZ^^tZ/ddEKE^EdK&EyKD͘EyKD^^hD^EK
Z^WKE^//>/dzKZ>//>/dz&KZd,h^K&d,/^KhDEdKZd,^/'E
KEWd^E/E&KZDd/KEKEd/E,Z/E&KZEKd,ZWZK:d͕KZ/E
DEEZd,dK^EKdZ>ddKd,&/dE^^KZWhZWK^K&d,/^
KhDEd͘/EEKsEd^,>>d,/^KhDEdKZd,^/'EKEWd^
E/E&KZDd/KEKEd/E,Z/Eh^/EEzDEEZdZ/DEd>
dKd,/EdZ^dK&EyKD͘>>WdEdZ/',d^ZZ^Zs͘WdE
K&d,>/sZzK&d,/^KhDEdKE^d/dh^
'ZDEddKd,^dZD^EKE/d/KE^͘
1(;20&21),'(17,$/,7<
180%(533,'
'(6&5,37,213LSLQJ ,QVWUXPHQWDWLRQ'LDJUDP3LOH&ORWK)LOWHU $
%
&'
$
%
&'
$87+ 06 &+.' 1$
81/(6627+(5:,6(63(&,),('',0(16,216$5(,1,1&+(672/(5$1&(625;;7+,5'$1*/(352-(&7,21 Example Only
N/A, 2022-05-12
CONCEPTS AND INFORMATION CONTAINED HEREIN FOR ANOTHER PROJECT, OR IN SCALE 1:80
AUTH.
NEXOM CONFIDENTIALITY
PAGE 1/5
A MANNER THAT DOES NOT RELATE TO THE FITNESS OR PURPOSE OF THIS DOCUMENT. IN NO EVENT SHALL THIS DOCUMENT OR THE DESIGN CONCEPTS
AND INFORMATION CONTAINED HEREIN BE USED IN ANY MANNER DETRIMENTAL TO THE INTEREST OF NEXOM. ALL PATENT RIGHTS ARE RESERVED. ACCEPTANCE
OF THE DELIVERY OF THIS DOCUMENT CONSTITUES
MS, 2022-05-12
RESPONSIBILITY OR LIABILITY FOR THE USE OF THIS DOCUMENT OR THE DESIGN CHKD.
DC
B
A
12 REV. 02
LOCATION: MITA Pilot
TEMPLATE LAST MODIFIED: 08.05.19 AGREEMENT TO THESE TERMS AND CONDITIONS. NUMBER: 210P GA.
DESCRIPTION: MITA Pilot GA
ABCD
12 3 4 5 6 7 8
3 4 5 6 7 8
ALL INFORMATION CONTAINED ON THIS DOCUMENT IS THE PROPERTY OF NEXOM, INC. (AND/OR ITS AFFILIATES). THE DESIGN CONCEPTS AND INFORMATION
CONTAINED HEREIN ARE PROPRIETARY TO NEXOM AND ARE SUBMITTTED IN CONFIDENCE. THEY ARE NOT TRANSFERABLE AND MUST BE USED ONLY FOR THE PURPOSE FOR WHICH THE DOCUMENT IS EXPRESSLY SUBMITTED. THEY MUST NOT
BE DISCLOSED, REPRODUCED, LOANED, OR USED IN ANY OTHER MANNER WITHOUT THE EXPRESS WRITTEN CONSENT OF NEXOM. NEXOM ASSUMES NO UNLESS OTHERWISE SPECIFIEDDIMENSIONS ARE IN INCHESTOLERANCES:00.0 OR X/X ± .125"00.00 ± .05"00.0° ± 2.0°
THIRD ANGLE PROJECTION
REVISIONS
REV. DESCRIPTION ENGINEER DATE
01 INITIAL RELEASE MS 2022-05-0902 SADDLE TAP INF LINE MS 2022-05-12 NOTES:
1(;200,7$3,/(&/27+),/7(56<67(0 9,(:66(&7,21('%(/2:522)/,1(729,(:
&217$,1(5,17(51$/6
)7'(&.7851.(<75$,/(502817('3,/27
6<67(0
932:(5',675,%87,21$1'&219(56,21
,1&/8'('
68%0(56,%/()(('38036$1'$//+26(6,1&/8'('
Example Only
VOLUME 2 / CHAPTER 1: INTRODUCTION/PLANT HISTORY
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
ATTACHMENT B SANTA MARIA TEMP TERTIARY
FILTRATION COST ESTIMATE
DETAILED COST ESTIMATE
Project: Santa Maria Temporary Tertiary Filteration Format: MASTER FORMAT 17 Client: City of Santa Maria Date : June 9, 2025
Location: Santa Maria, CA By : DLM
Element: 01 Temporary Tertiary Filters Reviewed:
SPEC. NO. DESCRIPTION QUANTITY UNIT UNIT COST SUBTOTAL TOTAL Division 02 - Site Construction
02220
Core Drilling, 18" Diameter Per Inch Of
Thickness 12.00 IN $35.88 $431
02220 Remove 4"-6" Asphalt Pavement 250.00 SF $.75 $187 02220 Asphalt Pavement Cutting 396.00 INFT $.70 $279
02300 20 Cy Dump Truck, 5 Miles/Round Trip 1,888.89 CY $3.37 $6,359 02300
Imported Pipe Bed & Zone/Confined
Structure Backfill, Class A Material 92.59 CY $57.29 $5,305 02300
Tractor/Backhoe, 30" Bucket Class C (Hard
Digging), 0-5' D 111.11 CY $19.27 $2,141
02300
Class A Material Hand Backfill & Compact
90% To 5' Depth 592.59 CY $384.55 $227,880
02300
D8 Dozer, Class C (Hard Dig), Grade, Cut,
Fill & Compact, 500' Haul 1,777.78 CY $8.85 $15,730
02742
4" Pavement Replacement On 8" Abc Over
Trench 55.56 SY $109.90 $6,106
Total $264,418
Division 03 - Concrete
03300 18" Edge Forms, Slab On Grade, Add 240.00 LF $6.37 $1,529 03300 18" Structural Flat Mat On Grade 266.67 CY $596.16 $158,978 03300 12" Straight Wall, To 8' High 35.56 CY $997.21 $35,461 Total $195,968
Division 05 - Metals
05000 Metal Canopy 1.00 LS $185,840.90 $185,841
05500
Aluminum Stairs, Including Railing And
Supports 20.00 RSR $714.06 $14,281
05500 Aluminum Pit Frame & Cover 12.50 SF $56.65 $708
05500 Aluminum Osha Handrail 192.00 LF $98.15 $18,844
05500 Aluminum Grating, 2-1/2" 500.00 SF $123.08 $61,541 Total $281,215
Division 11 - Equipment
11000 Tertiary Filters 1.00 LS $1,846,319.96 $1,846,320 11000 Feed Pumps 3.00 EA $33,409.60 $100,229
11000 Backwash Tank w/ Mixer 1.00 LS $25,716.60 $25,717 11000 Backwash Transfer Pumps 3.00 EA $10,286.64 $30,860 11000 Double Containment Chemical Area 1.00 LS $7,362.75 $7,363 11000 Chemical Feed Pumps 2.00 EA $10,231.69 $20,463
Total $2,030,951
Division 15 - Mechanical
15112 18" 150# Fxf Awwa Butterfly Valve, No Op 4.00 EA $7,593.14 $30,373 15114 16"- 125# Di Fxf Swing Check Valve 2.00 EA $29,527.62 $59,055 15119 Air/Vac Valve, 150# Flange, 6" 1.00 EA $3,430.12 $3,430 15121 18" Fca Above Ground 4.00 EA $4,106.51 $16,426
15251 18" Cldi Flg Straight Tee In Place 2.00 EA $8,254.93 $16,510 15251 18"X16" 125# Cldi Fxf Eccentric Rdcr 2.00 EA $10,573.99 $21,148 15251 18" 45° 125# Cldi Fxf Ell 4.00 EA $4,592.61 $18,370 15251 18" 90° 125# Cldi Fxf Ell 4.00 EA $4,955.28 $19,821 15251 18" 125# Cast Iron Blind Flange 2.00 EA $2,377.69 $4,755 15251 18" Flg Cldi Pipe In Bldg 80.00 LF $279.72 $22,377 15251 18" Flg Cldi Pipe In Open Trench 200.00 LF $248.53 $49,706 15251 8" 45° 125# Cldi Fxf Ell 6.00 EA $996.20 $5,977
15251 8" 90° 125# Cldi Fxf Ell 6.00 EA $1,022.27 $6,134 15251 8" Flg Cldi Pipe In Bldg 20.00 LF $99.75 $1,995
15251 8" Flg Cldi Pipe In Open Trench 1,000.00 LF $84.91 $84,906 Total $360,984
Division 16 - Electrical
16000 Electrical 1.00 LS $.00 $626,707
Total $626,707
Division 17 - Instrumentation and
Controls
17000 Instrumentation and Controls 1.00 LS $.00 $313,354 Total $313,354
Grand Total $4,073,597
f/n: Santa Maria Temp Tertiary Filtration Cost Estimate-01 Temporary Tertiary Filters Page 1 of 1 Form Rev: 2008June VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX B HEADWORKS SAMPLING RESULTS -
SEPTEMBER 2024
Summary of Data from three composite samples collected at the headworks - September 2024 Constituent Unit 9/16/2024 9/23/2024 9/30/2024 9/30/2025 9/30/2026 Metals CA MCL SMCL
Aluminum mg/L 0.10 0.08 0.06 1
Arsenic mg/L ND ND ND 0.01
Cadmium mg/L ND ND ND 0.005
Chromium mg/L 0.00 0.00 0.00 0.05
Manganese mg/L 0.05 0.06 0.06 0.05
Mercury mg/L 0.00 0.00 0.00 0.002
Selenium mg/L 0.00 0.00 0.00 0.05
Zinc mg/L 0.07 0.07 0.06 5
Wet Chemistry
Nitrate Nitrogen mg/L ND ND ND 10
Nitrite Nitrogen mg/L 0.59 ND ND
Phenols mg/L ND ND ND
Perchlorate ug/L 0.10 ND ND 6
EPA 524.2
4-Bromofluorobenzene ‡ % 90 88 86
1,2-Dichlorobenzene-d4 ‡ % 77.9 91.70 92.00
Methyl tert-Butyl Ether(MTBE) ug/L ND ND ND 13
Styrene ug/L ND ND ND 100
EPA 551.1
Decafluorobiphenyl ‡ % 80 82 85
Bromodichloromethane ug/L ND ND ND
Bromoform ug/L ND ND ND
Chloroform ug/L ND ND ND
Dibromochloromethane ug/L ND ND ND
Total Trihalomethanes ug/L ND ND ND 80
EPA 552.2
2,3-Dibromopropionic Acid ‡ % 126 125 108
Bromoacetic Acid ug/L ND ND ND
Chloroacetic Acid ug/L ND ND ND
Dibromoacetic Acid ug/L ND ND ND
Dichloroacetic Acid ug/L 3 4 3
Trichloroacetic Acid ug/L 4 4 4
Haloacetic acids (five) ug/L 7 8 7 60
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX C PFAS SAMPLING RESULTS - SEPTEMBER
2024
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN C-1
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/Master Plan/Volume 13/Appendix C1.docx PFAS SAMPLING RESULTS - SEPTEMBER 2024
A wide range of per- and polyfluoroalkyl substance (PFAS) compounds were also analyzed, but only perfluorohexanoic acid (PFHxA), perfluorobutanesulfonic acid (PFBS) and perfluorohexanesulfonic acid (PFHxS) were detected. The summarized results for these three selected compounds are shown in Table B.1. The two PFAS that have an Environmental Protection Agency maximum contaminant level (MCL) for drinking water, perfluorooctanoic acid (PFOA) and perfluorooctanesulfonic acid (PFOS), were both non-detect (ND). In July 2025, California announced proposed revisions to the PFAS regulations that include a Response Level (RL) for PFHxS at 10 nanograms per liter (ng/L) and a Notification Level (NL) and RL for perfluorohexanoic acid (PFHxA) of 1,000 ng/L and 10,000 ng/L, respectively. As indicated by the values in Table B.1, the concentrations of PFHxS are above California's proposed RL for drinking water, while the concentrations of PFHxA are well below the proposed NL and RL.
Table B.1 Summary of Results From First Sampling Event - September 2024 - PFAS Compounds Detected Sampling Date PFHxA(1)
(ng/L)
PFBS(2)
(ng/L)
PFHxS(1)
(ng/L)
9/16/2024 46 87 33
9/23/2024 47 53 33
9/30/2024 ND(3) ND(3) ND(3)
Average 31 46.7 22
Notes:
(1) PFHxA and PFHxS are regulated in drinking water in California. PFHxA has proposed NL and RL values at 1,000 ng/L and 10,000 ng/L, respectively. PFHxS has a proposed RL at 10 ng/L. (2) PFBS does not currently have a drinking water MCL.
(3) Reporting limit was 50 ng/L for this sample, which may explain why none of the three compounds were detected.
Summary of Data from three composite samples collected at the headworks - September 2024 - PFAS Results Constituent Unit 9/16/2024 9/23/2024 9/30/2024
PFAS by LCMSMS (QSM 5.3 Table B-15 Compliant)
Perfluorobutanoic acid (PFBA) ng/L ND ND ND
Perfluoropentanoic acid (PFPeA) ng/L ND ND ND
Perfluorohexanoic Acid (PFHxA) ng/L 46 47 ND
Perfluoroheptanoic Acid (PFHpA) ng/L ND ND ND
Perfluorooctanoic Acid (PFOA) (EPA MCL = 4.0 ng/L) ng/L ND ND ND Perfluorononanoic Acid (PFNA) ng/L ND ND ND
Perfluorodecanoic Acid (PFDA) ng/L ND ND ND
Perfluoroundecanoic Acid(PFUnA) ng/L ND ND ND
Perfluorododecanoic Acid(PFDoDA) ng/L ND ND ND
Perfluorotridecanoic Acid(PFTrDA) ng/L ND ND ND
Perfluorotetradecanoic Acid(PFTeDA) ng/L ND ND ND
Perfluorohexadecanoic acid(PFHxDA) ng/L ND ND ND
Perfluorooctadecanoic acid(PFOcDA) ng/L ND ND ND
Perfluorobutanesulfonic Acid(PFBS) ng/L 87 53 ND
Perfluoropentanesulfonate(PFPeS) ng/L ND ND ND
Perfluorohexanesulfonic Acid(PFHxS) ng/L 33 33 ND
Perfluoroheptanesulfonic acid(PFHpS) ng/L ND ND ND
Perfluorooctanesulfonic Acid (PFOS) (EPA MCL = 4.0 ng/L) ng/L ND ND ND Perfluorononanesulfonic acid(PFNS) ng/L ND ND ND
Perfluorodecanesulfonic acid(PFDS) ng/L ND ND ND
4:2 Fluorotelomer Sulfonate ng/L ND ND ND
6:2 Fluorotelomer Sulfonate ng/L ND ND ND
8:2 Fluorotelomer Sulfonate ng/L ND ND ND
10:2 Fluorotelomer sulfonate ng/L ND ND ND
PFAS by LCMSMS (QSM 5.3 Table B-15 Compliant)
N-methyl perfluorooctanesulfonamidoacetic ng/L ND ND ND N-ethyl perfluorooctanesulfonamidoacetic ng/L ND ND ND
Perfluorooctane Sulfonamide (PFOSA) ng/L ND ND ND
N-Methylperfluorooctanesulfonami de (MeFOSA) ng/L ND ND ND N-Ethylperfluorooctanesulfonamide (EtFOSA) ng/L ND ND ND N-Methylperfluorooctanesulfonamidoethanol (MeFOSE) ng/L ND ND ND N-Ethylperfluorooctanesulfonamidoethanol (EtFOSE) ng/L ND ND ND 4,4,5,5,6,6,6-Heptafluorohexanoic Acid (3:3 FTCA) ng/L ND ND ND 2H,2H,3H,3H-Perfluorooctanoic acid (5:3 FTCA) ng/L ND ND ND 2H,2H,3H,3H-Perfluorodecanoic acid (7:3 FTCA) ng/L ND ND ND Hexafluoropropylene oxide dimer acid (HFPO-DA) ng/L ND ND ND 4,8-dioxa-3H-perfluorononanoic Acid (ADONA) ng/L ND ND ND 9-chlorohexadecafluoro-3-oxanone-1-sulfonic Acid ng/L ND ND ND 11-chloroeicosafluoro-3-oxaundecane-1-sulfonic Acid ng/L ND ND ND VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX D SUMMARY OF CONSTITUENTS IN MAJOR
HAULER SAMPLING
Analyte Unit
BOD mg/L
Chloride mg/L
Sulfate mg/L
Hexavalent Chromium ug/L
Mercury mg/L
Boron mg/L
Iron mg/L
Sodium mg/L
Aluminium mg/L
Cadmium mg/L
Chromium mg/L
Cobalt mg/L
Copper mg/L
Lead mg/L
Nickel mg/L
Silver mg/L
Zinc mg/L
Chromium III mg/L
pH @ 25 C pH Units
Temperature During pH Sample Analysis °C
Specific Conductance (EC) @ 25 C umhos/cm
Total Alkalinity mg/L
Ammonia as N mg/L
Total Kjeldahl Nitrogen mg/L
Chemical Oxygen Demand mg/L
Total Oil & Grease MG/KG
Phenolics, Total mg/L
Total Dissolved Solids mg/L
Total Suspended Solids mg/L
Volatile Suspended Solids mg/L
Formaldehyde ug/l
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX E RESULTS FROM MAJOR HAULER
SAMPLING
USS ND Sample #1 USS ND Sample #2 USS ND Sample #3 USS ND Sample #4 3/20/25 7:22 4/7/25 7:29 4/8/25 7:19 4/17/25 7:31
BOD mg/L 2500 2600 2400 3400
MRL
4 4
4 4
Chloride mg/L 780 850 760 820
MRL 200 200 200 400
Sulfate mg/L 310 360 370 400
MRL 200 200 200.0 20.0
Hexavalent Chromium ug/L ND ND ND ND
MRL 20 10 10
5 Mercury mg/L ND ND ND ND
MRL 0.001 0.001 0.001 0.001
Boron mg/L 0.29 0.6 ND 0.4
MRL 0.200 0.500 0.500 0.400
Iron mg/L 1.2 1.6 1.1 1.2
MRL 0.100 0.250 0.250 0.200
Sodium mg/L 510 810 730 710
MRL 1 3
3 2
Aluminium mg/L 1.7 1.7 1.5 0.76
MRL 1 1 1 0
Cadmium mg/L ND ND ND ND
MRL 0.010 0.010 0.010 0.005
Chromium mg/L ND ND ND ND
MRL 0.030 0.030 0.030 0.015
Cobalt mg/L ND ND ND ND
MRL 0.010 0.010 0.010 0.005
Copper mg/L 0.034 0.12 0.066 0.13
MRL 0.020 0.020 0.020 0.010
Lead mg/L ND ND ND ND
MRL 0.010 0.010 0.010 0.005
Nickel mg/L ND 0.026 ND 0.019
MRL 0.020 0.020 0.020 0.010
Silver mg/L ND ND ND ND
MRL 0.010 0.010 0.010 0.005
United Site Services
USS ND Sample #1 USS ND Sample #2 USS ND Sample #3 USS ND Sample #4 3/20/25 7:22 4/7/25 7:29 4/8/25 7:19 4/17/25 7:31
United Site Services
Zinc mg/L 0.82 0.79 0.7 0.38
MRL 0.050 0.050 0.050 0.025
Chromium III mg/L ND ND ND ND
MRL 0.020 0.010 0.010 0.005
pH @ 25 C pH Units 7.61 7.75 8.11 7.89
MRL 0.100 0.100 0.100 0.100
Temperature During pH Sample
Analysis °C 21 21 22 21
MRL 1 1 1 1
Specific Conductance (EC) @ 25 C umhos/cm 9700 12000 10000 12000 MRL
2 2
2 2
Total Alkalinity mg/L 3600 5100 3700 4400
MRL 20 20 20 20
Ammonia as N mg/L 680 820 840 830
MRL 0.700 0.700 0.700 0.700
Total Kjeldahl Nitrogen mg/L 590 730 580 570
MRL
3 3
3 3
Chemical Oxygen Demand mg/L 9200 12000 5100 7000
MRL 800 400 400 200
Total Oil & Grease MG/KG 26 63 35 53
MRL
5 5
5 5
Phenolics, Total mg/L 6.3 N/A 7.1 6.1
MRL 0.280 - 0.700 0.700
Total Dissolved Solids mg/L 3500 4800 3400 4400
MRL 10 10 10 10
Total Suspended Solids mg/L 2900 7400 2100 3200
MRL 10 10 10 10
Volatile Suspended Solids mg/L 2400 6400 1300 2600
MRL 10 10 10 10
Formaldehyde ug/l 570 3200 2000 350
MRL 400 400 400 400
PPC Sample #1 PPC Sample #2 PPC Sample #3 PPC Sample #4 PPC Sample #5 PPC Sample #6 3/19/25 9:23 3/20/25 8:57 3/25/25 12:33 4/2/25 7:34 4/14/25 11:25 4/14/25 16:00 BOD mg/L 2700 1400 1200 2600 220 3700
MRL 44 4 4 4 4
Chloride mg/L 990 540 150 860 190 390
MRL 400 200 8 400 4 200
Sulfate mg/L 570 ND 43 520 35 150
MRL 400 200 8.0 400.0 4.0 4.0
Hexavalent Chromium ug/L ND ND ND ND ND ND
MRL 4 20 10 10 1 1
Mercury mg/L ND ND ND 0.0012 0.0016 ND
MRL 0.001 0.001 0.000 0.001 0.001 0.001
Boron mg/L ND ND 0.2 0.37 0.32 0.4
MRL 0.400 0.400 0.200 0.200 0.200 0.200
Iron mg/L 1.3 0.77 1.6 1.1 64 5.7
MRL 0.200 0.200 0.100 0.100 0.100 0.100
Sodium mg/L 890 440 150 690 150 270
MRL 22 1 1 1 1
Aluminium mg/L 1.1 0.58 6.5 ND 5 3.5
MRL 11 0 1 1 1
Cadmium mg/L ND ND ND ND ND ND
MRL 0.020 0.010 0.002 0.025 0.010 0.010
Chromium mg/L ND ND 0.0065 ND ND ND
MRL 0.060 0.030 0.006 0.075 0.030 0.030
Cobalt mg/L ND ND ND ND ND ND
MRL 0.020 0.010 0.002 0.025 0.010 0.010
Copper mg/L ND 0.021 0.44 0.092 1 0.6
MRL 0.040 0.020 0.004 0.050 0.020 0.020
Lead mg/L ND ND 0.004 ND 0.026 0.029
MRL 0.020 0.010 0.002 0.025 0.010 0.010
Nickel mg/L ND ND 0.012 ND 0.049 0.03
MRL 0.040 0.020 0.004 0.050 0.020 0.020
Silver mg/L ND ND ND ND ND ND
MRL 0.020 0.010 0.002 ,025 0.010 0.010
Zinc mg/L 0.91 0.74 0.5 0.85 2.6 3
MRL 0.100 0.050 0.010 0.120 0.250 0.250
Chromium III mg/L ND ND 0.0065 ND ND ND
MRL 0.004 0.020 0.006 0.010 0.001 0.001
pH @ 25 C pH Units 8.36 8.23 6.82 8.23 7.67 6.88
MRL 0.100 0.100 0.100 0.100 0.100 0.100
Temperature During pH Sample
Analysis °C 22 22 20 20 22 21
MRL 11 1 1 1 1
Pacific Petroleum
PPC Sample #1 PPC Sample #2 PPC Sample #3 PPC Sample #4 PPC Sample #5 PPC Sample #6 3/19/25 9:23 3/20/25 8:57 3/25/25 12:33 4/2/25 7:34 4/14/25 11:25 4/14/25 16:00 Pacific Petroleum
Specific Conductance (EC) @ 25 C umhos/cm 15000 8300 2000 13000 3300 7800 MRL 22 2 2 2 2
Total Alkalinity mg/L 6000 3000 660 4200 1300 2300
MRL 20 20 20 20 20 20
Ammonia as N mg/L 1500 730 110 800 260 850
MRL 0.700 0.700 0.140 0.700 0.700 1.400
Total Kjeldahl Nitrogen mg/L 660 640 110 1000 310 980
MRL 33 1 3 3 6
Chemical Oxygen Demand mg/L 8300 2800 2800 6500 2200 12000 MRL 400 400 80 400 200 400
Total Oil & Grease MG/KG 445 41 310 54 50 220
MRL 1005 5 5 5 5
Phenolics, Total mg/L 7.6 4.1 0.62 6.5 0.47 3.2
MRL 0.280 0.280 0.280 0.700 0.350 0.700
Total Dissolved Solids mg/L 4700 2700 860 4300 950 2200 MRL 10 10 10 10 10 10
Total Suspended Solids mg/L 1500 1100 610 1900 150 2800 MRL 10 10 10 10 10 10
Volatile Suspended Solids mg/L 1200 1100 550 1200 120 2600 MRL 10 10 10 10 10 10
Formaldehyde ug/l 2700 380 400 2800 ND ND
MRL 400 400 400 400 400 400
Portable Johns ND
Sample #1
Portable Johns ND
Sample #2
Portable Johns ND
Sample #3
Portable Johns ND
Sample #4
3/12/25 9:36 3/18/25 9:54 3/24/25 9:28 4/9/25 0:00
BOD mg/L 4500 4100 3600 4200
MRL 4 4 4 4
Chloride mg/L 1200 1200 1200 1300
MRL 400 400 80 400
Sulfate mg/L 510 550 450 490
MRL 400 20 80.0 400.0
Hexavalent Chromium ug/L ND ND ND ND
MRL 50 40 10 10
Mercury mg/L ND ND ND ND
MRL 0.001 0.001 0.001 0.001
Boron mg/L 0.42 ND 0.46 0.43
MRL 0.200 0.400 0.400 0.200
Iron mg/L 2.7 2.2 2.3 2.5
MRL 0.100 0.200 0.200 0.100
Sodium mg/L 730 860 770 780
MRL 1 2 2 1
Aluminium mg/L 1.7 1.4 1.2 1.3
MRL 1 1 1 1
Cadmium mg/L ND ND ND ND
MRL 0.010 0.020 0.010 0.010
Chromium mg/L ND ND ND ND
MRL 0.030 0.060 0.030 0.030
Cobalt mg/L ND ND ND ND
MRL 0.010 0.020 0.010 0.010
Copper mg/L 0.14 0.079 0.078 0.1
MRL 0.020 0.040 0.020 0.020
Lead mg/L ND ND ND ND
MRL 0.010 0.020 0.010 0.010
Nickel mg/L 0.034 ND 0.028 0.034
MRL 0.020 0.040 0.020 0.020
Silver mg/L ND ND ND ND
MRL 0.010 0.020 0.010 0.010
Zinc mg/L 1.5 1.1 0.6 0.89
MRL 0.050 0.100 0.050 0.050
Chromium III mg/L ND ND ND ND
MRL 0.030 0.040 0.010 0.010
pH @ 25 C pH Units 8.03 8.08 8.26 8.15
MRL 0.100 0.100 0.100 0.100
Temperature During pH Sample
Analysis °C 22 21 20 21
MRL 1 1 1 1
Portable Johns
Portable Johns ND
Sample #1
Portable Johns ND
Sample #2
Portable Johns ND
Sample #3
Portable Johns ND
Sample #4
3/12/25 9:36 3/18/25 9:54 3/24/25 9:28 4/9/25 0:00
Portable Johns
Specific Conductance (EC) @ 25 C umhos/cm 16000 17000 17000 18000 MRL 2 2 2 2
Total Alkalinity mg/L 6100 6400 6000 6800
MRL 20 20 20 20
Ammonia as N mg/L 1400 280 1400 1400
MRL 0.700 0.140 0.700 0.700
Total Kjeldahl Nitrogen mg/L 630 620 680 960
MRL 3 3 3 3
Chemical Oxygen Demand mg/L 13000 8700 9000 14000
MRL 1000 400 400 400
Total Oil & Grease MG/KG 170 201 35 79
MRL 5 100 5 5
Phenolics, Total mg/L 16 14 22 18
MRL 1.400 1.400 1.400 7.000
Total Dissolved Solids mg/L 5000 6200 5500 6000
MRL 10 10 10 10
Total Suspended Solids mg/L 8200 3600 1700 4300
MRL 10 10 10 10
Volatile Suspended Solids mg/L 7300 3100 1400 3800
MRL 10 10 10 10
Formaldehyde ug/l 710 6100 3800 5100
MRL 400 400 400 400
Al's Septic ND Sample
#1
Al's Septic ND Sample
#2
Al's Septic ND Sample
#3
Al's Septic ND Sample
#4
3/10/25 10:42 3/10/25 11:17 3/11/25 10:45 3/25/25 11:10 BOD mg/L 590 2300 2200 760
MRL 4 4 4 4
Chloride mg/L 410 410 2000 98
MRL 80 80 200 20
Sulfate mg/L 53 32 140 6.7
MRL 8 8 20.0 0.4
Hexavalent Chromium ug/L ND ND nd ND
MRL 1 1 2 10
Mercury mg/L ND 0.0047 ND 0.0018
MRL 0.001 0.001 0.001 0.001
Boron mg/L 0.21 0.82 0.25 0.39
MRL 0.200 0.200 0.200 0.200
Iron mg/L 20 80 230 23
MRL 0.100 0.100 0.100 0.100
Sodium mg/L 220 240 840 80
MRL 1 1 25 1
Aluminium mg/L 19 53 29 9.7
MRL 3 10 3 0
Cadmium mg/L ND 0.018 ND ND
MRL 0.002 0.010 0.002 0.002
Chromium mg/L 0.04 0.15 0.041 0.023
MRL 0.006 0.030 0.006 0.006
Cobalt mg/L 0.0024 0.018 0.0069 0.0046
MRL 0.002 0.010 0.002 0.002
Copper mg/L 0.15 4.5 0.11 0.054
MRL 0.004 0.400 0.004 0.004
Lead mg/L ND 0.085 0.013 0.003
MRL 0.002 0.010 0.002 0.002
Nickel mg/L 0.048 0.25 0.18 0.051
MRL 0.004 0.020 0.004 0.004
Silver mg/L ND ND 0.003 ND
MRL 0.002 0.010 0.002 0.002
Zinc mg/L 7.4 25 8.3 4.9
MRL 0.250 1.000 0.250 0.500
Chromium III mg/L 0.04 0.15 0.041 0.023
MRL 0.001 0.001 0.002 0.006
pH @ 25 C pH Units 7.38 6.68 6.75 7.23
MRL 0.100 0.100 0.100 0.100
Temperature During pH Sample
Analysis °C 20 20 20 21
MRL 1 1 1 1
Al's Septic
Al's Septic ND Sample
#1
Al's Septic ND Sample
#2
Al's Septic ND Sample
#3
Al's Septic ND Sample
#4
3/10/25 10:42 3/10/25 11:17 3/11/25 10:45 3/25/25 11:10 Al's Septic
Specific Conductance (EC) @ 25 C umhos/cm 2500 2200 6100 1500 MRL 2 2 2 2
Total Alkalinity mg/L 790 810 680 680
MRL 20 20 20 20
Ammonia as N mg/L 110 140 190 110
MRL 0.700 0.700 1.400 0.700
Total Kjeldahl Nitrogen mg/L 400 670 1000 280
MRL 3 3 6 3
Chemical Oxygen Demand mg/L 9700 16000 35000 6700
MRL 400 800 800 400
Total Oil & Grease MG/KG 210 1110 5160 456
MRL 5 100 100 100
Phenolics, Total mg/L 0.67 0.98 1.8 0.52
MRL 0.280 0.280 0.280 0.280
Total Dissolved Solids mg/L 1200 1800 2600 800
MRL 10 10 10 10
Total Suspended Solids mg/L 7400 20000 36000 3500
MRL 10 10 10 10
Volatile Suspended Solids mg/L 17000 810 28000 2700
MRL 10 10 10 10
Formaldehyde ug/l 180 3000 190 470
MRL 400 400 400 400
I&G Sample #1 I&G Sample #2
3/20/25 8:08 4/14/25 10:41
BOD mg/L 870 2100
MRL 4 4
Chloride mg/L 820 1200
MRL 80 200
Sulfate mg/L ND 32
MRL 80 8
Hexavalent Chromium ug/L ND ND
MRL 20 1
Mercury mg/L ND 0.0074
MRL 0.001 0.001
Boron mg/L 0.22 1.1
MRL 0.100 0.200
Iron mg/L 6 53
MRL 0.050 0.100
Sodium mg/L 470 740
MRL 5 1
Aluminium mg/L 9 67
MRL 0 25
Cadmium mg/L ND 0.047
MRL 0.002 0.010
Chromium mg/L 0.012 0.19
MRL 0.006 0.030
Cobalt mg/L ND 0.028
MRL 0.002 0.010
Copper mg/L 0.2 15
MRL 0.004 1.000
Lead mg/L ND 0.24
MRL 0.002 0.010
Nickel mg/L 0.03 0.29
MRL 0.004 0.020
Silver mg/L ND 0.028
MRL 0.002 0.010
Zinc mg/L 2.8 49
MRL 0.100 2.500
Chromium III mg/L 0.012 0.19
MRL 0.006 0.001
pH @ 25 C pH Units 7.36 6.93
MRL 0.100 0.100
Temperature During pH Sample
Analysis °C 21 22
MRL 1 1
Ingraham and Greene
I&G Sample #1 I&G Sample #2
3/20/25 8:08 4/14/25 10:41
Ingraham and Greene
Specific Conductance (EC) @ 25 C umhos/cm 3900 5000
MRL 2 2
Total Alkalinity mg/L 1700 1200
MRL 20 20
Ammonia as N mg/L 89 170
MRL 0.700 1.400
Total Kjeldahl Nitrogen mg/L 230 620
MRL 3 6
Chemical Oxygen Demand mg/L 4500 13000
MRL 400 400
Total Oil & Grease MG/KG 884 460
MRL 100 100
Phenolics, Total mg/L 0.69 0.35
MRL 0.280 0.280
Total Dissolved Solids mg/L 2100 2000
MRL 10 10
Total Suspended Solids mg/L 3800 8600
MRL 10 10
Volatile Suspended Solids mg/L 2800 6500
MRL 10 10
Formaldehyde ug/l 490 270
MRL 400 400
Harvey's
HHNDSample #1
Harvey's HH ND
Sample #2
Harvey's HH ND
Sample #3
Harvey's HH ND
Sample #4
3/11/25 9:08 3/18/25 8:38 3/19/25 8:09 3/19/25 8:09
BOD mg/L 1900 1900 3700 7600
MRL 4 4 4 4
Chloride mg/L 670 730 1200 1100
MRL 200 200 400 400
Sulfate mg/L 250 ND ND 250
MRL 20 200 400.0 8.0
Hexavalent Chromium ug/L ND ND ND ND
MRL 50 10 20 20
Mercury mg/L ND ND ND ND
MRL 0.002 0.001 0.001 0.001
Boron mg/L 0.15 0.24 ND 0.64
MRL 0.100 0.200 0.400 0.400
Iron mg/L 0.51 1 0.93 5.5
MRL 0.050 0.100 0.200 0.200
Sodium mg/L 180 410 610 700
MRL 1 1 2 2
Aluminium mg/L ND ND ND 63
MRL 1 1 1 1
Cadmium mg/L ND ND ND ND
MRL 0.010 0.010 0.020 0.020
Chromium mg/L ND ND ND ND
MRL 0.030 0.020 0.060 0.060
Cobalt mg/L ND ND ND ND
MRL 0.010 0.010 0.020 0.020
Copper mg/L 0.077 0.063 0.11 0.049
MRL 0.020 0.020 0.040 0.040
Lead mg/L ND ND ND ND
MRL 0.010 0.010 0.020 0.020
Nickel mg/L ND ND ND ND
MRL 0.020 0.020 0.040 0.040
Silver mg/L ND ND ND ND
MRL 0.010 0.010 0.020 0.020
Zinc mg/L 0.57 0.97 0.98 5.7
MRL 0.050 0.050 0.100 0.500
Chromium III mg/L ND ND ND ND
MRL 0.030 0.010 0.020 0.020
pH @ 25 C pH Units 8.73 8.45 8.61 8.09
MRL 0.100 0.100 0.100 0.200
Temperature During pH Sample
Analysis °C 20 22 21 20
MRL 1 1 1 1
Harverys Honey Huts
Harvey's
HHNDSample #1
Harvey's HH ND
Sample #2
Harvey's HH ND
Sample #3
Harvey's HH ND
Sample #4
3/11/25 9:08 3/18/25 8:38 3/19/25 8:09 3/19/25 8:09
Harverys Honey Huts
Specific Conductance (EC) @ 25 C umhos/cm 8400 9100 15000 14000 MRL 2 2 2 2
Total Alkalinity mg/L 3400 3500 6200 4800
MRL 20 20 20 20
Ammonia as N mg/L 740 830 220 1800
MRL 0.280 0.700 0.140 1.400
Total Kjeldahl Nitrogen mg/L 450 880 580 1200
MRL 1 3 3 6
Chemical Oxygen Demand mg/L 4600 3200 6400 25000
MRL 400 400 400 800
Total Oil & Grease MG/KG 31 40 40 675
MRL 5 5 5 100
Phenolics, Total mg/L 7.6 6.3 14 19
MRL 0.350 0.280 1.400 1.800
Total Dissolved Solids mg/L 2500 3000 340 320
MRL 10 10 10 10
Total Suspended Solids mg/L 990 990 1400 9500
MRL 10 10 10 10
Volatile Suspended Solids mg/L 830 850 1200 8400
MRL 10 10 10 10
Formaldehyde ug/l 310 1700 1800 9800
MRL 400 400 400 400
Marborg ND Sample
#1
Marborg ND Sample
#2
Marborg ND Sample
#3
Marborg ND Sample
#4
3/10/25 10:03 4/2/25 12:03 4/3/25 9:59 4/8/25 8:34
BOD mg/L 3000 2800 370 16000
MRL 4 4 4 4
Chloride mg/L 500 1500 770 950
MRL 80 400 200 200
Sulfate mg/L 90 ND 150 ND
MRL 80 400 20.0 20.0
Hexavalent Chromium ug/L ND ND ND ND
MRL 1 10 10 10
Mercury mg/L ND 0.0014 ND 0.0073
MRL 0.001 0.001 0.001 0.001
Boron mg/L 0.58 0.34 0.54 ND
MRL 0.200 0.100 0.500 2.500
Iron mg/L 90 5.6 0.93 280
MRL 0.100 0.050 0.250 1.200
Sodium mg/L 240 470 440 680
MRL 1 5 3 12
Aluminium mg/L 59 12 0.48 120
MRL 5 1 0 1
Cadmium mg/L ND ND ND 0.0081
MRL 0.010 0.010 0.005 0.025
Chromium mg/L 0.093 0.046 ND 0.49
MRL 0.030 0.030 0.015 0.075
Cobalt mg/L ND 0.022 ND 0.0072
MRL 0.010 0.010 0.005 0.025
Copper mg/L 2.1 5.4 0.025 21
MRL 0.020 0.100 0.010 0.200
Lead mg/L 0.022 0.039 ND 0.34
MRL 0.010 0.010 0.005 0.025
Nickel mg/L 0.14 0.072 ND 0.62
MRL 0.020 0.020 0.010 0.050
Silver mg/L ND ND ND 0.072
MRL 0.010 0.010 0.005 0.050
Zinc mg/L 8 7 0.22 0.072
MRL 0.500 0.250 0.025 0.025
Chromium III mg/L 0.093 0.046 ND 0.49
MRL 0.001 0.010 0.010 0.010
pH @ 25 C pH Units 7.02 8.99 8.19 6.33
MRL 0.100 0.100 0.100 0.100
Temperature During pH Sample
Analysis °C 20 21 21 22
MRL 1 1 1 1
Marborg
Marborg ND Sample
#1
Marborg ND Sample
#2
Marborg ND Sample
#3
Marborg ND Sample
#4
3/10/25 10:03 4/2/25 12:03 4/3/25 9:59 4/8/25 8:34
Marborg
Specific Conductance (EC) @ 25 C umhos/cm 2300 16000 8200 12000 MRL 2 2 2 2
Total Alkalinity mg/L 1100 11000 2900 5400
MRL 20 20 20 20
Ammonia as N mg/L 120 910 670 2700
MRL 0.700 0.700 0.700 1.400
Total Kjeldahl Nitrogen mg/L 560 1700 670 1200
MRL 3 6 3 6
Chemical Oxygen Demand mg/L 19000 12000 1700 78000
MRL 1000 800 400 2000
Total Oil & Grease MG/KG 2990 520 5.8 1520
MRL 100 5 5 100
Phenolics, Total mg/L 2.1 6.1 0.44 9
MRL 0.280 0.350 0.350 1.800
Total Dissolved Solids mg/L 1900 5300 2900 5500
MRL 10 10 10 10
Total Suspended Solids mg/L 14000 8500 410 54000
MRL 10 10 10 10
Volatile Suspended Solids mg/L 4400 6400 330 37000
MRL 10 10 10 10
Formaldehyde ug/l 600 2800 100 9300
MRL 400 400 40 4000
Valley Septic ND
Sample #1
Valley Septic ND
Sample #2
Valley Septic ND
Sample #3
Valley Septic ND
Sample #4
3/18/25 9:01 3/24/25 9:04 4/1/25 9:26 4/14/25 12:09
BOD mg/L 1300 1200 540 2900
MRL 4 4 4 4
Chloride mg/L 1000 190 130 220
MRL 80 80 8 80
Sulfate mg/L 18 130 18 55
MRL 8 80 0.4 4.0
Hexavalent Chromium ug/L ND ND ND ND
MRL 2 10 10 1
Mercury mg/L 0.0032 ND ND 0.0012
MRL 0.001 0.001 0.001 0.001
Boron mg/L 0.38 0.78 0.12 0.25
MRL 0.200 0.200 0.100 0.200
Iron mg/L 73 15 4.9 15
MRL 0.100 0.100 0.050 0.100
Sodium mg/L 490 270 61 160
MRL 1 1 1 1
Aluminium mg/L 55 20 9.7 9.1
MRL 2 2 0 1
Cadmium mg/L ND ND ND ND
MRL 0.004 0.002 0.004 0.010
Chromium mg/L 0.078 0.047 0.019 0.048
MRL 0.012 0.006 0.012 0.030
Cobalt mg/L 0.0086 0.0057 ND ND
MRL 0.004 0.002 0.004 0.010
Copper mg/L 0.69 0.11 0.48 1.1
MRL 0.008 0.004 0.008 0.020
Lead mg/L 0.0068 0.0025 0.0084 ND
MRL 0.004 0.002 0.004 0.010
Nickel mg/L 0.15 0.089 0.032 0.042
MRL 0.008 0.004 0.008 0.020
Silver mg/L ND ND ND ND
MRL 0.004 0.002 0.004 0.010
Zinc mg/L 15 5.1 2.3 4.1
MRL 1.000 0.200 1.000 0.500
Chromium III mg/L 0.078 0.047 0.019 0.048
MRL 0.002 0.006 0.010 0.001
pH @ 25 C pH Units 6.96 7.15 7.45 7.04
MRL 0.100 0.100 0.100 0.100
Temperature During pH Sample
Analysis °C 21 22 21 22
MRL 1 1 1 1
Valley Septic
Valley Septic ND
Sample #1
Valley Septic ND
Sample #2
Valley Septic ND
Sample #3
Valley Septic ND
Sample #4
3/18/25 9:01 3/24/25 9:04 4/1/25 9:26 4/14/25 12:09
Valley Septic
Specific Conductance (EC) @ 25 C umhos/cm 4100 1800 2200 2900 MRL 2 2 2 2
Total Alkalinity mg/L 970 900 940 1100
MRL 2 20 20 20
Ammonia as N mg/L 150 100 140 190
MRL 0.700 1.400 0.280 1.400
Total Kjeldahl Nitrogen mg/L 630 510 230 340
MRL 3 6 3 6
Chemical Oxygen Demand mg/L 19000 12000 3100 9600
MRL 800 400 200 400
Total Oil & Grease MG/KG 2600 875 34 150
MRL 100 100 5 5
Phenolics, Total mg/L 0.71 0.5 0.89 0.65
MRL 0.280 0.280 0.140 0.350
Total Dissolved Solids mg/L 2800 1500 880 1500
MRL 10 10 10 10
Total Suspended Solids mg/L 19000 9000 2000 7100
MRL 10 10 10 10
Volatile Suspended Solids mg/L 13000 6900 1900 6300
MRL 10 10 10 10
Formaldehyde ug/l 3600 630 210 100
MRL 400 400 400 100
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX F HEADWORKS SAMPLING RESULTS - JUNE
2025
Summary Date On Date Off Duration Sample ID Location
TSS
(mg/L)
TDS
(mg/L)
NH3-N
(mg/L)
Total -N
(mg/L)
NH3-N
(mg/L)
TKN
(mg/L)
Mon - 6/9/2025 6/10/2025 1400-1400 Junction Box A Trunk Line 368 1124 41.8 71.7 47 64 Tues 6/9/2025 6/10/2025 1400-1400 Junction Box B Bar Screen 396 1052 50.1 77.0 54 75 Wed- 6/11/2025 6/12/2025 1400-1400 Junction Box A Trunk Line 351 1064 46.2 60.9 47 68 Thurs 6/11/2025 6/12/2025 1400-1400 Junction Box B Bar Screen 398 1232 51.8 68.2 53 75 6/15/2025 6/16/2025 630--630 Junction Box A Trunk Line 338 1048 54.7 66.8 - - 6/15/2025 6/16/2025 630--630 Junction Box B Bar Screen 369 1032 52.2 67.5 - - Tues- 6/17/2025 6/18/2025 930-930 Junction Box A Trunk Line 311 1124 51.5 68.3 - - Wed 6/17/2025 6/18/2025 930-930 Junction Box B Bar Screen 506 1112 59.5 77.9 - - 6/21/2025 6/22/2025 645-645 Junction Box A Trunk Line 273 1156 49.7 70.5 - - 6/21/2025 6/22/2025 645-645 Junction Box B Bar Screen 335 1084 50.9 69.6 - - Friday - 6/26/2025 6/27/2025 600-600 Junction Box A Trunk Line 287 1004 51.5 70.7 - - Captured 6/26/2025 6/27/2025 600-600 Junction Box B Bar Screen 547 1080 58.9 77.6 - - Monday - 6/29/2025 6/30/2025 600-600 Junction Box A Trunk Line 313 1068 49.4 68.9 49 68 Captured 6/29/2025 6/30/2025 600-600 Junction Box B Bar Screen 419 1080 56.0 75.8 55 78 Responsible Laboratory
June 2025 Sampling Plan Data CSML OEC
Sun - No
Septage
Sat - No
Septage
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN
APPENDIX G COMPARISON OF LOADING EVENTS
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN G-1
pw://Carollo/CA/Santa Maria/202301-000000/03 Reports and Studies/02 Deliverables/Master Plan/Volume 13/Appendix G.docx
COMPARISON OF LOADING EVENTS
Table F.1 indicates the ammonia (NH3) loading comparison amongst the available data and across the sampling events.
Table F.1 Comparison of NH3 Loading From Different Sampling Events Sampling Event
NH3 Concentration
NH3 Loading
(lb/day)
Percentage of
Septage Contribution Upstream
(Pre-Septage, mg/L)
Downstream
(Post-Septage, mg/L)
September 2024 72 76 275(1) 7%
Major Haulers - - 128(2) -
June 2025 49 55 344 12%
August 2025 49 58 499 17%
Notes:
lb/day - pounds per day; mg/L - milligrams per liter
(1) Loading adjusted for a 24-hour composite flow, using the month's average from the sampled 8-hour composite. (2) Major Haulers represent 57% of the septage flow received in a standard 24-hour period.
The discrepancy in NH3 loading may be attributed to different flows observed over the sampling period.
The observed concentrations over the sampling events in June and August are similar.
The total Kjeldahl nitrogen (TKN) concentrations and loadings from the September and June events are summarized in Table F.2.
Table F.2 Comparison of TKN Loading From Different Sampling Events Sampling Event
TKN
TKN Loading
(lb/day)
Percentage of
Septage Contribution Upstream
(Pre-Septage, mg/L)
Downstream
(Post-Septage, mg/L)
September 2024 98 111 697(1) 12%
June 2025 66 76 495 14%
Major Haulers - - 142(2) -
Notes:
(1) Loading adjusted for a 24-hour composite flow, using the month's average from the sampled 8-hour composite. (2) Major Haulers represent 57% of the septage flow received in a standard 24-hour period.
Table F.3 indicates the biochemical oxygen demand (BOD) loading comparison amongst the available data and across the sampling events. Table F.4 indicates that the septage contribution of total suspended solids (TSS) across the sampling events.
VOLUME 13 / SUPPORT FACILITIES
OCTOBER 2026 / FINAL / CAROLLO
CITY OF SANTA MARIA
WASTEWATER TREATMENT PLANT MASTER PLAN G-2
Table F.3 Comparison of BOD Loading From Different Sampling Events Sampling Event
BOD
BOD Loading
(lb/day)
Percentage of
Septage Contribution Upstream
(Pre-Septage, mg/L)
Downstream
(Post-Septage, mg/L)
September 2024 380 524 7,820(1) 28%
Major Haulers - - 612 -
July/August 2025 393 469 4,179 15%
Notes:
(1) Loading adjusted for a 24-hour composite flow, using the month's average from the sampled 8-hour composite.
Table F.4 Comparison of TSS Loading From Different Sampling Events Sampling Event
TSS
TSS Loading
(lb/day)
Percentage of
Septage Contribution Upstream
(Pre-Septage, mg/L)
Downstream
(Post-Septage, mg/L)
Major Haulers - - 2,176 -
June 2025 320 453 7,231 30%
July/August 2025 311 442 7,134 30%
September 2026
INITIAL STUDY CHECKLIST
SANTA MARIA WASTEWATER TREATMENT PLANT
IMPROVEMENTS PROJECT
SANTA MARIA, CALIFORNIA
Attachment G
This page intentionally left blank
September 2026
I NITIAL STUDY CHECKLIST
SANTA MARIA WASTEWATER TREATMENT PLANT
IMPROVEMENTS PROJECT
SANTA MARIA, CALIFORNIA
Submitted to:
Carollo Engineers
3150 Bristol Street, Suite 500
Costa Mesa, California 92626
Prepared by:
LSA
LSA Associates, Inc.
860 Walnut Street, Suite B
San Luis Obispo, California 93401
(805) 782-0745
Project No. 20241463
This page intentionally left blank
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) i
TABLE OF CONTENTS
TABLE OF CONTENTS ............................................................................................................................... i FIGURES AND TABLES ............................................................................................................................ iii LIST OF ABBREVIATIONS AND ACRONYMS ............................................................................................. v
1.0 PROJECT INFORMATION ................................................................................... 1-1
2.0 PROJECT DESCRIPTION ..................................................................................... 2-1
2.1 Project Site ........................................................................................................................ 2-1
2.2 Project Background ........................................................................................................... 2-8
2.3 Project Purpose ................................................................................................................. 2-9
2.4 Proposed Project............................................................................................................... 2-9
2.5 Project Approvals............................................................................................................ 2-18
3.0 ENVIRONMENTAL FACTORS POTENTIALLY AFFECTED......................................... 3-1
3.1 Determination ................................................................................................................... 3-1
4.0 CEQA ENVIRONMENTAL CHECKLIST .................................................................. 4-1
4.1 Aesthetics.......................................................................................................................... 4-1
4.2 Agriculture and Forestry Resources.................................................................................. 4-4
4.3 Air Quality ......................................................................................................................... 4-8
4.4 Biological Resources........................................................................................................ 4-19
4.5 Cultural Resources........................................................................................................... 4-29
4.6 Energy.............................................................................................................................. 4-35
4.7 Geology and Soils............................................................................................................ 4-39
4.8 Greenhouse Gas Emissions.............................................................................................4-45
4.9 Hazards and Hazardous Materials...................................................................................4-52
4.10 Hydrology and Water Quality..........................................................................................4-57
4.11 Land Use and Planning .................................................................................................... 4-68
4.12 Mineral Resources........................................................................................................... 4-70
4.13 Noise................................................................................................................................ 4-72
4.14 Population and Housing .................................................................................................. 4-84
4.15 Public Services................................................................................................................. 4-86
4.16 Recreation ....................................................................................................................... 4-89
4.17 Transportation................................................................................................................. 4-91
4.18 Tribal Cultural Resources................................................................................................. 4-95
4.19 Utilities and Service Systems...........................................................................................4-98
4.20 Wildfire.......................................................................................................................... 4-102
4.21 Mandatory Findings of Significance ..............................................................................4-105
5.0 LIST OF PREPARERS........................................................................................... 5-1
5.1 LSA Associates, Inc. ........................................................................................................... 5-1
6.0 REFERENCES..................................................................................................... 6-1
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) ii
APPENDICES
A: CALEEMOD OUTPUT WORKSHEETS
B: BIOLOGICAL RESOURCES TECHNICAL MEMORANDUM AND HABITAT ASSESSMENT C: NOISE MEASUREMENT SHEETS
D: OPERATIONAL NOISE GRAPHIC
E: RESPONSE TO COMMENTS
F: MITIGATION MONITORING AND REPORTING PROGRAM
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) iii
FIGURES AND TABLES
FIGURES
Figure 2-1: Regional Location .............................................................................................................. 2-3 Figure 2-2: Project Site ........................................................................................................................ 2-5 Figure 2-3: Proposed Near-Term Project...........................................................................................2-11 Figure 2-4: Proposed Phase 1 Improvements....................................................................................2-15 Figure 2-5: Proposed Phase 1 and Phase 2 Improvements...............................................................2-19 Figure 4-1: Noise Monitoring Locations ............................................................................................4-76 TABLES
Table 2.A: Existing WWTP Facilities..................................................................................................... 2-7 Table 2.B: Structures to Be Removed During Phase 1 Construction .................................................2-13 Table 2.C: Structures Planned to Be Completed During Phase 1 Construction.................................2-17 Table 2.D: Potential Permits and Approvals ......................................................................................2-18 Table 4.A: Project Construction Emissions ........................................................................................4-13 Table 4.B Project Operation Emissions..............................................................................................4-17 Table 4.C: Greenhouse Gas Operational Emissions...........................................................................4-48 Table 4.D: Construction Vibration Damage Criteria ..........................................................................4-74 Table 4.E: Long-Term 24-Hour Ambient Noise Monitoring Results...................................................4-75 Table 4.F: Typical Maximum Construction Equipment Noise Levels (Lmax)........................................4-80 Table 4.G: Noise Levels By Construction Phase .................................................................................4-81 Table 4.H: Vibration Source Amplitudes for Construction Equipment..............................................4-82
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) iv This page intentionally left blank
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) v
LIST OF ABBREVIATIONS AND ACRONYMS
AAQS ambient air quality standards
AB Assembly Bill
af acre-feet
ALUCP Airport Land Use Compatibility Plan
APCD Air Pollution Control District
APN Assessor’s Parcel Number
AQAP Air Quality Attainment Plan
ATC Authority to Construct
Basin Plan Water Quality Control Plan
bgs below ground surface
Bio Memo Biological Resources Technical Memorandum
BMP Best Management Practice
BOD Biological Oxygen Demand
Btu British thermal units
CAL FIRE California Department of Forestry and Fire Protection Cal/OSHA California Occupational Safety and Health Administration CalARP Program California Accidental Release Prevention Program CalEEMod California Emission Estimator Model
CALGreen California Green Building Standards Code
CalRecycle California Department of Resources Recycling and Recovery Caltrans California Department of Transportation
CARB California Air Resources Board
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
vi P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) CBC California Building Code
CCAA California Clean Air Act
CCIC Central Coast Information Center
CCR California Code of Regulations
CDFW California Department of Fish and Wildlife
CEC California Energy Commission
CEQA California Environmental Quality Act
CF Community Facilities
CGS California Geological Survey
CH4 methane
City City of Santa Maria
CNDDB California Natural Diversity Database
CNEL community noise equivalent level
CO carbon monoxide
CO2 carbon dioxide
CO2e carbon dioxide equivalents
Construction
General Permit
NPDES General Permit for Stormwater Discharges Associated with Construction and Land Disturbance Activities, Order No. 2022-0057-DWQ, NPDES No. CAS000002
CRHR California Register of Historical Resources
CUPA Certified Unified Program Agency
CWA Clean Water Act
dB decibel(s)
dBA A-weighted decibel(s)
DOC California Department of Conservation
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) vii DPM diesel particulate matter
DWR California Department of Water Resources
EO Executive Order
EPA United States Environmental Protection Agency
FCAA Federal Clean Air Act
FEMA Federal Emergency Management Agency
FHSZ Fire Hazard Severity Zone
FMMP Farmland Mapping and Monitoring Program
FTA Federal Transit Administration
FTA Manual Federal Transit Administration Transit Noise and Vibration Impact Assessment Manual
General Dewatering
Permit
SWRCB’s WQ Order No. 2003-0003-DWQ Statewide General Waste Discharge Requirements (WDRs) for Discharges to Land with a Low Threat to Water Quality
GHG greenhouse gas
GSP Groundwater Sustainability Plan
GWP Global Warming Potential
H2S hydrogen sulfide
HFCs hydrofluorocarbons
HMBP Hazardous Materials Business Plan
hp horsepower
in/sec inch(es) per second
IS Initial Study
kW kilowatt(s)
Ldn day-night average level
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
viii P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) Leq equivalent continuous sound level
LID Low Impact Development
LRA Local Responsibility Area
mgd million gallons per day
MRZ mineral resource zone
N2O nitrous oxide
NAHC Native American Heritage Commission
NO2 nitrogen dioxide
NOX nitrogen oxides
NPDES National Pollution Discharge Elimination System
NRCS Natural Resources Conservation Service
NRHP National Register of Historic Places
O3 ozone
PF Public Facilities
PFCs perfluorocarbons
PG&E Pacific Gas and Electric Company
PM10 particulate matter less than 10 microns in diameter PM2.5 particulate matter less than 2.5 microns in diameter Porter-Cologne Act Porter-Cologne Water Quality Control Act PPV peak particle velocity
PRC Public Resources Code
project Santa Maria Wastewater Treatment Plant Phase 1 Upgrades Project PTO permit to operate
RMS root-mean-square
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) ix ROC reactive organic compounds
RTP Regional Transportation Plan
RWQCB Regional Water Quality Control Board
SB Senate Bill
SBCAG Santa Barbara County Association of Governments
SBCAPCD Santa Barbara County Air Pollution Control District SCCAB South Central Coast Air Basin
SCS Sustainable Communities Strategy
SF6 sulfur hexafluoride
SGMA Sustainable Groundwater Management Act
SLF Sacred Lands File
SLOCAPD San Luis Obispo County Air Pollution Control District SMX Santa Maria Public Airport
SR State Route
SWP State Water Project
SWPPP Stormwater Pollution Prevention Plan
SWRCB State Water Resources Control Board
TACs toxic air contaminants
TMDL Total Maximum Daily Load
TSS Total Suspended Solids
US United States Route
USACE United States Army Corps of Engineers
USFWS United States Fish and Wildlife Service
UWMP Urban Water Management Plan
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
x P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) VCAPCD Ventura County Air Pollution Control District
VHFHSZ Very High Fire Hazard Severity Zone
VMT vehicle miles traveled
VOC volatile organic compounds
WDR Waste Discharge Requirement
WOTUS waters of the United States
WWTP Wastewater Treatment Plant
ytt Tribe yak tityu tityu yak tiłhini Northern Chumash Tribe ZE zero emission
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 1-1
1.0 PROJECT INFORMATION
1. Project Title:
Santa Maria Wastewater Treatment Plant Improvements Project
2. Lead Agency Name and Address:
City of Santa Maria
110 East Cook Street
Santa Maria, California 93454
3. Contact Person and Phone Number:
Shad S. Springer, Director of Utilities
Phone: (805) 925-0951, ext. 7211
Email: [email protected]
4. Project Location:
The Santa Maria Wastewater Treatment Plant (WWTP) is located at the west edge of the City of Santa Maria at 601 Black Road, Santa Maria, California, 93458, on land identified as Assessor’s Parcel Number (APN) 113-120-034, approximately 0.5 mile south of West Main Street, which makes up a portion of California State Route (SR) 166. The project site includes the existing WWTP west of Black Road, as well as APNs 117-191-010 and 117-191-013 to the east of Black Road and north of West Stowell Road, and APN 117-820-002 to the east of Black Road and south of West Stowell Road.
5. Project Sponsor’s Name and Address:
City of Santa Maria, Utilities Department
2065 East Main Street
Santa Maria, California 93454
6. General Plan Designation:
Community Facilities (CF)
7. Zoning:
Public Facilities (PF)
8. Description of Project:
The City of Santa Maria (City) proposes to expand and update its existing WWTP to accommodate anticipated growth, provide long-term reliable treatment, and adhere to applicable regulatory requirements, including the updated effluent discharge limits. The project would modify the existing WWTP currently owned and operated by the City at 601 Black Road, Santa Maria, California 93458, and expand onto adjacent land to the east and southeast. A more detailed description of the proposed project is provided in Chapter 2.0, Project Description.
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
1 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -2
9. Surrounding Land Uses and Setting:
The project site is surrounded primarily by existing agricultural fields. A more detailed description of the surrounding land uses is provided in Chapter 2.0, Project Description.
10. Other Public Agencies Whose Approval is Required (e.g., permits, financial approval, or participation agreements):
• City of Santa Maria
• Regional Water Quality Control Board (RWQCB)
• Santa Barbara County Air Pollution Control District
• State Water Resources Control Board
• Santa Barbara County Environmental Health Services (certified by the California Environmental Protection Agency as the Certified Unified Program Agency [CUPA]) • State of California Department of Industrial Relations, Division of Occupational Safety & Health
11. Have California Native American tribes traditionally and culturally affiliated with the project area requested consultation pursuant to Public Resource Code section 21080.3.1? If so, is there a plan for consultation that includes, for example, the determination of significance of impacts to tribal cultural resources, procedures regarding confidentiality, etc.? On August 29, 2025, the City of Santa Maria sent Assembly Bill (AB) 52 outreach letters to the tribes listed in the contact list that was provided by the Native American Heritage Commission (NAHC) on May 7, 2024. The letters, which were sent via certified mail to the tribal contacts, described the project, provided maps of the project site, and invited the tribes to request consultation should they have any concerns. On September 3, 2025, a tribal representative from the yak tityu tityu yak tiłhini Northern Chumash Tribe (ytt Tribe) responded to the tribal consultation letter requesting that the ytt Tribe be removed from the City’s AB 52 consultation list. No other responses were received.
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 2-1
2.0 PROJECT DESCRIPTION
The following describes the proposed Santa Maria WWTP Improvements Project (project) that is the subject of this Initial Study (IS) prepared pursuant to the California Environmental Quality Act (CEQA). The proposed project would modify and expand the existing WWTP as detailed below. The City of Santa Maria is the lead agency for review of the proposed project under CEQA.
2.1 PROJECT SITE
The following describes the project location, existing conditions, surrounding land uses, and regulatory setting.
2.1.1 Project Location
The Santa Maria WWTP is located at the west edge of the City of Santa Maria at 601 Black Road, Santa Maria, California 93458. The current site of the WWTP is identified as APN 113-120-034 and is located approximately 0.5 mile south of West Main Street, which makes up a portion of SR-166. The project site includes the existing WWTP west of Black Road, as well as APNs 117-191-010 and 117- 191-013 to the east of Black Road and north of West Stowell Road, and APN 117-820-002 to the east of Black Road and south of West Stowell Road. The project’s location and regional vicinity are shown on Figure 2-1, Project Location and Regional Vicinity Map, and an aerial photograph of the project site and surrounding land uses is shown on Figure 2-2, Project Site.
The project site makes up an approximately 310-acre irregular shape, including 210 acres west of Black Road (which includes the existing WWTP) and 100 acres east of Black Road. The project site begins near the southeast corner of the intersection of Ray Road and West Main Street, is divided by Black Road and West Stowell Road, and extends to and includes the southeast corner of the intersection of Black Road and West Stowell Road.
Additional agricultural fields and associated infrastructure are located to the north, east, south, and west of the project site. While irrigation ditches are present within the project area, they have no existing downstream connections. An Atlas Performance Industries trailer facility borders the project area to the east, a Santa Maria Railroad right-of-way borders the project area to the south of West Stowell Road, and an auto wrecking yard borders the area to the west along Black Road.
2.1.2 Existing Conditions
Presently, approximately two-thirds of the project site is developed with the existing WWTP, which consists of percolation ponds, pumps, tanks, process areas, and associated buildings.
The existing WWTP has a maximum monthly hydraulic capacity of 13.5 million gallons per day (mgd) and treats on average 6.2 mgd of wastewater from its existing domestic, commercial, and industrial customers. The WWTP treats incoming domestic wastewater through a process of screening and grit removal, primary clarification, primary and secondary trickling filters, secondary clarification, and disposal via percolation ponds. Separate solids handling facilities, including anaerobic digestion, are utilized to process biosolids to Class B requirements before the solids are trucked from the site for
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
2 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -2 This page intentionally left blank
SOURCE: USGS The National Map (2018)
I:\2024\20241463\GIS\Pro\Santa Maria WWTP Project\Santa Maria WWTP Project.aprx (5/16/2025) FIGURE 2-1
Santa Maria Wastewater Treatment
Plant Improvements Project
S A N L U I S
O B I S P O
C O U N T Y
S A N T A
B A R B A R A
C O U N T Y
£¤101
Ã1
Ã227
Ã135 Ã166
Project Vicinity
0 1000 2000
FEET
Project Site
Regional Location Map
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
2 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -4 This page intentionally left blank
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
2 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -6 This page intentionally left blank
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 2-7 disposal at the Santa Maria Regional Landfill or taken to Engel and Gray Composting Facility for composting. The existing WWTP facilities are described below in Table 2.A.
Table 2.A: Existing WWTP Facilities
Facility Type Quantity
Liquids
Septage Receiving Station 1
Bar Screen Facility 1
Grit Chambers 1
Primary Trickling Filters 2
Primary Clarifiers 2
Intermediate Clarifier 1
Secondary Trickling Filters 2
Secondary Clarifiers 2
Percolation Ponds 18
Solids
Solids Thickeners 2
Anaerobic Digesters 4
Gas Flare 2
Sludge Drying Beds 13
Source: Compiled by LSA (2025).
WWTP = wastewater treatment plant
The remaining undeveloped portions of the project site are occupied by interim agricultural uses largely consisting of row crops. The row crop uses, which align with historical uses for the area, were permitted to continue pending the eventual development under the site’s Public Facilities Zoning designation. Several irrigation ditches are also present along the road shoulders and in the WWTP.
According to historic aerial imagery, vegetation within the project site is subject to regular anthropogenic disturbance associated with the operations of the existing facilities (e.g., vegetation clearing, facility maintenance, and agriculture), and the site has remained in its current condition for more than 20 years. The site is generally flat and is approximately 168 feet above mean sea level.
2.1.3 Surrounding Land Uses
As shown on Figure 2-2, the project site is generally bordered by unincorporated County lands to the north, east, south, and west, which are primarily used for agricultural production, including row crops. The surrounding parcels are currently under a Williamson Act contract, with the exception of the incorporated land to the south of the project site, which is currently used for Light, Commercial, and General Manufacturing. Additional other nearby uses include a composting facility; a fertilizer facility; an irrigated pasture; a Humane Society; a small, low-density residential area; and other industrial uses.
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
2 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -8
2.1.4 Regulatory Setting
The project site is designated as Community Facilities (CF) in the City of Santa Maria 1991 General Plan1 as well as the General Plan Update, 2 scheduled for adoption in spring 2026. The CF designation is intended to provide for necessary facilities for use by the public, including schools and government buildings. The project site is zoned Public Facilities (PF). 3 The PF district is designed and intended to provide for those uses and activities that serve the public and are generally conducted by government agencies or charitable and philanthropic nonprofit organizations. Permitted uses within the PF zone include governmental buildings and facilities designed for public use and accommodation; public libraries, museums, and schools and colleges; charitable and philanthropic institutions; cemeteries, crematories or mausoleums; water and wastewater treatment plants, substations, and other public service facilities of a similar nature; uses, buildings, and structures incidental, accessory, and subordinate to permitted uses; churches; student housing; and emergency shelters.
2.2 PROJECT BACKGROUND
The City of Santa Maria Utilities Department oversees the WWTP and provides water and wastewater services to over 23,000 residential and commercial accounts. The City has operated wastewater treatment and disposal facilities at the site on Black Road since the plant was initially built in 1932. Since the initial construction, the plant has been expanded five times to meet the continued growth and demand of the City; expansions occurred in 1948, 1961, 1982, 1996, and 2008. The proposed project includes an additional expansion of the WWTP to meet expected future demands of the City and provide updates and improvements to the existing infrastructure.
The most recent 2008 expansion included construction of a primary clarifier, a primary trickling filter, a digester, a digester control building, a percolation pond pump station, and addition of new equipment such as the emergency generator. In addition to the WWTP itself, the City’s wastewater system includes associated infrastructure, including one lift station and approximately 250 miles of gravity pipelines.
The 2008 expansion enabled the system to handle a peak wet weather flow of 29.5 mgd and to process a max month flow of 13.5 mgd to accommodate existing community and expected growth, provide adequate sewage treatment capabilities, and provide functionally efficient and cost-effective wastewater treatment to serve the community. As Santa Maria continues to grow, further expansion of the existing WWTP is required to accommodate anticipated growth. 1 City of Santa Maria. 1991. Santa Maria General Plan, Land Use Element. August. Amended September 6, 2011. Website: https://www.cityofsantamaria.org/home/showpublisheddocument/610/ 635488452782530000 (accessed May 6, 2025). 2 City of Santa Maria. 2025. Santa Maria Draft General Plan, Land Use Element. August. Website:
https://www.imaginesantamaria.com/_files/ugd/e3bef4_3b8626962f804223a9792ba2a449b6ee.pdf (accessed January 20, 2026). 3 City of Santa Maria. 2005. City of Santa Maria Zoning Map. December 20. Website:
https://www.cityofsantamaria.org/home/showpublisheddocument/10037/638563088414970000 (accessed May 6, 2025).
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 2-9 The Central Coast RWQCB recently issued a new General Permit to the City that requires the WWTP to comply with updated effluent discharge limits. With its current treatment regime, the WWTP does not meet several newly established effluent limits. The proposed project would not only increase the load capacity of the WWTP, allowing it to meet future growth demands, it would also allow the WWTP to meet all applicable discharge requirements under the newly issued General Permit.
2.3 PROJECT PURPOSE
The purpose of the proposed project is to allow the WWTP to meet expected future growth demands within its service area by expanding the size and capacity of the WWTP, as well as allowing the plant to come into compliance with all applicable regulations, including the updated effluent discharge limits.
2.4 PROPOSED PROJECT
The City proposes to modify the existing WWTP to serve the community’s current and future growth.
The City, in coordination with Carollo Engineers, prepared a Wastewater Treatment Plant Master Plan to provide a 35-year road map for the City’s wastewater treatment, disposal, and reuse needs.
The Wastewater Treatment Plant Master Plan updates, replaces, and expands on the existing 1993 Master Plan. As identified in the Wastewater Treatment Plant Master Plan, the proposed project would include three components: (1) near-term projects that must be completed prior to the initiation of Phase 1; (2) Phase 1 Improvements; and (3) Phase 2 Improvements. Each of these components is described below.
2.4.1 Near-Term Project – Percolation Pond Construction Because the existing pond disposal capacity is a physical constraint for the WWTP, one near-term project needs to be undertaken immediately to increase disposal capacity. The near-term project would involve constructing six new percolation ponds, approximately 7 acres each, totaling approximately 42 acres on approximately 100 acres of City-owned land currently being used for interim agricultural production. The new ponds would be located to the east of the existing WWTP across Black Road. Figure 2-3 shows the location and preliminary layout of the proposed percolation ponds. As part of this near-term project, at least one permanent entrance providing access to the ponds would be constructed along Black Road, as shown on Figure 2-3. This entrance would also be used for ingress and egress during project construction.
The depth of the new percolation ponds is expected to vary depending on the geological and morphological qualities of the soil within the project site. Current estimations put the average depth of each pond at approximately 13 feet below grade level. Associated infrastructure, including berms, would vary in height depending on the final grading of the area; however, the maximum berm height is generally estimated to be less than 5 feet above the existing grade across the site.
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
2 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -10 This page intentionally left blank
FIGURE 2-3
Near Term Project – Percolation Pond Construction
Santa Maria Wastewater Treatment Plant Improvements Project I:\2024\20242046\G\Near-Term_Projects1.ai (6/12/2026)
SOURCE: Carollo Engineers, 2025
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
2 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -12 This page intentionally left blank
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 2-13 Table 2.B: Structures Planned to Be Completed
During Near-Term Project Construction
Structures to Be Constructed Quantity
Percolation Ponds 6
Source: Compiled by LSA (2026)
This near-term project is expected to require approximately 879,000 cubic yards of soil excavation, with approximately 703,000 cubic yards of soil off-hauled for disposal. Construction of the near-term project is expected to begin in early 2028 and extend approximately 24 months.
As shown on Figure 2-3, the City is currently installing a 5-acre solar array on the City-owned land, east of the proposed percolation ponds. The solar array is not part of the proposed project and would be constructed prior to initiation of the near-term project.
2.4.2 Phase 1 Improvements
Due to water conservation efforts over the last 15 years, per-capita wastewater flows have decreased and influent organic and nitrogen concentrations have proportionally increased. Phase 1 of the proposed project would retain the peak wet-weather capacity of 29.95 mgd and upgrade the existing facility to treat a higher organic and nitrogen load associated with an annual daily average flow of 10.0 mgd. The upgrade would change the biological treatment regime from a trickling filter system to a nutrient removal activated sludge process. The proposed Phase 1 Improvements are shown on Figure 2-4.
Phase 1 would include upgrades to some existing structures, including the two existing primary clarifiers, two sludge digesters, a gravity thickener, a headworks, a maintenance building, an operations building, and the intermediate clarifier that will be covered and used for storage.
To accommodate the new facilities, some structures would be removed completely. A preliminary list of anticipated structures that would be demolished is shown in Table 2.C.
Table 2.C: Structures to Be Removed
During Phase 1 Construction
Structures to Be Removed Quantity
Primary Trickling Filters 2
Secondary Trickling Filters 2
Sludge Drying Beds 8
Secondary Clarifiers 2
Grit Chamber 1
Source: Compiled by LSA (2025).
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
2 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -14 This page intentionally left blank
0 100 200
FEET
SOURCE: Carollo Engineers, 2025
I:\2024\20242046\G\Phase1_Improvements.ai (4/3/2026)
FIGURE 2-4
Santa Maria Wastewater Treatment Plant Improvements Project Proposed Phase 1 Improvements
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
2 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -16 This page intentionally left blank
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 2-17 Table 2.D shows the new structures that are planned to be constructed as part of the Phase 1 Improvements. Upon completion of the Phase 1 Improvements, the WWTP is expected to have the capacity to meet anticipated service demands through the year 2052, by which time the Phase 2 Improvements would also be completed.
Table 2.D: Structures Planned to Be Completed
During Phase 1 Construction
Structures to Be Constructed Quantity
Aeration Basins (ABs) 41
Grit Chamber (GC) 1
Secondary Clarifier (SC) 3
Tertiary Filter (TF) 1
Anaerobic Digester (AD) 2
Dewatering Facility (DB) 1
Sludge Storage (SS) 1
Digester Gas Flare (within Cogeneration Facility) 1
Hot Water Boilers 2
Cogeneration Facility with Battery 1
Source: Compiled by LSA (2026).
1 Preliminary estimate. The number of aeration basins to be installed will be determined as part of the final design.
Structures proposed as part of the Phase 1 Improvements would include installation of various mechanical and electrical equipment, including pumps, blowers, and mixers. The majority of this equipment would be housed within existing or proposed buildings; however, some would be installed outdoors and would operate up to 24 hours per day. A full list of proposed equipment is included in Appendix D.
Construction of the Phase 1 Improvements is expected to begin in early 2030 and is anticipated to take 5 years to complete. All construction activities would occur within the limits of the existing WWTP, with construction staging occurring in the northern portion of the WWTP site. Because the WWTP must continue to operate and treat wastewater during construction, the sequencing and location of the proposed improvements are critical. Each of the new process structures must not impact ongoing operation of the WWTP during their construction. Most of the new construction would occur on the existing sludge drying beds once the solids dewatering facility has been constructed. Road improvements and underground piping improvements would also be required throughout the site.
The total area of ground disturbance for implementation of the Phase 1 Improvements would be approximately 40 acres. The depth of excavation would be approximately 10 to 15 feet for some of the proposed structures, such as the secondary clarifiers and aeration basins and approximately 5 to 10 feet for pipeline installation. Other facilities are anticipated to be constructed at grade.
Demolition activities associated with the removal of existing facilities is anticipated to result in approximately 35,000 cubic yards of material. The Phase 1 Improvements are expected to require approximately 46,000 cubic yards of soil excavation, for a total of 72,000 cubic yards of material to be hauled off site during Phase 1.
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
2 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -18
2.4.3 Phase 2 Improvements
The Phase 2 Improvements are anticipated to include modifications to and expansion of some of the new facilities constructed during Phase 1, including a new headworks, expansion of the aeration basins and installation of two additional secondary clarifiers, and an additional sludge storage digester, as shown on Figure 2-5. However, changes in the future growth of Santa Maria, changes in service demands, updated regulations, and modified treatment objectives could significantly change both the timeline and design requirements of the Phase 2 Improvements. Presently, the Phase 2 Improvements are expected to allow the WWTP to meet planned growth beyond the year 2060.
Phase 2 is expected to be completed before the year 2052 to align with when the projected service demands could surpass the capacity of the WWTP Phase 1 Improvements.
2.4.4 WWTP Operations
The existing WWTP currently operates 24 hours per day, 7 days per week. Operating and maintenance staff are on site Monday through Friday, with on-call operators in attendance on weekends and holidays. Fourteen full-time employees are dedicated to WWTP operations and collections activities. Administrative, regulatory, and support staff are on site Monday through Friday, with other maintenance and support personnel (employees and contractors) on site as needed. With implementation of the Phase 1 Improvements, the City anticipates that an additional 11 full-time employees would be needed, for a total of 25 dedicated WWTP and collections staff. The WWTP would continue to operate 24 hours per day, 7 days per week.
2.5 PROJECT APPROVALS
A number of permits and approvals would be required for the proposed project. While the City is the Lead Agency for the project, other agencies also have discretionary authority related to the project and approvals. A list of these agencies and potential permits and approvals that may be required is provided in Table 2.E.
Table 2.E: Potential Permits and Approvals
Lead Agency Potential Permits/Approvals
City of Santa Maria Environmental Review
Project Approval
Building Permit
Other Agencies
Regional Water Quality Control Board Waste Discharge Permit Santa Barbara County Air Pollution Control District Authority to Construct Permit to Operate
State Water Resources Control Board Construction General Permit Industrial General Permit
Santa Barbara County Environmental Health Services
certified by the California Environmental Protection Agency as the Certified Unified Program Agency (CUPA)
Unified Program Facility Permit
State of California Department of Industrial Relations
Division of Occupational Safety & Health
Permit to Operate
Source: Compiled by LSA (2025).
SOURCE: Carollo Engineers, 2025
I:\2024\20242046\G\Phase1_Phase2.ai (3/13/2026)
FIGURE 2-5
Santa Maria Wastewater Treatment Plant Improvements Project Proposed Phase 1 and Phase 2 Improvements
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
2 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -20 This page intentionally left blank
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 3-1
3.0 ENVIRONMENTAL FACTORS POTENTIALLY AFFECTED
The environmental factors checked below would be potentially affected by this project, involving at least one impact that is a “Potentially Significant Impact” as indicated by the checklist in Chapter 4.0.
As indicated, none of the environmental factors involve a “Potentially Significant Impact.” Aesthetics Agriculture and Forestry Resources Air Quality Biological Resources Cultural Resources Energy
Geology/Soils Greenhouse Gas Emissions Hazards & Hazardous Materials Hydrology/Water Quality Land Use/Planning Mineral Resources Noise Population/Housing Public Services
Recreation Transportation Tribal Cultural Resources
Utilities/Service Systems Wildfire Mandatory Findings of Significance
3.1 DETERMINATION
On the basis of this initial evaluation:
I find that the proposed project COULD NOT have a significant effect on the environment, and a NEGATIVE DECLARATION will be prepared.
I find that although the proposed project could have a significant effect on the environment, there will not be a significant effect in this case because revisions in the project have been made by or agreed to by the project proponent. A MITIGATED NEGATIVE DECLARATION will be prepared.
I find that the proposed project MAY have a significant effect on the environment, and an ENVIRONMENTAL IMPACT REPORT is required.
I find that the proposed project MAY have a “Potentially Significant Impact” or “Potentially Significant Unless Mitigated” impact on the environment, but at least one effect (1) has been adequately analyzed in an earlier document pursuant to applicable legal standards, and (2) has been addressed by mitigation measures based on the earlier analysis as described on attached sheets. An ENVIRONMENTAL IMPACT REPORT is required, but it must analyze only the effects that remain to be addressed.
I find that although the proposed project could have a significant effect on the environment, because all potentially significant effects (a) have been analyzed adequately in an earlier ENVIRONMENTAL IMPACT REPORT or NEGATIVE DECLARATION pursuant to applicable standards, and (b) have been avoided or mitigated pursuant to that earlier ENVIRONMENTAL IMPACT REPORT or NEGATIVE DECLARATION, including revisions or mitigation measures that are imposed upon the proposed project, nothing further is required.
Signature Date
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
3 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -2 This page intentionally left blank
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 4-1
4.0 CEQA ENVIRONMENTAL CHECKLIST
4.1 AESTHETICS
Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Except as provided in Public Resources Code Section 21099, would the project:
a. Have a substantial adverse effect on a scenic vista? b. Substantially damage scenic resources, including, but not limited to, trees, rock outcroppings, and historic buildings within a state scenic highway
c. In non-urbanized areas, substantially degrade the existing visual character or quality of public views of the site and its surroundings? (Public views are those that are experienced from a publicly accessible vantage point.) If the project is in an urbanized area, would the project conflict with applicable zoning and other regulations governing scenic quality?
d. Create a new source of substantial light or glare which would adversely affect day or nighttime views in the area?
4.1.1 Environmental Setting
The Santa Maria WWTP is located at 601 Black Road in the western portion of the City of Santa Maria in northern Santa Barbara County. The approximately 310-acre project site is owned by the City and is bifurcated by Black Road into two distinct areas with differing visual characteristics.
The western portion of the site, located west of Black Road, is fully developed with wastewater treatment infrastructure, including aeration basins, clarifiers, trickling filters, digesters, percolation ponds, sludge drying beds, administration buildings, and utility facilities. The area is characterized by flat terrain, open views, and an industrial appearance consistent with public utility operations.
Vegetation in this area is limited to ornamental landscaping and perimeter grassland used for maintenance and buffer purposes. Due to the utilitarian nature of the site, visual features are primarily functional in design and not intended to contribute to aesthetic value.
The eastern portion of the site, located east of Black Road, remains undeveloped and is currently used for active agricultural interim operations. This area consists of flat, cultivated fields with minimal built features, providing a rural visual landscape. Existing views on this portion of the project site are dominated by open farmland and distant natural backdrops, including the coastal hills to the west.
The entire project site is located outside of any officially designated scenic vistas, scenic corridors, or visually sensitive areas identified by the City or the State. There are no rock outcroppings, historic
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
4 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -2 buildings, or prominent topographic features on the project site. The nearest eligible scenic highway is a portion of United States Route (US) 101 located approximately 4-miles east of the project site. 4
4.1.2 Impact Analysis
a. Would the project have a substantial effect on a scenic vista? Less Than Significant Impact. A scenic vista is generally defined as a public vantage point that provides the public with an expansive view of significant landscape feature(s). The project site is located in the west area of the City of Santa Maria in an area with extensive agricultural production.
The project site is partially developed, with approximately two-thirds of the project site west of Black Road containing the existing WWTP, while the portion east of Black Road is currently undeveloped and occupied by interim agricultural uses. The undeveloped portion and areas surrounding the project site are generally flat and provide expansive views of the surrounding fields as well as distant views of the valley’s hills. While the proposed project would replace the existing interim agricultural uses on the eastern (undeveloped) portion of the project site, development of the eastern portion of the project site would include installation of percolation ponds and associated infrastructure, which would be similar in size and scope to the existing WWTP facilities on the western portion of the project site. The new development on the eastern portion of the project site would be largely at-grade or low-lying (e.g., less than 5 feet above the existing grade) and would not reduce, obstruct, or degrade scenic vistas. Additionally, the City’s General Plan does not specifically designate any scenic vistas within the City, much less in the vicinity of the project site. Lastly, the proposed project would develop a facility anticipated by and consistent with the Public Facilities (PF) zoning and land use designation of Community Facilities (CF). Therefore, the proposed project would not have a substantial effect on scenic vistas, and the impact would be less than significant. b. Would the project substantially damage scenic resources, including, but not limited to, trees, rock outcroppings, and historic buildings within a state scenic highway? Less Than Significant Impact. The project site is partially developed, with approximately two-thirds of the project site west of Black Road containing the existing WWTP. The portion east of Black Road is undeveloped and occupied by interim agricultural uses, such as row crops. The project site does not include any trees, rock outcroppings, or historic buildings. Additionally, according to the California Department of Transportation (Caltrans) mapping of State Scenic Highways, there are no State-designated scenic highways in the City. The nearest eligible scenic highway is a portion of US-101 located approximately 4 miles east of the project site. 5 Because of this distance, viewers on US-101 do not have views of the proposed project. Therefore, since there are no scenic resources onsite, impacts to such resources would be less than significant. 4 California Department of Transportation (Caltrans). 2025. State Scenic Highway Map. Website:
https://dot.ca.gov/programs/design/lap-landscape-architecture-and-community-livability/lap-liv-i-scenic-highways (accessed July 1, 2025). 5 Ibid.
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 4-3 c. In non-urbanized areas, would the project substantially degrade the existing visual character or quality of public views of the site and its surroundings? (Public views are those that are experienced from a publicly accessible vantage point.) If the project is in an urbanized area, would the project conflict with applicable zoning and other regulations governing scenic quality? Less Than Significant Impact. Although the project site is located at the western edge of the City of Santa Maria and is partially developed with the existing WWTP, the remainder of the project site and the lands surrounding the project site are undeveloped and occupied by interim agricultural uses. As a result, the project site is located within a non-urbanized area and the proposed project has been evaluated for its potential to substantially degrade the existing visual character or quality of public views of the site and its surroundings. Existing uses on the developed portion of the project site would be altered to meet the existing needs of plant operations but would remain similar in size and scope with the existing WWTP facilities and would remain within the existing boundaries of the developed portion of the project site. The project would develop the eastern portion of the project site with municipal uses similar to those in use on the western portion of the project site. New facilities on the previously undeveloped portion of the project site include six percolation ponds and their associated infrastructure. These proposed improvements would be essentially at grade or low-lying (e.g., less than 5 feet above the existing grade) and would not be visible to the public except those viewers driving on Black Road immediately adjacent to the project site. The new facilities would be similar in character to facilities that currently exist within the project site. The percolation ponds would be constructed entirely within the project boundary and are consistent with the land use and zoning designations of the project site. Therefore, the project would not substantially degrade the existing visual character or quality of public views, and any impacts would be less than significant.
d. Would the project create a new source of substantial light or glare which would adversely affect day or nighttime views in the area?
Less Than Significant Impact. Existing light sources at the project site are generally confined to security lighting associated with the existing infrastructure on the developed portion of the project site. While the proposed project would develop the eastern portion of the project site, new facilities would largely consist of six new percolation ponds and their associated infrastructure. It is anticipated that only minimal security lighting would be required and would be similar to the existing light sources on the developed portion of the site. Therefore, the proposed project would not create a new source of substantial light or glare, and any impacts would be less than significant.
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
4 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -4
4.2 AGRICULTURE AND FORESTRY RESOURCES
In determining whether impacts to agricultural resources are significant environmental effects, lead agencies may refer to the California Agricultural Land Evaluation and Site Assessment Model (1997) prepared by the California Department of Conservation (DOC) as an optional model to use in assessing impacts on agriculture and farmland. In determining whether impacts to forest resources, including timberland, are significant environmental effects, lead agencies may refer to information compiled by the California Department of Forestry and Fire Protection (CAL FIRE) regarding the State’s inventory of forest land, including the Forest and Range Assessment Project and the Forest Legacy Assessment Project; and the forest carbon measurement methodology provided in Forest Protocols adopted by the California Air Resources Board (CARB).
Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project:
a. Convert Prime Farmland, Unique Farmland, or Farmland of Statewide Importance (Farmland), as shown on the maps
prepared pursuant to the Farmland Mapping and Monitoring Program of the California Resources Agency, to non-agricultural use? b. Conflict with existing zoning for agricultural use, or a Williamson Act contract?
c. Conflict with existing zoning for, or cause rezoning of, forest land (as defined in Public Resources Code Section 12220(g)), timberland (as defined by Public Resources Code Section 4526), or timberland zoned Timberland Production (as
defined by Government Code Section 51104(g))?
d. Result in the loss of forest land or conversion of forest land to non-forest use?
e. Involve other changes in the existing environment which, due to their location or nature, could result in conversion of Farmland, to non-agricultural use or conversion of forest land to non-forest use?
4.2.1 Environmental Setting
The project site is approximately 310 acres located in the northwestern edge of Santa Maria and is bifurcated by Black Road. The western portion contains the WWTP and associated infrastructure.
The eastern portion of the project site consists of actively cultivated interim agricultural fields on City-owned land. These fields are generally flat, machine-tilled row crops typical of the Santa Maria Valley, with perimeter farm roads, irrigation ditches, and seasonal vegetation.
The broader project vicinity is dominated by irrigated agriculture interspersed with rural residences and utility corridors. Soils across the site are young alluvial deposits of sands, silts, and localized clays, as found across the Santa Maria Valley. Groundwater occurs at relatively shallow depths typical of the valley floor, and on-site agricultural irrigation is supplied via existing farm infrastructure. No orchards, vineyards, or specialty timber operations occur on the site.
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 4-5 There are no forest lands, commercial timberlands, or Timberland Production Zone designations within or adjacent to the WWTP. Vegetation on the developed portion of the project site is limited to ornamental landscaping and perimeter grassland used for maintenance and buffer purposes; the eastern portion is actively farmed and lacks native woodland stands or timber resources. The nearest natural riparian or wooded habitats are associated with the Santa Maria River corridor approximately 2 miles north of the project site across large, expansive fields of agriculture.
4.2.2 Impact Analysis
a. Would the project convert Prime Farmland, Unique Farmland, or Farmland of Statewide Importance (Farmland) as shown on the maps prepared pursuant to the Farmland Mapping and Monitoring Program of the California Resources Agency, to non-agricultural use? Less Than Significant Impact. The proposed project would upgrade the existing WWTP treatment infrastructure within the exiting WWTP site, which includes City-owned land east of Black Road, which is presently being used for interim agricultural production.
The DOC’s Farmland Mapping and Monitoring Program (FMMP) identifies Prime Farmland, Farmland of Statewide Importance, and Unique Farmland as categories which constitute “agricultural land” under CEQA (Public Resources Code [PRC] §21060.1). While the existing WWTP facilities occupy land classified as “Urban and Built-Up Land”, the portion of the project site east of Black Road is classified as “Prime Farmland” and “Farmland of Statewide Importance” by the DOC. 6 The proposed project
would permanently impact approximately 25 acres of Prime Farmland and 19 acres of Farmland of Statewide Importance to accommodate the near-term project. In addition, approximately 15 acres of Prime Farmland would be temporarily impacted for construction staging and soil stockpiling. After project construction is completed, these staging areas may be restored and allowed to return to interim agricultural use pending future development under the Public Facilities (PF) zoning.
The conversion of Prime Farmland and Farmland of Statewide Importance on this portion of the project site was addressed in the Santa Maria Wastewater Treatment Plant Expansion Final Environmental Impact Report 7 (Expansion EIR), which was certified by the City in September 2006.
With certification of the Expansion EIR and approval of the Santa Maria Wastewater Treatment Plant Expansion Project, this portion of the project site was annexed into the City, and the land use designation and zoning was changed to Community Facilities (CF) and Public Facilities (PF), respectively, for the purpose of development as wastewater treatment facilities. Therefore, the existing agricultural use on the project site represents an interim use and the change in use from agricultural production to use for public facilities was previously accounted for under the Expansion EIR. In accordance with the Expansion EIR, the City has implemented Mitigation Measure AG-1(a):
Project Phasing, as the land has remained in agricultural production for the duration of the previously existing Williamson Act contract and the City has deferred development on the most significant Prime Farmland for the greatest time possible. 6 California Department of Conservation (DOC). 2022a. California Important Farmland Finder. Website:
https://maps.conservation.ca.gov/DLRP/CIFF/ (accessed July 11, 2025). 7 Rincon Consultants, Inc. 2006. Santa Maria Wastewater Treatment Plant Expansion Final Environmental Impact Report (State Clearinghouse No. 2005121171).
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
4 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -6 Since the Expansion EIR addressed potential impacts associated with conversion of farmland, and the City Council adopted a Statement of Overriding Considerations regarding the conversion of farmland and the land use designation and zoning were changed at that time, implementation of the proposed project would not result in the conversion of farmland that was not already evaluated.
Additionally, the interim agriculture uses on the eastern portion of the project site represents an existing non-conforming use, as the PF zoning designation does not include agriculture as a permitted use.
Because the proposed project would develop uses consistent with the zoning and land use designation for the project site and would not result in the conversion of Important Farmland to non-agricultural use that was not already addressed in the Expansion EIR, this impact would be less than significant.
b. Would the project conflict with existing zoning for agricultural use, or a Williamson Act contract? Less Than Significant Impact. All parcels which make up the project site are designated Community Facilities (CF) in the City General Plan and zoned Public Facilities (PF). While a portion of the project site is currently used for cultivating row crops, proposed uses would be consistent with the existing zoning and land use designation. Additionally, the project site is not currently enrolled under a Williamson Act contract. 8 Therefore, construction and operation of the proposed project would not conflict with an existing zoning designation for agricultural use or a Williamson Act contract. The impact would be less than significant.
c. Would the project conflict with existing zoning for, or cause rezoning of, forest land (as defined in Public Resources Code Section 12220(g)), timberland (as defined by Public Resources Code Section 4526), or timberland zoned Timberland Production (as defined by Government Code Section 51104(g))?
No Impact. The project area consists of developed wastewater facilities and fields of cultivated row-crops; no forest lands occur on or near the project site. PRC Section 12220(g), defines “forest land” as land capable of supporting 10 percent native tree cover and associated forest resources.
California Government Code §51104 defines “timberland” as land capable of growing and harvesting timber and eligible for Timberland Production. All parcels that make up the project site are designated Community Facilities (CF) in the City General Plan and zoned Public Facilities (PF), neither of which include forest land or timberland as a permitted use. Because the project site does not contain forest or timberland, the proposed project would not conflict with the existing zoning for or cause the rezoning of forest land or timber land. There would be no impact. d. Would the project result in the loss of forest land or conversion of forestland to non-forest use? No Impact. As described above in 4.2.c, the project site does not contain any forest land, as defined in PRC Section 12220(g), and is zoned Public Facilities (PF), which does not include forest land or 8 DOC. 2022b. Williamson Act Enrollment Finder. Website:
https://maps.conservation.ca.gov/dlrp/WilliamsonAct/ (accessed July 11, 2025).
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 4-7 timberland as a permitted use. Therefore, the project would not result in the loss or conversion of forestland to non-forest use. There would be no impact. e. Would the project involve other changes in the existing environment which, due to their location or nature, could result in conversion of Farmland, to non-agricultural use or conversion of forest land to non-forest use?
Less Than Significant Impact. As discussed in 4.2.a, the proposed project would result in the conversion of interim farmland on the eastern portion of the project site. However, all farmland that would be converted as a result of the proposed project is designated Community Facilities (CF) in the City’s General Plan and zoned Public Facilities (PF), with which the project would be consistent.
Farmland is not listed as a permitted use in the PF zoning district. Beyond the direct farmland conversion on the project site, the proposed project would not extend urban services or infrastructure that would facilitate additional conversion of farmland in the area. The impact would be less than significant.
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
4 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -8
4.3 AIR QUALITY
Where available, the significance criteria established by the applicable air quality management district or air pollution control district may be relied upon to make the following determinations.
Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project:
a. Conflict with or obstruct implementation of the applicable air quality plan?
b. Result in a cumulatively considerable net increase of any criteria pollutant for which the project region is non-attainment under an applicable federal or state ambient air quality standard?
c. Expose sensitive receptors to substantial pollutant
concentrations?
d. Result in other emissions (such as those leading to odors) adversely affecting a substantial number of people?
4.3.1 Environmental Setting
The City of Santa Maria is located in the northern portion of Santa Barbara County, within the South Central Coast Air Basin (SCCAB), which includes San Luis Obispo, Santa Barbara, and Ventura counties. The region’s air quality is regulated by the Santa Barbara County Air Pollution Control District (SBCAPCD), which monitors criteria pollutants and enforces air quality standards established by the United States Environmental Protection Agency (EPA) and California Air Resources Board (CARB).
The climate of the Santa Maria Valley is characterized by mild temperatures and moderate rainfall, with prevailing winds generally from the northwest. The region benefits from frequent marine breezes and relatively flat topography, which help disperse air pollutants. Despite these favorable conditions, air quality in the SCCAB is influenced by both local emissions and pollutants transported from upwind urban areas, particularly the South Coast Air Basin (including Los Angeles).
The Santa Maria WWTP is located near the western edge of the Santa Maria urban area, surrounded by agricultural land uses and rural residential properties. Existing sources of air pollutant emissions in the project vicinity include traffic from nearby roads (including Black Road and Main Street), agricultural operations, and stationary sources such as the WWTP itself. On-site sources include equipment operations, treatment processes, and emergency generators, all of which are regulated under air district permits.
The primary pollutants of concern in the SBCAPCD are ozone (O3) and particulate matter less than 10 microns in size (PM10), as the SBCAPCD is designated as nonattainment under State AAQS standards for these pollutants. The SBCAPCD is either in attainment or unclassified for all other State and federal standards. However, in 2017, the SBCAPCD changed from nonattainment to nonattainment-
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 4-9 transitional for O3 due to the declining number of State 1-hour and 8-hour O3 exceedances that occurred in Santa Barbara County between 1990 and 2005.
Construction activities associated with the Santa Maria WWTP upgrades, including excavation, grading, material delivery, and equipment use, would generate temporary emissions of dust and exhaust from construction equipment. However, the project is not located within or adjacent to any sensitive receptor zones (e.g., schools or hospitals), and the nearest residences are located more than 1,000 feet away from the center of the proposed work areas.
4.3.2 Impact Analysis
a. Would the project conflict with or obstruct implementation of the applicable air quality plan? Less Than Significant Impact. The proposed project is located within the City of Santa Maria in Santa Barbara County. CARB has divided California into 15 regional air basins according to topographic drainage features, geographic features, and meteorological features for the purpose of managing the air resources of the State on a regional basis. Santa Maria is within the SCCAB, which includes all of San Luis Obispo, Santa Barbara, and Ventura counties. The SCCAB consists of three Air Pollution Control Districts (APCDs) that are County governing authorities with primary responsibility for controlling air pollution from stationary sources within their jurisdiction: the San Luis Obispo County APCD (SLOCAPCD), SBCAPCD, and Ventura County APCD (VCAPCD). The City of Santa Maria is located within Santa Barbara County and therefore is within the jurisdiction of the SBCAPCD.
Both State (i.e., CARB) and federal (EPA) agencies have established health-based ambient air quality standards (AAQS) for six criteria air pollutants: carbon monoxide (CO), O3, nitrogen dioxide (NO2), sulfur dioxide (SO2), lead (Pb), and suspended particulate matter (PM). These standards are designed to protect the health and welfare of the populace with a reasonable margin of safety. Two criteria pollutants, O3 and NO2, are considered regional pollutants because they (or their precursors) affect air quality on a regional scale. Pollutants such as PM, CO, SO2, and Pb are considered local pollutants because they tend to accumulate in the air locally.
As noted above, the proposed project is within the jurisdiction of the SBCAPCD, which regulates air quality in Santa Barbara County. Each air district establishes significance thresholds that are used to manage total regional and local emissions within an air basin. Significance thresholds are based on whether or not the air basin has met State and federal AAQS standards for criteria pollutants. These emission thresholds were established for individual development projects that would contribute to regional and local emissions and could adversely affect or delay the air basin’s projected attainment target goals for nonattainment criteria pollutants.
Under the California Clean Air Act (CCAA), the SBCAPCD is required to prepare a plan for air quality improvement for pollutants for which the SBCAPCD is in nonattainment. The SBCAPCD updates the plan every 3 years. Each SBCAPCD Air Quality Attainment Plan (AQAP) is an update of the previous plan and has a 20-year horizon. The latest AQAP is the 2022 Ozone Plan, which was adopted in
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
4 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -10 December 2022. 9 Based on the region’s nonattainment status for O3, each of the SBCAPCD plan updates has included an “every feasible measure” strategy to ensure continued progress toward attainment of the state O3 standards. The 2022 Ozone Plan documents the SPCAPCD’s progress toward the State 1-hour and 8-hour O3 standards.
The 2022 Ozone Plan incorporates and builds upon the prior Clean Air Plans and focuses on achieving attainment of the State O3 standards. The 2022 Ozone Plan focuses on reducing O3 precursor emissions through implementation of reduction measures for four major categories:
stationary; area; on-road motor vehicle; and other mobile sources. In addition, the 2022 Ozone Plan utilizes the Santa Barbara County Association of Governments (SBCAG) Regional Growth Forecast and CARB on-road emissions forecasts to project population growth and associated air pollutant emissions within Santa Barbara County.
CEQA requires that proposed projects be analyzed for consistency with the applicable air quality plan. An air quality plan describes air pollution control strategies to be implemented by a city, county, or region classified as a nonattainment area. The main purpose of the air quality plan is to bring the area into compliance with the requirements of the federal and State AAQS. The SBCAPCD has developed the 2022 Ozone Plan to satisfy Federal Clean Air Act (FCAA) and CCAA requirements and ensure attainment of the State O3 standard. The SBCAPCD does not have a plan to address PM10 attainment.
For a project to be consistent with the SBCAPCD 2022 Ozone Plan, a project’s direct and indirect emissions must be consistent with the policies in the 2022 Ozone Plan. Emissions that lead to ozone production are primarily related to vehicle use, 10 which are directly related to population because additional residents result in more vehicular use. Populations accounted for in the 2022 Ozone Plan and Santa Barbara County Association of Governments (SBCAG) forecasts are also accounted for in the SBCAPCD emissions inventories. The proposed project would expand and update its existing WWTP to accommodate anticipated growth (planned growth associated with implementation of the General Plan and therefore accounted for in the 2022 Ozone Plan and SBCAPCD emissions inventories) provide long-term reliable treatment, and adhere to applicable regulatory requirements, including the updated effluent discharge limits. The proposed project does not include residential units and therefore would not increase population projections within the City of Santa Maria or Santa Barbara County. Therefore, the proposed project would be within growth forecast assumptions used in the 2022 Ozone Plan. As such, the proposed project would be consistent with the 2022 Ozone Plan and would not conflict with or obstruct the implementation of the applicable air quality plan, and air quality impacts would be less than significant. 9 Santa Barbara County Air Pollution Control District (SBCAPCD). 2022a. 2022 Ozone Plan. December.
Website: https://www.ourair.org/wp-content/uploads/2022-Ozone-Plan.pdf (accessed September 2025). 10 Vehicle use is the only source applicable to this project. Other sources include industrial boilers, power plants and chemical plants, which do not apply.
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 4-11 b. Would the project result in a cumulatively considerable net increase of any criteria pollutant for which the project region is non-attainment under an applicable federal or state ambient air quality standard?
Less Than Significant with Mitigation Incorporated. As discussed above, the primary pollutants of concern in the project area are O3 and PM10, as the SBCAPCD is designated as nonattainment under State AAQS standards for these pollutants. However, in 2017, the SBCAPCD changed from nonattainment to nonattainment-transitional for O3 due to the declining number of State 1-hour and 8-hour O3 exceedances that occurred in the county between 1990 and 2005. The SBCAPCD is either in attainment or unclassified for all other State and federal standards. The SBCAPCD’s nonattainment status is attributed to the region’s development history. Past, present, and future development projects contribute to the region’s adverse air quality impacts on a cumulative basis. By its very nature, air pollution is largely a cumulative impact. No single project is sufficient in size to, by itself, result in nonattainment of AAQS. Instead, a project’s individual emissions contribute to existing cumulatively significant adverse air quality impacts. If a project’s contribution to the cumulative impact is considerable, then the project’s impact on air quality would be considered significant.
In developing thresholds of significance for air pollutants, the SBCAPCD considered the emission levels for which a project’s individual emissions would be cumulatively considerable. If a project exceeds the identified significance thresholds, its emissions would be cumulatively considerable, resulting in significant adverse air quality impacts to the region’s existing air quality conditions. The following analysis assesses the potential project-level construction- and operation-related air quality impacts.
Short-Term Construction Emissions. During construction, short-term degradation of air quality may occur due to the release of particulate emissions generated by site preparation, grading, hauling, and building activities. Emissions from construction equipment are also anticipated and would include CO, NOX, reactive organic compounds (ROC), directly emitted particulate matter (PM2.5 and PM10), and toxic air contaminants (TACs) such as diesel particulate matter (DPM).
Site preparation and project construction would involve demolition, grading, paving, and building activities. Construction-related effects on air quality from the proposed project would be greatest during the site preparation phase due to the disturbance of soils. If not properly controlled, these activities would temporarily generate particulate emissions. Sources of fugitive dust would include disturbed soils at the construction site. Unless properly controlled, vehicles leaving the site would deposit dirt and mud on local streets, which could be an additional source of airborne dust after it dries. PM10 emissions would vary from day to day, depending on the nature and magnitude of construction activity, local weather conditions, soil moisture, silt content of soil, and wind speed. Larger dust particles would settle near the source, while fine particles would be dispersed over greater distances from the construction site.
The SBCAPCD does not currently have quantitative thresholds of significance for short-term construction-related emissions; however, CEQA requires that short-term impacts, such as exhaust emissions from construction equipment and fugitive dust generation during grading, be discussed in the environmental document. Therefore, the SBCAPCD recommends that construction-related NOX, ROC, PM10, and PM2.5 emissions from diesel and gasoline powered
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
4 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -12 equipment, paving, and other construction activities be quantified. Additionally, SBCAPCD’s Scope and Content of Air Quality Sections in Environmental Documents recommends quantification of construction-related emissions and suggests a 25-tons-per-year threshold for ROC or NOX as a guideline for determining the significance of construction impacts. 11 This is a
limit that requires offsets if the construction activity is for a project that requires SBCAPCD permits and also provides guidance for other construction projects involving standard grading and building activities. In addition, standard dust control measures must be implemented for any discretionary project involving earthmoving activities, regardless of size or duration. According to the SBCAPCD, proper implementation of these required measures reduces fugitive dust emissions to a level that is less than significant. 12
The California Emissions Estimator Model (CalEEMod), Version 2022.1, was used to estimate construction emissions for the proposed project. As discussed in the Project Description, one near-term project will be completed before Phase 1 of the proposed project begins construction.
As such, for purposes of the CalEEMod analysis, construction of the near-term project is expected to begin in 2028 and extend approximately 24 months. 13 The total acreage of
disturbance associated with the near-term project would be approximately 42 acres. The near-term project is expected to require approximately 879,000 cubic yards of soil excavation, with approximately 703,000 cubic yards of soil off-hauled for disposal.
Following the completion of the near-term project, as discussed in the Project Description, Phase 1 construction activities would begin in early 2030 and would take 5 years to complete, which was included in CalEEMod. As discussed in the Project Description, the total area of ground disturbance for implementation of the Phase 1 Improvements would be approximately 40 acres.
Construction of Phase 1 would include approximately 23,050 square feet of new structures.
Demolition activities associated with the removal of existing facilities is anticipated to result in approximately 35,000 cubic yards of material. The Phase 1 Improvements are expected to require approximately 46,000 cubic yards of soil excavation for a total of 72,000 cubic yards of material to be hauled off site during Phase 1. Other construction details are not yet known; therefore, default assumptions (e.g., construction fleet activities) from CalEEMod were used.
Appendix A contains CalEEMod output worksheets. Results are summarized in Table 4.A and are compared to the SBCAPCD’s recommended thresholds.
11 SBCAPCD. 2022b. Scope and Content of Air Quality Sections in Environmental Documents. January.
Website: https://www.ourair.org/wp-content/uploads/ScopeContentJanuary2022-LimitedUpdates.pdf (accessed September 2025). 12 SBCAPCD. 2022b. Scope and Content of Air Quality Sections in Environmental Documents. January.
Website: https://www.ourair.org/wp-content/uploads/ScopeContentJanuary2022-LimitedUpdates.pdf (accessed September 2025). 1313 The CalEEMod analysis evaluated near-term project construction emissions with a start date of 2027 and a duration of 24 months. The proposed project’s construction schedule has since been modified; project construction is now scheduled to begin in 2028 and would still occur over a 24-month duration. Based on this minimal modification to the project construction schedule, a later construction start date would not result in any additional air quality impacts than identified herein.
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 4-13 As shown in Table 4.A, construction NOx emissions associated with the construction of the near-term and Phase 1 elements of the proposed project would be minimal. The SBCAPCD does not have significance thresholds for CO, SOX, PM10, or PM2.5; however, as indicated in Table 4.A, the proposed project would be below the SBCAPCD’s recommended thresholds of significance; therefore, construction of the proposed project is not expected to generate substantial emissions.
Table 4.A: Project Construction Emissions
Emissions (tons/yr)
ROC NOX CO SOX PM10 PM2.5
2027 0.1 5.4 3.0 0.1 0.8 0.4
2028 0.2 5.6 3.4 <0.1 0.6 0.3
2029 0.3 1.0 0.8 <0.1 <0.1 <0.1
2030 0.1 4.5 3.3 <0.1 0.5 0.3
2031 0.1 2.6 2.0 <0.1 0.1 0.1
2032 0.1 2.6 2.0 <0.1 0.1 0.1
2033 0.1 2.6 2.0 <0.1 0.1 0.1
2034 0.6 1.8 1.4 <0.1 0.1 0.1
Maximum Project Construction Emissions 0.6 5.6 3.4 0.1 0.8 0.4 SBCAPCD Significance Threshold 25.0 25.0 N/A N/A N/A N/A Exceed Threshold? No No No No No No
Source: Compiled by LSA (March 2026).
CO = carbon monoxide
N/A = not applicable
NOX = nitrogen oxides
PM10 = particulate matter less than 10 microns in size
PM2.5 = particulate matter less than 2.5 microns in size ROC = reactive organic compounds
SBCAPCD = Santa Barbara County Air Pollution Control District SOX = sulfur oxides
tons/yr = tons per year
Phase 2 Improvements are anticipated to include modifications to and expansion of the new facilities constructed during Phase 1, including a new headworks, expansion of the aeration basins and installation of two additional secondary clarifiers, and an additional sludge storage digester. However, as discussed in the Project Description, changes in the future growth of Santa Maria, changes in service demands, updated regulations, and modified treatment objectives could significantly change both the timeline and design requirements of the Phase 2 Improvements. As such, construction emissions associated with the Phase 2 Improvements were not quantified as part of this analysis. However, given that the construction required for Phase 2 would require less equipment and would occur for a shorter duration than Phase 1, emissions associated with Phase 2 would be less than those associated with Phase 1. Since Phase 1 emissions are below SBCAPCD thresholds and not significant, emissions associated with Phase 2 would also be less than significant.
Santa Barbara County is in non-attainment for PM10 emissions. As such, the SBCAPCD requires standard measures for reducing fugitive dust emissions (PM10) and particulate emissions from diesel exhaust for all discretional construction activities. 14 For example, the SBCAPCD requires 14 SBCAPCD. 2022. Scope and Content of Air Quality Sections in Environmental Documents. January 2022 Limited Update. Website: https://www.ourair.org/wp-content/uploads/ScopeContentJanuary2022- LimitedUpdates.pdf (accessed June 2025).
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
4 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -14 that water or other soil stabilizers be used at a project site to control dust. Using water or soil stabilizers can result in fugitive dust emissions reductions of 50 percent or more. Mitigation Measure AIR-1 would require the project contractor to implement the SBCAPCD’s standard dust control and equipment exhaust measures to reduce construction fugitive dust.
Mitigation Measure AIR-1 During construction, the project contractor shall implement the following Santa Barbara County Air Pollution Control District (SBCAPCD) standard dust control and equipment exhaust
measures:
• Water trucks or sprinkler systems shall be used to keep all areas of vehicle movement damp enough to prevent dust
from leaving the site. At a minimum, this should include wetting down such areas in the late morning and after work is completed for the day. Increased watering frequency
should be required whenever the wind speed exceeds 15
miles per hour (mph). Reclaimed water should be used
whenever possible. However, reclaimed water should not be used in or around crops for human consumption.
• On site vehicle speeds shall be no greater than 15 miles per hour when traveling on unpaved surfaces.
• A track-out prevention device shall be installed and
operated where vehicles enter and exit unpaved roads onto paved streets. The track-out prevention device can include any device or combination of devices that are effective at preventing track-out of dirt, such as gravel pads, pipe-grid track-out control devices, rumble strips, or wheel-washing systems.
• If importation, exportation and stockpiling of fill material is involved, soil stockpiled for more than 2 days shall be covered, kept moist, or treated with soil binders to prevent dust generation. Trucks transporting fill material to and from the site shall be tarped from the point of origin.
• The amount of disturbed area shall be minimized. After clearing, grading, earthmoving, or excavation is completed, the disturbed area shall be treated by watering, roll-compaction, revegetating, or spreading soil binders until the area is paved or otherwise developed so that dust
generation will not occur. All roadways, driveways,
sidewalks, etc., to be paved should be completed as soon as possible.
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 4-15 • Clearing, grading, earthmoving, and excavation activities shall be scheduled during periods of low wind speed to the extent feasible. During periods of high winds (>25 mph), clearing, grading, earthmoving, and excavation operations shall be minimized to prevent fugitive dust created by on-site operations from becoming a nuisance or hazard. • The contractor or builder shall designate a person or persons to monitor the dust control program and to order increased watering, as necessary, to prevent transport of dust off site. Their duties shall include holiday and weekend periods when work may not be in progress. The name and
telephone number of such persons shall be provided to the Santa Barbara County Air Pollution Control District
(SBCAPCD) prior to grading/ building permit issuance and/or map clearance.
• All portable diesel-powered construction equipment shall be registered with the State’s portable equipment
registration program or shall obtain an SBCAPCD permit. • Fleet owners of mobile construction equipment are subject to the California Air Resource Board (CARB) Regulation for In-Use Off-Road Diesel Vehicles (Title 13, California Code of Regulations [CCR] §2449), the purpose of which is to reduce nitrogen oxides (NOX), diesel particulate matter (DPM), and other criteria pollutant emissions from in-use (off-road) diesel-fueled vehicles. Off-road heavy-duty trucks shall comply with the State Off-Road Regulation. For more
information, see https://ww2.arb.ca.gov/our-work/programs/use-road-diesel-fueled-fleets-regulation. • Fleet owners of mobile construction equipment are subject to the CARB Regulation for In-Use (On-Road) Heavy-Duty
Diesel-Fueled Vehicles (13 CCR §2025), the purpose of
which is to reduce DPM, NOX, and other criteria pollutants from in-use (on-road) diesel-fueled vehicles. On-road heavy-duty trucks shall comply with the State On-Road Regulation. • All commercial off-road and on-road diesel vehicles are subject, respectively, to 13 CCR §2449(d)(3) and §2485, limiting engine idling time. Idling of heavy-duty diesel construction equipment and trucks during loading and
unloading shall be limited to 5 minutes; electric auxiliary power units should be used whenever possible.
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
4 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -16 With implementation of Mitigation Measure AIR-1, construction of the proposed project would not result in a cumulatively considerable net increase of any criteria pollutant for which the project region is in nonattainment under an applicable federal or State AAQS.
Long-Term Operational Emissions. Long-term air pollutant emission impacts are those associated with mobile sources (e.g., vehicle trips), energy sources (e.g., natural gas), area sources (e.g., architectural coatings and the use of landscape maintenance equipment), off-road sources (e.g., pumps), and stationary sources (e.g., use of boilers).
Mobile-source emissions include ROC and NOX emissions that contribute to the formation of O3.
Additionally, PM10 emissions result from running exhaust, tire and brake wear, and the entrainment of dust into the atmosphere from vehicles traveling on paved roadways. Energy-source emissions result from activities for which natural gas is used. Typically, area-source emissions consist of direct sources of air emissions located at the project site, including architectural coatings and the use of landscape maintenance equipment. In addition, off-road-source emissions are associated with pumps, and stationary-source emissions are associated with the use of generators and boilers.
The proposed project would expand and update its existing WWTP to accommodate anticipated growth, provide long-term reliable treatment, and adhere to applicable regulatory requirements, including the updated effluent discharge limits. Long-term operational emissions associated with the proposed project were estimated using CalEEMod. As discussed in the Project Description, because the existing WWTP must remain operational during project construction, one near-term project must be completed before Phase 1 of the proposed project can begin construction.
However, for a worst-case analysis, this analysis evaluates operational emissions associated with buildout of the project (Phase 1 and the near-term project). Once Phase 1 is operational, the proposed project would result in two sludge haul trucks per day and 11 additional full-time employees, resulting in a total of four sludge haul trips and 22 employee trips per day, which was included in CalEEMod. In addition, the proposed project would include the installation of various mechanical and electrical equipment, including pumps, blowers, and mixers, which would operate up to 24 hours per day. The equipment included in CalEEMod was based on an equipment list provided by the project team (Appendix D). In addition, the proposed project would require two new boilers with a rating of 2 million British thermal units per hour (Btu/hour), which was included in CalEEMod. The existing WWTP includes an existing emergency generator, which would be sufficient for the proposed project. As such, the proposed project would not include any new emergency generators. Where project-specific data were not available, default assumptions from CalEEMod were used to estimate project emissions. Model results are shown in Table 4.B. CalEEMod output sheets are included in Appendix A.
As shown in Table 4.B, long-term operational emissions associated with the proposed project would be minimal and would be well below SBCAPCD significance thresholds for criteria air pollutants.
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 4-17 Table 4.B Project Operation Emissions
Emissions (lbs/day)
ROC NOX CO SOX PM10 PM2.5
Mobile Source Emissions <0.1 <0.1 <0.1 <0.1 <0.1 <0.1
Area Source Emissions 1.1 <0.1 1.0 <0.1 <0.1 <0.1
Energy Source Emissions <0.1 0.3 0.2 <0.1 <0.1 <0.1
Off-Road Source Emissions 0.0 0.0 0.0 0.0 0.0 0.0
Stationary Source Emissions 0.5 0.0 9.2 0.1 0.7 0.7
Total Project Operation Emissions 1.6 0.3 10.5 0.2 0.7 0.8 SBCAPCD Mobile Source Significance Threshold 25.0 25.0 N/A N/A N/A N/A Exceed Threshold? No No No No No No
SBCAPCD All Source Significance Threshold 240.0 240.0 N/A N/A 80.0 N/A Exceed Threshold? No No No No No No
Source: LSA (March 2026).
CO = carbon monoxide
lbs/day = pounds per day
N/A = not applicable
NOX = nitrogen oxides
PM10 = particulate matter less than 10 microns in size
PM2.5 = particulate matter less than 2.5 microns in size ROC = reactive organic compounds
SBCAPCD = Santa Barbara County Air Pollution Control District SOX = sulfur oxides
In addition, the proposed project would include a Cogeneration Facility with battery, digester gas flares, and sludge withdrawal within the WWTP boundary. Currently, the WWTP generates digester gas, which is flared under an existing SBAPCD permit. The Cogeneration Facility would also include installation of a battery to reduce the purchase of utility power during peak periods.
The cogeneration engines would include emissions control equipment as needed to comply with the SBCAPCD requirements. It is assumed that the emissions control equipment would remove hydrogen sulfide (H2S) and ROCs from the digester gas in order to enhance the reliability of the cogeneration units. The cleaned biogas would then be piped to the cogeneration engine. The Cogeneration Facility would be designed and operated to use as much digester gas as possible. All stationary sources associated with the proposed project would be required to obtain an Authority to Construct (ATC) permit prior to installation. As part of the ATC, the SBCAPCD would evaluate the proposed sources for consistency with local, State, and federal air pollution control requirements.
If proposed sources are found to be consistent with requirements, prior to operation, SBCAPCD would issue a Permit to Operate (PTO) that describes how the equipment must be operated to minimize air pollution, and would ensure emissions would be less than significant.
As demonstrated in Table 4.B, above, operation of the proposed project would not result in a cumulatively considerable net increase of any criteria pollutant for which the proposed project region is in non-attainment under an applicable federal or State AAQS. As a result, impacts would be less than significant. No mitigation is required. c. Would the project expose sensitive receptors to substantial pollutant concentrations? Less Than Significant with Mitigation Incorporated. Sensitive receptors are defined as people who have an increased sensitivity to air pollution or environmental contaminants. Sensitive receptor locations include schools, parks and playgrounds, day-care centers, nursing homes, hospitals, and residential dwelling units. The closest sensitive receptors include a single-family residence located approximately 265 feet northeast of the project site boundary across Black Road.
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
4 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -18 Construction of the proposed project may expose surrounding sensitive receptors to airborne particulates, as well as a small quantity of construction equipment pollutants (i.e., usually diesel-fueled vehicles and equipment). However, construction contractors would be required to implement Mitigation Measure AIR-1, as described above. With implementation of Mitigation Measure AIR-1, project construction pollutant emissions would not be a source of substantial emissions. Once the project is constructed, operational activities associated with the proposed project would not be a source of substantial emissions. Therefore, sensitive receptors are not expected to be exposed to substantial pollutant concentrations during project construction or operation, and with implementation of Mitigation Measure AIR-1, potential impacts associated with project construction would be considered less than significant.
d. Would the project result in other emissions (such as those leading to odors) adversely affecting a substantial number of people?
Less Than Significant Impact. During construction, the various diesel-powered vehicles and equipment in use on site would create localized odors. Construction-related odors are often localized as they are concentrated at the source and dispersed by wind and distance. In addition, construction-related odors are temporary and would cease to occur after construction. As such, these odors would be temporary and are not likely to be noticeable for extended periods of time beyond the project site. Because the project’s potential construction-related odor impacts are localized and temporary, they would not adversely affect a substantial number of people. Therefore, the project’s potential construction-related odor impacts are less than significant.
According to the SBCAPCD, examples of types of facilities that are known producers of odors include fast-food restaurants, bakeries, and coffee roasting facilities. 15 The proposed project would not include any of these types of land uses. Although not specifically discussed by SBCAPCD in its guidance for assessing environmental impacts, wastewater treatment facilities are known to produce odors. However, the proposed project would modify the existing WWTP to serve current and future growth and come into compliance with applicable regulations. A public records request to the SBCAPCD, which included potential complaints from nearby off-site residents, revealed 26 odor complaints have been received at the existing WWTP in the last 5 years; however, none of these odor complaints were verified by the SBCAPCD. In addition, the proposed project would be required to comply with the SBCAPCD’s Rule 303, Nuisance, which requires that a source shall not discharge quantities of air contaminants or other material in violation of Section 41700 of the Health and Safety Code which cause injury, detriment, nuisance, or annoyance to any considerable number of persons or to the public or which endanger the comfort, repose, health, or safety of any such persons or the public, or which cause or have a natural tendency to cause injury or damage to business or property. As such, the proposed project is not expected to result in an increase in any sources of significant odors that could cause complaints from surrounding uses. Therefore, the proposed project would not result in other emissions (such as those leading to odors) adversely affecting a substantial number of people, and impacts would be less than significant. 15 SBCAPCD. 2022. op. cit.
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 4-19
4.4 BIOLOGICAL RESOURCES
Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Incorporated
Less Than
Significant
Impact
No
Impact
Would the project:
a. Have a substantial adverse effect, either directly or through habitat modifications, on any species identified as a
candidate, sensitive, or special-status species in local or regional plans, policies, or regulations, or by the California Department of Fish and Game or U.S. Fish and Wildlife
Service?
b. Have a substantial adverse effect on any riparian habitat or other sensitive natural community identified in local or regional plans, policies, regulations or by the California Department of Fish and Game or U.S. Fish and Wildlife
Service?
c. Have a substantial adverse effect on state or federally protected wetlands (including, but not limited to, marsh, vernal pool, coastal, etc.) through direct removal, filling, hydrological interruption, or other means?
d. Interfere substantially with the movement of any native resident or migratory fish or wildlife species or with
established native resident or migratory wildlife corridors, or impede the use of native wildlife nursery sites?
e. Conflict with any local policies or ordinances protecting biological resources, such as a tree preservation policy or ordinance?
f. Conflict with the provisions of an adopted Habitat
Conservation Plan, Natural Community Conservation Plan, or other approved local, regional, or state habitat conservation plan?
4.4.1 Environmental Setting
The project site, including the existing Santa Maria WWTP, spans approximately 310 acres and is bifurcated by Black Road into two distinct areas. The western portion of the project site is developed with wastewater treatment infrastructure and is largely disturbed, containing buildings, percolation ponds, trickling filters, clarifiers, digesters, sludge drying beds, paved surfaces, and landscaped buffers. The eastern portion of the project site is currently used for interim agricultural cultivation and includes row crops, tilled soil, and perimeter access roads. No natural habitats are present within actively farmed portion of the project site.
Biological field surveys and a literature review conducted for the proposed project confirm that the majority of the project site consists of previously disturbed or developed land that supports minimal native biological resources. According to the Biological Resources Technical Memorandum (BRTM) (July 8, 2024) and follow-up species-specific Habitat Assessment (February 19, 2026) prepared for the proposed project, the project site does not contain any federally or State-listed sensitive natural communities and wildlife species expected to occur, primarily including common species adapted to urban and agricultural environments. However, five special-status animal species were determined
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
4 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -20 to have some potential to occur. These species include tricolored blackbird (Agelaius tricolor), western burrowing owl (Athene cunicularia), northern California legless lizard, coast horned lizard, and yellow warbler (Setophaga petechia).
No riparian habitat, wetlands, or other jurisdictional features were identified within the project site.
Additionally, no designated critical habitat occurs within the project site boundaries. However, there are several irrigation ditches and wastewater percolation ponds on the project site. The project site is not part of a recognized wildlife movement corridor or migratory route, and the developed and agricultural land uses provide limited value as a native wildlife nursery or wildlife habitat area.
Although wildlife may occasionally move through the project site or along the project site perimeters, there are no ridgelines, natural drainages, or constraining features in the surroundings area (e.g., development) that would funnel wildlife through the project site. Therefore, the project site is not expected to be used consistently or to provide high-value habitat for migratory species.
Vegetation within the developed western portion of the project site is limited to landscape plantings and turf grasses used for screening and site maintenance. The eastern portion, used for farming, supports non-native crops and is subject to regular soil disturbance.
4.4.2 Impact Analysis
a. Would the project have a substantial adverse effect, either directly or through habitat modifications, on any species identified as a candidate, sensitive, or special-status species in local or regional plans, policies, or regulations, or by the California Department of Fish and Game or U.S. Fish and Wildlife Service?
Less Than Significant with Mitigation Incorporated. A Biological Resources Technical Memorandum (BRTM) (July 8, 2024) and a focused species-specific Habitat Assessment (February 9, 2026) were prepared to evaluate potential biological resources effects of the proposed project and are included as Appendix B of this Initial Study. LSA conducted a literature review, including database searches, and a field survey to identify the special-status species known to occur in the vicinity that may have potential to occur on the project site. As described above, five special-status animal species were determined to have some potential to occur. Of these species, the potential for northern California legless lizard and coast horned lizard is considered limited due to the repeated soil disturbance and compaction of agricultural areas and the lack of native scrub and grassland habitats. The loss of a limited amount of marginally suitable habitat for these species would not be expected to substantially reduce the population of these species in the region. Therefore, impacts on these species would be considered less than significant. The remaining three special-status species with the potential to occur are described further below.
The potential for protected resources to be impacted by construction of the proposed project is a function of the likelihood the species is present when the project is constructed, as well as the type and duration of construction activities. Another factor is the sensitivity of the species or resource to disturbance. Construction of the proposed project could directly and indirectly result in significant impacts to special-status wildlife species if they are present on the site during construction. Project activities could also contribute to erosion and/or degradation to the habitats on the site and unintentionally harm special-status wildlife without incorporation of best management practices.
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) 4-21 Additionally, inadvertent introduction of invasive plant species to the project site could occur as a result of equipment or vehicles harboring seeds or rhizomatous roots. In addition to the species-specific mitigation measures identified further below, the following mitigation measures would be implemented to reduce potential direct and indirect impacts to special-status species to a less than significant level.
Mitigation Measure BIO-1 Worker Environmental Awareness Program (WEAP). Prior to any ground disturbance or construction activities, a qualified biologist shall conduct a training session for all construction personnel. The training shall include a description of the western burrowing owl, tricolored blackbird, and yellow warbler and their habitats. The training shall also discuss the project mitigation measures described herein, including Mitigation Measure BIO-2, Mitigation Measure BIO-3, Mitigation Measure BIO-6, Mitigation Measure BIO-7, and Mitigation Measure BIO-8. Following the training, all construction personnel receiving the training shall sign a WEAP log to document their training. The WEAP training shall be repeated periodically as needed throughout construction so that all construction personnel are trained prior to starting work.
Mitigation Measure BIO-2 Project Site Delineation. Prior to the start of construction, the contractor shall clearly delineate the work areas (e.g., t-posts and
0.25-inch yellow nylon rope and temporary signage) in or adjacent to sensitive biological areas to provide clear limits to the extent of the work area. A qualified biologist shall confirm that the work areas are clearly delineated prior to work.
Mitigation Measure BIO-3 Additional Construction Site Housekeeping and Operational Requirements. The following measures will be implemented to avoid or minimize impacts on special-status species:
• No monofilament plastic (e.g., straw roll netting) shall be used for erosion control.
• All food-related trash items such as wrappers, cans, bottles, and food scraps shall be disposed of in securely closed containers and removed at least once a week from a construction or project site.
• Pets, such as dogs or cats, shall not be permitted on the project site.
• Use of rodenticides and herbicides in project site shall be restricted. This is necessary to prevent primary or secondary poisoning of native predators (e.g., western burrowing owl) and the depletion of prey populations on which they depend. All
S ANTA MARIA WWTP I MPROVEMENTS P ROJECT
S ANTA MARIA , C ALIFORNIA
INITIAL S TUDY C HECKLIST
S EPTEMBER 2026
4 P:\2024\20241463 CPZ Santa Maria WWTP\PRODUCTS\Initial Study\Final Draft\SantaMariaWWTP_ISMND.docx (09/25/26) -22 uses of such compounds shall observe label and other
restrictions mandated by the U.S. Environmental Protection Agency, California Department of Food and Agriculture, and other State and federal legislation. If rodent control must be conducted, zinc phosphide shall be used.
• Any nonnative plants removed during construction shall be contained and properly disposed of offsite.
• All mulch, topsoil, seed mixes, or other plantings used for erosion-control shall be free of invasive plant species seeds or propagules.
• No plant species listed on the California Invasive Plant Council (Cal-IPC) inventory shall be installed in the project site, and all plant palettes proposed to be installed on the project site(s) shall be reviewed and approved by a qualified biologist.
With implementation of Mitigation Measures BIO-1 through BIO-3, in conjunction with the species-specific measures described below, impacts to common and special-status wildlife species would be reduced to less than significant with mitigation, by ensuring that direct and indirect effects to special-status species are avoided during project construction.
As described above, based on a review of the species’ habitat requirements and the existing habitats on the site, it was determined that three special-status wildlife species could be impacted by the proposed project. These species are described further below.
Tricolored Blackbird. Tricolored blackbird is State listed as threatened, and colonial nesting sites are protected. This species is a resident of California and is found predominantly in the Central Valley and in coastal areas south of Sonoma County.
There are no CNDDB occurrences of tricolored blackbird in the project site or the vicinity. However, several eBird records have documented tricolored blackbird within the WWTP as recently as 2022 and as far back as 1991. The tricolored blackbird may forage and nest in agricultural fields; therefore, there is suitable habitat for this species. Conversion of existing agricultural fields to new percolation ponds could have the potential to directly and permanently impact habitat that could provide suitable foraging and nesting habitat for this species. The proposed project may also result in temporary indirect impacts to this species during construction as a result of increased noise and construction activities. Therefore, it is recommended that vegetation clearing be timed to occur outside of the breeding season for tricolored blackbird. The breeding season typically starts on February 1 and extends through September 15. If the breeding season cannot be avoided, project construction could result in significant impacts to tricolored blackbird. In the event that construction is planned during the breeding season, implementation of Mitigation Measure BIO-4 would be required to reduce impacts to less than significant.